Citation : 2023 Latest Caselaw 479 AP
Judgement Date : 30 January, 2023
1
HON'BLE SRI JUSTICE D.V.S.S.SOMAYAJULU
WRIT PETITION No.30004 of 2013
ORDER:
This Writ Petition is filed for the following relief:
".....to issue a Writ of Mandamus, or any other appropriate writ, order or direction, to the respondents No.1 to 3 to assign the plot earmarked by the respondent NO.3, a physical extents of 25x19 in Sy.No.572/A1, 743/A2, of Kallur (V) & (M) vide proposal No.Rc.B/1195/Dt.17.09.2012 beside the gate of TTD for assign to the petitioners, as consequently direct the Respondent No.5 to accept the same as their earlier proposal through the D.O.Roc.in Prop.2/57869/76, Dt.21.04.2000 to adjust in the existing site for accommodate of allocation to the petitioners in sequence of the implementation of this Hon'ble Court's Judgments, as stated above to meets the ends of the justice and to pass such other order or orders as this Hon'ble Court may deems fit just and proper in the circumstances of the case."
2) This Court has heard the learned counsel for the
petitioners, the learned Government Pleader for Assignments
and the learned standing counsel for Tirumala Tirupati
Devasthanam.
3) This is a case with a long and chequered history. The
petitioners before this Court have claimed relief on the basis of
their long and settled possession of the property. Learned
counsel for the petitioners points out that initially the Writ
Petition No.5643 of 1977 was filed by the petitioners'
predecessors in title along with others. It is held in that case
vide orders dated 09.11.1979 that Ac.0-64 cents in
Sy.Nos.742/A2 and 572/A2 of Kurnool Town be separated from
the property allotted to TTD Kalayanamandapam and it was
decided that Ac.0-64 cents should be allotted to the hut
dwellers. It is also pointed out that subsequently suit in
O.S.No.293 of 1995 was also filed against the District Collector
and others for permanent injunction by the petitioners'
predecessors. The order passed in W.P.No.5643 of 1977 was
also considered and a permanent injunction was granted to the
plaintiff therein. An appeal in A.S.No.36 of 1998 was also
decreed in favour of the appellant/plaintiff overruling the
objection of the Revenue. A second appeal in S.A.No.1287 of
2003 was also filed against the order of the First Appellate
Court and in S.A.No.1287 of 2003 a direction was given to the
plaintiff therein and her legal heirs to make an application to
the District Collector for allotment of the site and District
Collector was directed to consider the same on its own merits.
This order was passed on 12.10.2011. Thereafter a
representation was made by the present writ petitioners in
2012, which is sent to Tahsildar by the District Collector. The
Tahsildar in turn gave an endorsement dated 17.09.2012 for
allotment of a site. This recommendation of the Tahsildar,
dated 17.09.2012, is sought to be enforced through a
Mandamus in this Writ Petition. Learned counsel points out
that a site has been located and despite the success of the
petitioners and their predecessors in the earlier long litigation
the allotment was not made in favour of the petitioners.
Therefore, learned counsel submits that the petitioners are
entitled to an order as prayed for, since the availability of site
has been borne out by the record including the
recommendation dated 17.09.2012. It is pointed out that the
consent for allotment is been unnecessarily withheld and that
too without reasons. So the petitioners pray for an order.
4) For the respondents first arguments are advanced by the
learned Government Pleader for Assignment. It is asserted that
while there is no dispute about the earlier litigation, the
occupation of site by the petitioners' predecessors in title etc., it
is pointed out that the entire site of Ac.1-72 cents it was given
to the TTD for construction of Kalyanamandapam. With regard
to the balance site of Ac.0-64 cents it was allotted to 27
members, but the petitioners' predecessor in title is not a part
of 27 members. It is also pointed out that the recommendation
dated 17.09.2012, on which the petitioners relying, states that
the site is within the premises of the TTD and is next to the
gate. Therefore, the consent of the TTD is necessary to allot the
plot in favour of the writ petitioners. The land in question is
also under the possession of the TTD. This was informed to the
writ petitioners and two alternative sites were proposed to allot
a site to the petitioners. One is a plot in Sy.No.217 of Kalluru
village and a further plot in Sy.No.780/8B/J in Sudda Vagu
village. Therefore, it is submitted that it is not possible to allot
the site recommended by the Tahsildar without the consent of
the TTD.
5) For the TTD also learned standing counsel argued the
matter. It is reiterated that for the allotment of Ac.0.64 cents
27 beneficiaries were identified and land was allotted to them.
The petitioners' predecessor did not find a place in the said list.
The TTD had noticed that allotment of site next to the actual
area allotted to the TTD was resulting in unlawful activity being
carried out like consuming liquor etc., within the area and,
therefore, the TTD wanted to construct a compound wall
around the Kalayana Mandapam after eviction of the occupant.
It is also reiterated that the present site proposed to be allotted
to the petitioners is fully within the site that was earlier allotted
to the TTD. In that view of the matter, learned standing
counsel submits that the TTD cannot give its consent and the
petitioners should be called upon to choose one of the
alternative sites that have been identified under the Indiramma
Housing programme or otherwise. It is, therefore, submitted
that the petitioners cannot seek a mandamus.
6) This Court after considering all the submissions notices
that it is a fact that the petitioners' predecessor was recognized
as an occupier of a vacant site. It is also a fact that some of the
encroachers / occupiers were allotted house sites. The
petitioners' predecessor was not found to be in the list of 27
encroachers, who were allotted house sites. The petitioners'
predecessor pursued the legal remedies and ultimately in
S.A.No.1287 of 2003 a learned Judge of this Court clearly held
that since the suit is only for a permanent injunction to protect
the possession of the property, the petitioners do not have a
right to claim for allotment of a particular site. He held that the
grievance on this account cannot be considered in the Second
Appeal as the suit is only for the permanent injunction.
Therefore, the learned single Judge dismissed the Second
Appeal but gave a liberty to the plaintiff to approach the
Government by making an application. The District Collector /
concerned authorities were directed to consider the request of
the plaintiff for allotment of site in view of the orders of this
High Court and also the allotment made to others. Pursuant
thereto a representation was made and it was considered. The
Tahsildar found that there is a bit of site which is available near
the plots allotted, but next to the gate. The Tahsildar, however,
noticed that the site could be allotted only if the TTD authorities
consent to the same. This Court notices that the proposal
made by the Tahsildar himself in a letter dated 17.09.2012
clearly shows that the site proposed to be allotted is within the
premises of the TTD. The TTD has gone on record stating that
it s not possible to provide the site within the compound wall of
TTD Kalyana Mandapam. The plot suggested for allotment by
the Tahsildar is within the extent of Ac.1-72 cents alienated to
the TTD. It is also pointed out that there is an issue about the
antisocial elements using the said plot during the night time
and spoiling the premises by consuming liquor etc. Therefore,
TTD has taken a stand that it is not possible to give consent for
allotment of particular site. The TTD also relies upon the fact
that Plot No.433 near Dal Mill, Kurnool-Bellary road is capable
of allotment to the petitioners under Indiramma Urban Housing
Scheme. To the same effect is the counter affidavit filed by the
State. It is reiterated that in 2008 itself a Plot No.433 near Dal
Mill, Kurnool is allotted for the petitioners' predecessor. This is
reiterated in Tahsildar's endorsement on 19.03.2013, wherein
the writ petitioner was directed to approach the Tahsildar,
Kalluru, with regard to allotment of Plot No.433 near Dal Mill,
Kurnool. It is also clearly reiterated that the allotment of site
within the compound of the TTD is not feasible.
7) This Court is also of the opinion that it has to concur with
what is argued by the learned counsel for the respondents that
the mandamus is a discretionary remedy. The petitioners
should have a right and there should be a corresponding
violation on the part of the respondents of that right. Then the
Court can issue a mandamus directing the respondents to do
the needful. In the case on hand, the petitioners do not have a
"right" as is recognized under law for the particular plot of land
recommended in the Tahsildar's letter dated 17.09.2012. The
recommendation itself states that the consent of the TTD is
necessary. The consent of the TTD has not been given for the
said plot of land. On the other hand, both the TTD and the
revenue authorities clearly state that the petitioners are entitled
for an alternative bit of land but not the exact bit of land which
they claim. The Tahsildar, Kalluru, in the course of his counter
affidavit in paragraph 11 and 12 is clearly admitted that two
bits of land are available for allotment as on the date of filing of
the counter viz., Ac.0-02 cents in Sy.No.217 of Kalluru village
under Indiramma Urban Housing Scheme or a bit of Ac.0-02
cents of Sy.No.781/J of Sudda vagu of Kalluru village, for the
second plot of land the permission of Municipal Corporation of
Kurnool is necessary.
8) In this view of the matter, it is held that the petitioners do
not have a right that can be enforced through a mandamus,
leaving it open to the petitioners to take up the offer made by
the revenue authorities and as specified in paragraphs 11 and
12 of the counter affidavit. If the petitioners are interested in
seeking allotment of the land of Ac.0-02 cents in
Sy.No.217/Kalluru village or Sy.No.781/J of Sudda Vagu of
Kallur Village as mentioned in paragraphs 11 and 12 of the
counter, they should make an application for the same within
two weeks from the date of receipt of a copy of this Court. The
respondents are directed to process the said application, if it is
otherwise in accordance with law, within a further period of two
weeks and decide on the same as per law and on its merits
only. It is made clear that the petitioners are not entitled to a
mandamus with regard to the specific plot of land that is
mentioned in the Tahsildar's letter dated 17.09.2012 in
Rc.B/1195, besides the TTD gate.
9) With the above observations the Writ Petition is disposed
of. There shall be no order as to costs. Consequently,
Miscellaneous Applications pending, if any, shall also stand
dismissed.
__________________________ D.V.S.S.SOMAYAJULU, J Date:30.01.2023.
Ssv
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!