ORDER:

The petitioner had been awarded the contracts for

construction of CC Road, Box Culvert in Chandrababu Nagar

colon, and CC Road, CC side Drain in Agraharapeta SC colony-

package No.1, under SSC Component (Earlier SCSP) Grant

2018-19 vide Agreement No.104/2018-19, dated 29.12.2018.

After execution of the said works, a final bill for Rs.92,19,872/-

had been prepared on the basis of Measurement Books and

submitted to the concerned for payment. As the payment of the

said amount has not been made by the respondents, the

petitioner has approached this Court, by way of this writ

petition.

2. It is the contention of the petitioner that even

though the respondents admitted that the petitioner is entitled

for payment of the aforesaid sums of money, no payment is

being made. The petitioner contends that such non-payment of

money is clearly arbitrary and high-handed requiring the

interference of this Court.

3. This Court, in various orders, including the

judgment of a learned Single Judge of this Court dated

05.10.2021 in W.P.No.10038 of 2021 and batch had taken the

view that such non-payment of dues is arbitrary and that such

dues need to be cleared by the respondents at the earliest.

4. Sri N.Ranga Reddy, learned standing counsel for

respondent No.6 submits that the respondent authorities are

verifying the claims of the petitioner and would be in a position

to make payments only after such verification is completed.

5. In view of the aforesaid directions of this Court in

various cases and after hearing the submissions of the learned

counsel for the petitioner, learned Government pleader for

Municipal Administration and Sri N.Ranga Reddy, learned

standing counsel for respondent No.6, this writ petition is

disposed of with a direction to the respondents to complete the

verification process within a period of three weeks. It is clarified

that in the event of the verification process not being completed

within the aforesaid period of three weeks, the respondents shall

pay the amounts due to the petitioner, without insisting upon

any further time for verification. It would also be open to the

petitioner to agitate his/her/their claim for interest, if any

payable by the respondents, in an appropriate forum. There

shall be no order as to costs.

As a sequel, pending miscellaneous petitions, if any, shall

stand closed.

____________________________ R. RAGHUNANDAN RAO, J.

25.07.2022 RJS

HON'BLE SRI JUSTICE R. RAGHUNANDAN RAO

WRIT PETITION No.18151 of 2022

25.07.2022

RJS

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter