Wednesday, 22, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Shree Sai Enterprises vs Mahanagar Telephone Nigam Ltd. ...
2007 Latest Caselaw 437 Bom

Citation : 2007 Latest Caselaw 437 Bom
Judgement Date : 21 April, 2007

Bombay High Court
Shree Sai Enterprises vs Mahanagar Telephone Nigam Ltd. ... on 21 April, 2007
Equivalent citations: 2007 (4) MhLj 469
Author: A V Mohta
Bench: A V Mohta

JUDGMENT

Anoop V. Mohta, J.

1. By these petitions both the parties have the challenge the second award dated 29.07.2006 passed by the sole Arbitrator Shri S.V. Joshi between the parties arising out of the same contract.

2. As disputes arose in reference to construction of underground cable duct at Rabale-Thane-Cherai (I)/NB-01/1203/08/08.11.1996, the matter was referred to an Arbitrator one Shri D.N. Joshi. By an award dated 21.07.2002, after considering the rival contentions and material placed on record by the parties, out of total claims, the Arbitrator had awarded the following claims:

---------------------------------------------------------------------------------

S.   Claim for                           Amount claimed           Amount awarded
No.

---------------------------------------------------------------------------------

1.  Amount towards final 
    bill                                    2,47,458               2,47,300.00 
     - Details as above. 
2.  Payment for threaded 4,128.00                                      Nil 
    sockets - claim on the 
    basis of alleged payments 
    to other contractors not 
    acceptable. 
3.  Refund for works 
    Contract tax                           26,853.00                 26,853.00
     - Respondents have not 
     made any payments on 
     behalf of the claimants. 
4.  With held amount for 
    not submitting labour 
    licence.                               10,000.00                 10,000.00 
     - No payments made by 
     Respondents. 
5.  Interest for reduced 
    payment at part rate 15,621.00                                      Nil 
     - Not justified. 
6.  Interest on S.D. 
     - Not justified                       17,159.00                    Nil 
7.  Security Deposit                     2,85.980.00                 2,85,980.00 
     - Claim for refund of 
     security deposit is justified. 
8.  Interest on final bill 
     - Not justified                       14,848.00                    Nil
9.  Escalation based on 
    average indices                      6,88,770.00                    Nil
     - The contract has no 
     provision for payment of 
     escalation and details of 
     increase claimed on ad hoc 
     basis. Not justified. 
10. Payment for renewal of 6,000.00 
    bank guarantee.                                                     Nil
      - Not justified.
11. Compensation at 3% on the 
    cost of an account of idle 
    overheads etc.                       15,82,339.00                   Nil 
     - Not justified. 
     Additional claims no.12 to 15 
     made by the claimants are for 
     interest and are not justified. Nil 
     Prayers a to d made by the 
     claimants in their claim statement 
     (page 76 and 77) seek declaratory 
     award and are rejected. 
     No amounts are awarded in response 
     to prayers e to h. 

---------------------------------------------------------------------------------

Total Award Rs. 5,70,133.00

---------------------------------------------------------------------------------

Counter claims of Respondent (referred on 3.6.02

---------------------------------------------------------------------------------

S.   Claim for                           Amount claimed           Amt. awarded
No.

---------------------------------------------------------------------------------

1.  Work done at Claimants 
    risk and cost                           24,219.00                10,314.00 
     - Portion of cost for 
     carrying out test only 
     justified. 
2.  Payment R.I. Charges to 
    NMMC to repair damaged 
    duct.                                   43,125.00                   Nil
     - Claim not justified 
     and established. 

---------------------------------------------------------------------------------

Total award for counter claim : Rs. 10,314.00

---------------------------------------------------------------------------------

Net amount to be paid by the Respondents to the claimants is (Rs.5,70,133-Rs.10,314.00) Rs. 5,59,819.00 Costs of Arbitration are awarded to the claimants at Rs. 30,000/-making the total amount of award as Rs. 5,89,819.00."

2. The Arbitrator has also rejected the counter claim filed by the Mahanagar Telephone Nigam Limited (for short, "MTNL") in Arbitration Petition No. 417/2006 and the petitioner in Arbitration Petition No. 433/2006. The petitioner in Arbitration Petition No. 417/2006 who is respondent in Arbitration Petition No. 433/2006 is the contractor in question (for short, "the Contractor") who, being aggrieved by the same has challenged the award by Arbitration Petition No. 205/2003. MTNL admittedly made no challenge to the first award (for short, "the first award"). This Court, after considering the rival contentions and submissions raised by the parties as challenge was restricted to two items viz. (i) award of Rs. 10,314/-to the respondents against counter claim made by the respondents and (ii) rejection of the claim of the petitioners for compensation at 3% of the cost on account of idle overheads, allowed the petition of the contractor, in the following words:

In the result, petition succeeds in part, the award impugned in the petition to the extent of awarding Rs. 10,314/- in favour of the Respondents and rejecting the claim of the Petitioners for compensation at the rate of 3% of the cost on account of idle machinery etc. is set aside. The Award is modified to the extent above. Petition is disposed off. The Respondents are directed to pay cost of this petition to the Petitioners as incurred by the Petitioners

3. MTNL in view of this appointed one Shri S.V. Joshi (second Arbitrator) to decide, make & modify the award as shown in the statement enclosed subject to admissibility under Clause 25 of the agreement with a condition that the Arbitrator should give reasons for the award.

4. The agreed terms of reference/claims were as under:

-----------------------------------------------------------------

Sr.  Brief Details of claims       Amount            Remarks
No.

-----------------------------------------------------------------

1.   Whether the claimant is    Rs. 15,82,339/-     Arbitrator
     entitled to receive                            to     decide
     compensation at 3% of the                      whether claim
     cost on account of idle                        is  justified
     overheads etc.                                 and  to  what
                                                    extent.

-----------------------------------------------------------------

5. The matter was need to be reheard on the point of reference only. However, by an impugned award dated 29.7.2006 the Second Arbitrator has exceeded its jurisdiction and awarded various claims as agitated by the contractor and as referred in the first award. The law is settled that Arbitrator cannot go beyond the point of reference. In the present case, admittedly, the point of reference was well within the knowledge of the parties and in fact parties have acted upon and proceeded accordingly. The second Arbitrator, therefore, as there was no consent given by the MTNL to allow the contractor to raise all other points, could not have answered or agitated or allowed to agitate other points/other claims.

6. In view of this settled principle, I am not inclined to entertain the submission of the Constituted Attorney of the contractor who is appearing in person that by the impugned order dated 20.1.2005 in Arbitration Petition No. 205/2003 passed by this Court, all the points have been kept open or permitted to reagitate. There is nothing of that sort mentioned in the said order. The parties themselves have in fact proceeded initially on the basis of points of reference as referred above. The submission therefore of the learned Counsel for MTNL is correct. I am acceding to the same. Therefore, the claim as awarded in the Second Award by the Second Arbitrator i.e. claim No. (I), Claim No. (II), Claim No. (III), Claim Nos. (III)(a to (d), Claim No. (IV), Claim No. (V) in party, Claim No. (VII) and Claim No. (VIII) are rejected as the same are beyond the scope and power of the Arbitrator to proceed with.

7. There is no dispute that all these items as claimed and decided by the first Arbitrator, were subject matter of the Arbitration Petition No. 205/2003. There is no question of re-agitating the same issue even on facts as well as on law of resjudicata as submitted by the learned Counsel for the MTNL.

8. The Apex Court has time and again reiterated the power and scope of the Arbitrator. The Supreme Court has reiterated that the Arbitrator cannot enlarge the scope of the reference. In the present case, the point of reference was never agreed to be enlarged by the parties. The Arbitrator therefore should not have gone beyond the point of reference. ( Orissa Mining Corporation Ltd. v. Prannath Vishwanath Rawley and Union of India v. G.S. Atwal & Company). The parties were fully aware of the scope of controversy in view of the reference. Therefore, the Arbitrator has determined the issues which were beyond the scope of the reference to the arbitration. The Supreme Court in McDermott International Inc. v. Burn Standard Co. Ltd. and Ors. (2006) 11 SCC 181 in para 59 and in Centrotrade Minerals & Metals Inc. v. Hindustan Copper Ltd. (2006) 11 SCC 245 in para 103 observed as under:

103. ...Where the arbitrator, however, has gone contrary to or beyond the expressed law of the contract or granted relief in the matter not in dispute would come within the purview of Section 34 of the Act.

The Supreme Court in Md. Army Welfare Housing Organisation v. Sumangal Services (P) Ltd. , in paragraphs 72, 73 and 74 observed as under:

72. This Court cannot sit in appeal over the award of the arbitrator but can certainly interfere when the award suffers from non-application of mind or when a relevant fact is ignored or an irrelevant fact not germane for deciding the dispute is taken into consideration.

73. Where an order has been passed without jurisdiction, the principles of estoppel, waiver and acquiescence will have no application. There is no estoppel against a statute.

74. The award, therefore, suffers from legal misconduct on the part of the arbitrators.

9. In view of this, I am inclined to modify the award. All the claims as awarded by the Second Arbitrator are quashed and set aside except the award on the point of reference.

10. In so far as the point of reference is concerned, the Arbitrator has considered the rival submissions made by the parties and by giving following reasons granted a total amount of Rs. 2,46,150/- towards this claim i.e. idle machinery and idle overheads.

Arguments for idle overheads and idle machinery:

The claimant contractor claims Rs. 9 lakhs for the extended period of 36 months after the stipulated date of completion was over. This Rs. 9 lakhs is claimed under the title as office establishment expenses, office staff salary, telephone, electric bills, transport expenses, site office with chowkidar and rent of the place, supervisor, engineers and movement from office to site. This claim also includes idle machinery cost of compressor with double barrel gun with operator and helper, concrete mixture with operator 2 dewatering pumps and a vibrator brought on the site for 7 times additionally and were send back without doing work because of non availability of site. The Respondent had not objected in the High Court as well as in this proceeding for this.

Finding : Partly justified.

Reasons:-(A) For IDLE MACHINERY

Though the Claimant has raised the claim for 36 months considering the actual working time, period of fair working season, mitigation of losses the maximum period of claims cannot be more than two months ie. 60 days.

The Transportation of machinery required is to be taken as approximately 6 times.

Rental for the idle machinery is considered as follows:

 (i)   Compressor with double barrel gun, operator
      and helper                                             Rs. 450/-per day 
(ii)  Concrete mixture with operator-Rs.250/- per day 
(iii) Dewatering pumps 2 Nos. @ Rs. 50/- per No./per day.    Rs. 100/-per day 
(iv)  Vibrator 2 Nos. @ Rs. 25/- per No./Per day.            Rs. 50/-per day 
                              Total per day :                Rs. 850/-per day
Transportation of these rental machinery from the place
of its original to work place Rs. 800/- per trip.
Therefore the total amount works out to be Rs. 850/- per
 day x 60 days.                                              Rs. 51,000/-
Transportation Rs. 800/- x 6 times.                          Rs.  4,800/-
                                                             ------------ 
Therefore the Award Sum                                      Rs. 55,800/-.
                                                             ------------ 
 

(B) Idle Over Heads:
 

The idle overheads for site office and land on rent for keeping material and machines are considered as follows for 27 months.

2 watchmen for day night for security of pipes, cement, steel, spacers, idle machinery for total extended period of 27 months ie. beyond 8/2/98 (on page No. 11).

 2 watchmen salary          Rs. 3500 per month totally
Land site                  Rs. 1000 per month,
Part time Supervisor -Nil in view of principle of
                           mitigation of losses.
Totally                    Rs. 3500 per month.
Findings: Partly justified.
Rs. 4500 per month x 27 months= 1,21,500/-
Therefore the Award sum: Rs. 1,21,500/-.
Therefore Total Award Sum for claim No. VI-
= 68,850 + 55.800 + 1,21,500 = Rs. 2,46,150/-.
 

11. After hearing both the parties, I am also of the view that the amount so awarded by the Second Arbitrator is just, proper and reasonable. Considering the facts and circumstances of the case, the reasoning as given cannot be said to be perverse or bad in law. The Award, therefore, sofar as the points of reference is concerned need to be maintained. The amount as awarded therefore need no interference.

12. The learned Counsel appearing for the MTNL submitted that in fact they have raised various challenges and even claim damages against the contractor. Admittedly they had not challenged the first award. The submission in respect of other claims as granted second time by second Arbitrator are beyond the jurisdiction and scope of the reference is accepted. The restricted challenge made on that count by the MTNL is well founded. The counter claim of the MTNL in this background is rejected.

13. The Arbitrator, after considering the submission as raised by the contractor based on various judgments cited by the contractor granted simple interest in the following terms. The interest as awarded is reasonable and fair.

- - - -

b) Simple interest of 8% P.A. is allowed in favour of Claimant on the amount awarded for claim (No. III c, IV, VII and VI) with effect from 21.09.2002 (from the date of the award by the previous Arbitrator upto the date of making and publishing the award as on today dt.29.07.2006.

Respondents shall pay sum of award as above to the Claimant within the period of 30 days with 8% interest P.A. till the realization of payment failing which 12% per annum interest (simple) is allowed on the sum awarded with effect from date of making and publishing the award till the date of realization of payment.

14. It is made clear that in view of the other reasoning, the contractor is entitled to claim interest as ordered above only on the idle overheads and idle machinery as awarded. The award of interest is restricted and granted accordingly. The contractor is not entitled for any interest on other claims.

15. The impugned award above extent. Both the petitions are disposed of accordingly. There shall be no order as to costs. is modified accordingly to the

C.C. expedited.

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 
 
Latestlaws Newsletter