M/S. Pinaki Infrastructures Private ... vs M/S. Vasishta Mantena Nh4 Jv

Citation : 2026 Latest Caselaw 237 Tel
Judgement Date : 1 April, 2026

[Cites 2, Cited by 0]

Telangana High Court

M/S. Pinaki Infrastructures Private ... vs M/S. Vasishta Mantena Nh4 Jv on 1 April, 2026

Author: P.Sam Koshy
Bench: P.Sam Koshy
     IN THE HIGH COURT FOR THE STATE OF TELANGANA
                     AT HYDERABAD

       THE HONOURABLE SRI JUSTICE P.SAM KOSHY

           ARBITRATION APPLICATION No.83 of 2025

                           DATE: 01.04.2026

Between:
M/s. Pinaki Infrastructure Private Limited.
                                                            ...Applicant
                                  AND

M/s. Vasishta Mantena NH4 JV.
                                                          ...Respondent


ORDER:

Heard Mr. Bhaskar Muthyala, learned counsel for the applicant; and Mr. Naumene Suraparaj Karlapalem, learned counsel for the respondent.

2. The instant Arbitration Application under Section 11 (5) & (6) of the Arbitration and Conciliation Act, 1996 (for short the 'Act') has been filed by the applicant seeking for appointment of an Arbitrator to adjudicate upon the disputes that have arisen between the applicant and Page 2 of 6 the respondent as per clause 16 of both the sub-contract agreements dated 07.01.2019.

3. The facts of the case in nutshell are that the applicant is a company incorporated under the provisions of Companies Act, 1956 and carries out a wide range of infrastructure and engineering activities. Its core business includes executing civil and electrical engineering projects such as construction of transmission and distribution lines, substations, and turnkey power projects and is also involved in manufacturing components for power infrastructure. The applicant company also has its business in renewable and conventional energy sectors (solar, wind, thermal, etc.), industrial electrification, and automation and also undertakes water infrastructure projects like dams, reservoirs, pipelines, and distribution systems. Further, the applicant company is also engaged in housing and development projects (independently or through joint ventures) and deals in generation, distribution, supply, import, export, and trading of electricity and energy-related products in various forms. On 07.01.2019 both the parties entered into two sub-contract agreements; one for construction / shifting of electrical utilities along Page 3 of 6 ongoing widening and construction work of NH-4 in Andaman and Nicobar Islands and rehabilitation and another for upgradation of section from Km 206.00 to Km 239.425 of NH-4 (total length 33.405 Km) of NH-4 to 2 lane with hard shoulder in the Union Territory in Andaman & Nicobar Islands on EPC basis.

4. Learned counsel for the applicant submits that quality work was carried out by the applicant until oral instructions were received from the respondent directing cessation of the work, for reasons best known to the respondent. It is further submitted that the applicant has raised invoices timely, but the respondent failed to clear the same in a time-bound manner and the applicant also approached the respondent to clear the same in time but the respondent failed in doing so.

5. It was submitted by the learned counsel for the applicant that in terms of clause 16 of the sub-contract agreements, dated 07.01.2019, the applicant sent a notice to the respondent for settlement of disputes by appointment of Mr. Mohammed Imran Khan, Senior Advocate as a sole Arbitrator, however the respondent rejected the said proposal stating that since they have failed in giving consent regarding appointment of Page 4 of 6 Mr. Mohammed Imran Khan, Senior Advocate as a sole Arbitrator, they do not intend to proceed with arbitration on the said terms.

6. On the other hand, the learned counsel for the respondent opposing the instant Arbitration Application submits that the respondent has never instructed the applicant to stop the work either orally or in writing. However, the learned counsel for the respondent does not dispute the existence of the arbitration clause in sub-contract agreements, dated 07.01.2019, which provides a mechanism for resolving disputes through the appointment of an Arbitrator.

7. Having heard the contentions put forth on either side and on perusal of records, undisputedly there is an arbitration clause in the agreement dated 07.01.2019to resolve the dispute by way of arbitration. It would be trite at this juncture to take note of the arbitration clause which is reflected in the agreement dated 07.01.2019. For ready reference, the arbitration clause i.e. clause 16 of the agreement dated 07.01.2019 is reproduced hereunder, viz., Page 5 of 6 "16. Arbitration:

Any dispute resulting from this agreement shall be settled amicably by mutual consultation. In the event if amicable settlement is not reached in any particular case, the dispute shall be referred to arbitration to a Sole Arbitrator to be mutually agreed by and between PIPL and the NH4 JV. The venue for arbitration shall be at Hyderabad and each party shall bear its expenses. The decision of the majority of the arbitrators shall be final and binding on both the parties. Subject to the above, the courts in the city of Hyderabad shall alone have jurisdiction to entertain any litigation relating to or arising out of this agreement."
8. A plain reading of the aforesaid clause makes it amply clear that any dispute arising out of or relating to the agreement, has to be resolved by way of negotiations and still if the dispute stands unresolved, the same has to be referred to arbitration. Furthermore, all the objections that the respondent have can be raised before the Arbitrator, which the Arbitrator is expected to take note of, and decide the same after hearing both the sides in accordance with law.
9. In the given factual circumstances of the case, this Court is inclined to appoint an arbitrator who shall in turn decide the grievances and the claims raised by the applicant. In the course of the deliberation, learned counsel for the parties accepted the suggestion of Hon'ble Sri Page 6 of 6 Justice P.Naveen Rao, former judge of this High Court to be appointed as an Arbitrator and adjudicate the claim raised by the applicant.

Accordingly, this Court appoints Hon'ble Sri Justice P.Naveen Rao, former Judge of this High Court (#3001, My Home Bhooja, Block-A, Plot Nos.22-24 & 31-33, Rayadurgam, Ranga Reddy District, Mobile No.8374012311) to act as an Arbitrator and to pass appropriate award in terms of the provisions of the Act. The venue of the arbitration shall be decided mutually by the parties subject to the consultation and agreement of the learned Arbitrator. The fees of the learned Arbitrator also be decided mutually by the parties again in consultation and agreement with the learned Arbitrator and the arbitration proceedings shall be governed in accordance with the provisions of the Act.

10. The instant Arbitration Application accordingly stands allowed.

11. As a sequel, miscellaneous petitions pending if any, shall stand closed. However, there shall be no order as to costs.

________________ P.SAM KOSHY, J Date: 01.04.2026 Note: Office to communicate a copy of this order to the learned Arbitrator.

(B/o)GSD