Saturday, 09, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

The Project Director vs K Praveen Babu
2024 Latest Caselaw 8767 AP

Citation : 2024 Latest Caselaw 8767 AP
Judgement Date : 23 September, 2024

Andhra Pradesh High Court - Amravati

The Project Director vs K Praveen Babu on 23 September, 2024

Author: R Raghunandan Rao

Bench: R Raghunandan Rao

APHC010310382024
                   IN THE HIGH COURT OF ANDHRA PRADESH
                                 AT AMARAVATI                 [3488]
                          (Special Original Jurisdiction)

           MONDAY, THE TWENTY THIRD DAY OF SEPTEMBER
                TWO THOUSAND AND TWENTY FOUR

                               PRESENT

        THE HONOURABLE SRI JUSTICE R RAGHUNANDAN RAO

               THE HONOURABLE SRI JUSTICE HARINATH.N

    CIVIL REVISION PETITION Nos: 1593, 1656, 1661 & 1662 of 2024

C.R.P. No.1593 of 2024

Between:

The Project Director                                  ...PETITIONER

                                    AND

K Praveen Babu and Others                         ...RESPONDENT(S)

C.R.P. No.1656 of 2024

Between:

The Project Director ...PETITIONER

AND

K Vijaya Bhaskar Reddy and Others ...RESPONDENT(S)

C.R.P. No.1661 of 2024

Between:

The Project Director ...PETITIONER

AND

K Mohanrami Reddy and Others ...RESPONDENT(S)

RRR, J & HN, J C.R.P.Nos.1593 of 2024 & batch

Between:

The Project Director, ...PETITIONER

AND

K Chandrasekhar Reddy and Others ...RESPONDENT(S)

Counsel for the Petitioner:

1. S S VARMA (SC FOR NHAI)

Counsel for the Respondent(S):

1. MUNI REDDY PERURU

The Court made the following common order:

(per Hon'ble Sri Justice R Raghunandan Rao)

As all these Civil Revision Petitions arise out of the same issue, they

are being disposed of by way of this common order.

2. In all these cases, the petitioner herein had sought to challenge

the arbitral award passed by the Learned Principal District Judge, Chittoor,

under Section 34 of the Arbitration and Conciliation Act, 1996.

3. In all these cases, the period of 90 days for approaching the

District Court, after receipt of the award, had elapsed prior to the Summer

Vacation, 2023. The subsequent 30 days period, which could be condoned by

the Learned District Judge, had elapsed during the Summer Vacation, 2023.

The petitioner had filed an appeal under Section 34, on the reopening day

after the said Summer Vacation.

RRR, J & HN, J C.R.P.Nos.1593 of 2024 & batch

4. The period of delay in each of these cases is different. However,

the fact remains that the 90 days period, for filing the appeal, in all the cases,

had elapsed before the Court had closed for the Summer Vacation and the 30

days period had lapsed during the Summer Vacation.

5. The Learned Principal District Judge, Chittoor, by way of separate

orders, dated 28.03.2024, had dismissed the Interlocutory Applications filed

for condoning the delay, under Section 34 (3) of the Arbitration and

Conciliation Act, 1996, on the ground that the period for filing the appeal had

lapsed and there was no power for the Court to condone such delay.

6. Aggrieved by these orders, the petitioner has approached this

Court, by way of the present Civil Revision Petitions.

7. Sri S .S. Varma, learned counsel appearing for the petitioner

would submit that though the 30 days period, for which the Learned Principal

District Judge has power to condone the delay, had lapsed during the

Summer Vacation, the Learned Judge ought to have given the benefit under

Section 4 of the Limitation Act, 1963, to the petitioner as the petitioner had

approached the Court on the reopening day.

8. Sri O. Manohar Reddy, learned Senior Counsel appearing for the

private respondents, in all these cases, relies upon the Judgment of the

RRR, J & HN, J C.R.P.Nos.1593 of 2024 & batch

Hon'ble Supreme Court of India in the case of State of West Bengal vs.

Rajpath Contractors and Engineers Limited1 .

9. Paragraph 12 of the said Judgment covers the entire issue as the

said paragraph reads as follows:

"12. In the facts of the case in hand, the three months provided by way of limitation expired a day before the commencement of the pooja vacation, which commenced on 01.10.2022. Thus, the prescribed period within the meaning of Section 4 of the Limitation Act ended on 30.09.2022. Therefore, the appellants were not entitled to take benefit of Section 4 of the Limitation Act. As per the proviso to sub-section (3) of Section 34, the period of limitation could have been extended by a maximum period of 30 days. The maximum period of 30 days expired on 30.10.2022. As noted earlier, the petition was filed on 31.10.2022."

10. In view of the aforesaid finding of the Hon'ble Supreme Court, the

petitioner would not be entitled to the benefit of Section 4 of the Limitation Act,

1963, in the present case.

11. Accordingly, the present Civil Revision Petitions are dismissed.

There shall be no order as to costs.

(2024) 7 SCC 257

RRR, J & HN, J C.R.P.Nos.1593 of 2024 & batch

As a sequel, interlocutory applications pending, if any shall stand

closed.

_______________________ R RAGHUNANDAN RAO, J

______________ HARINATH.N, J MJA

RRR, J & HN, J C.R.P.Nos.1593 of 2024 & batch

THE HONOURABLE SRI JUSTICE R RAGHUNANDAN RAO

THE HONOURABLE SRI JUSTICE HARINATH.N

CIVIL REVISION PETITION Nos: 1593, 1656, 1661 & 1662 of 2024 (per Hon'ble Sri Justice R Raghunandan Rao)

23.09.2024

MJA

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter