Citation : 2023 Latest Caselaw 6141 AP
Judgement Date : 26 December, 2023
IN THE HIGH COURT OF ANDHRA PRADESH : AMARAVATI HON'BLE MR. JUSTICE DHIRAJ SINGH THAKUR, CHIEF JUSTICE & HON'BLE MR. JUSTICE R.RAGHUNANDAN RAO WRIT APPEAL No.1170 of 2023 The Project Director, National Highways Authority of India, Project Implementation Unit, Plot Nos.149 and 150, KVR Estate, Koradapet Chellur Junction, Vizianagaram -- 535 004. .. Appellant Vs. M/s. Vijayanagaram Hatcheries Pvt. Ltd., Represented by its Authorized Signatory K.Srinivas Reddy, Aged about 48 years, R/o.54-1-9, 4% Floor, Dr.N.G.R's Lotus Plaza, Isukathota, Visakhapatnam - 530 0&8 and 5 others ... Respondents
Counsel forthe Appellant : Mr. Padma Rao G. 8S. Lakkaraju
Counsel for the Respondents: Mr. G. Ramesh Babu - Rl Mr. Jupudi V. K. Yagnadutt, Deputy Solicitor General of India
-R2
Mr. 8S. 8S. Varma, Standing Counsel - Rd & R4
G.P. for Land Acquisition - R5 & R6
2 HCJ & RRR, J W.A.No.1170 of 2023
Dt.: 26.12.2025
PER DHTRAJ SINGH THAKUR, CJ (Oral):
The present writ appeal has been filed under Clause 15 of the Letters Patent against the Judgment and Order dated 13.09.2023
in W.P.No.144382 of 20238.
2. The case setup before the learned single Judge by the writ petitioner was that even when its land measuring one acre twenty one cents in Sy.No.336/1B and two acres and twenty four cents in Sy.No.336/2B belonging to the petitioner had been acquired by the National Highways Authority of India (Gin short 'NHAI') and compensation determined as per the Award No.135-1/28028, dated
10.08.2022, payment had not been released in its favour.
3. The case of the petitioner further was that the Award was challenged before the Arbitrator (the District Collector) in terms of Section 3G(5) of the National Highways Act, 1956, which came to be dismissed on 05.04.2022 and since the Award had been upheld and had attained finality, withholding the payment of compensation
was unjustified and illegal.
4. In the backdrop of the aforementioned claims, the learned single Judge, by virtue of the judgment and order impugned, on
being satisfied that there was no challenge to the Award, dated
3 HCJ & RRR, J
10.08.2022, which had attained finality "as on date", issued directions to deposit the compensation amount payable to the
petitioner as per the Award, dated 10.08.2088.
5. Learned counsel for the Appellant submitted that the petitioner had in fact not brought to the notice of the learned single Judge that the order passed by the Arbitrator (the District Collector) was already under challenge under Section 34 of the Arbitration and Conciliation Act, 1996, which was still pending adjudication. It was admitted that while a prayer for grant of interim relief had been made, yet no orders had been passed on the
same by the learned District Judge.
6. Apart from this, reliance has been placed upon judgment of the Hon'ble Supreme Court in the case of National Highways Authority of India Vs. Sheetal Jaidev Vade & Others!, to buttress the point that the Hon'ble Supreme Court had disapproved the entertainment of writ petitions under Article 226 of the Constitution of India for execution of Awards passed by the Arbitral Tribunal/Court, instead of relegating the judgment creditor to file
execution proceedings before the competent Executing Court.
*1(2022) SCC Online SC 1070]
4 HCJ & RRR, J
The aforementioned observations were made by the Apex Court in an appeal preferred against a judgment and order passed in exercise of powers under Article 226 of the Constitution of India directing the NHAI to deposit the entire compensation amount as awarded by the Arbitrator and thereafter permitting the original
land owners/writ petitioners to withdraw the said amount.
The Apex Court in paragraph 12 of the judgment had noted that the Award had been challenged by the NHAI by initiating proceedings under Section 34 of the Arbitration and Conciliation Act, 1996, which were reported to be pending and in those circumstances held that the High Court ought not to have entertained the writ petition under Article 226 of the Constitution of India for purposes of execution of the Award and that by issuing such directions, the High Court had virtually converted itself into
an Executing Court.
7. The facts of the present case are quite similar to the ones which were before the Apex Court in the case supra. Admittedly, the appellant herein had initiated the proceedings under Section 34 of the Arbitration and Conciliation Act, 1996, before the learned District Judge, which proceedings are still stated to be pending.
This fact, however, could not be brought to the notice of the learned
5 HCJ & RRR, J
single Judge by the NHAI on account of the fact that on the date when the judgment and order came to be passed, the appellant was
not represented.
8. Be that as it may, considering the ratio of the judgment discussed hereinabove, the judgment and order passed by the learned single Judge is unsustainable and is accordingly set aside leaving the parties to avail the remedies before the appropriate
forum. The writ appeal is, accordingly, disposed of. No costs.
Pending miscellaneous applications, if any, shall stand closed.
DHIRAJ SINGH THAKUR, CJ R.RAGHUNANDAN RAO, J kbs
6 HCJ & RRR, J
HON'BLE MR. JUSTICE DHIRAJ SINGH THAKUR, CHIEF JUSTICE
& HON'BLE MR. JUSTICE R.RAGHUNANDAN RAO
Dt: 26.12.2025
kbs
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!