M/S. Sanyu Infra Projects Private ... vs The Union Of India And 6 Others

Citation : 2023 Latest Caselaw 1127 Tel
Judgement Date : 10 March, 2023

Telangana High Court
M/S. Sanyu Infra Projects Private ... vs The Union Of India And 6 Others on 10 March, 2023
Bench: Ujjal Bhuyan, N.Tukaramji
     THE HON'BLE THE CHIEF JUSTICE UJJAL BHUYAN
                         AND
        THE HON'BLE SRI JUSTICE N. TUKARAMJI

                 WRIT APPEAL No.303 of 2023

JUDGMENT: (Per the Hon'ble the Chief Justice Ujjal Bhuyan)


      Heard Mr. D.Prakash Reddy, learned Senior Counsel for

the appellant and Mr. Gadi Praveen Kumar, learned Deputy

Solicitor General of India for respondent Nos.1 to 6.


2.    This intra-court appeal is directed against the common

order dated 18.01.2023 passed by the learned Single Judge

dismissing writ petition No.23748 of 2022 and batch.


3.    The present appeal arises out of writ petition No.23753

of 2022.


4.    Appellant as the writ petitioner had filed the related writ

petition assailing the action of respondent No.4 in terminating

the contract work awarded to the appellant under Letter of

Acceptance dated 17.09.2021 and consequently, forfeiting the

bank guarantee.
                                     2



5.    Subject matter of the contract relates to construction of

Road under Bridge (RuB). Pursuant to a tender process,

appellant was awarded the contract and in this connection,

Letter of Acceptance was issued on 17.09.2021. Without

entering into the rival contentions, it is seen that there was

delay in the execution of the work. While according to the

appellant, the delay occurred because of respondent No.4 not

taking prompt action in signing the contract agreement and

subsequently in preparing and approving the drawings, on

the other hand, according to the respondents, the delay was

because of the appellant's failure to execute the work in a

time bound manner. Ultimately, respondents issued seven (7)

days notice followed by forty-eight (48) hours notice. It was

thereafter    that     the    contract   was    terminated       by   the

respondents.


6.    While according to the appellant, no notice was issued

and   no     hearing    was    granted   to    the   appellant    before

termination of the contract, it is the case of the respondents

that the termination notice was uploaded in the common

portal called Indian Railway- Works Contract Management
                                  3



System (IRWCMS). After terminating the contract of the

appellant, respondents forfeited the bank guarantee furnished

by the appellant. This led to filing of the writ petition.


7.    At the initial stage, interim order was passed by the

learned Single Judge directing the respondents not to award

contract for the balance work to third party contractors.


8.    Respondents in their vacate stay petition which was

treated as counter affidavit contested the very maintainability

of the writ petition. On merit, it was contended that there was

delay on the part of the appellant in executing the contract

which is of public importance. Therefore, respondents were

compelled to terminate the contract but before doing so,

adequate notice was granted to the appellant.


9.    Learned Single Judge held that though there is an

arbitration clause in the contract, yet the writ petition is

maintainable. In support of such conclusion, learned Single

Judge has placed reliance on several decisions of the

Supreme     Court.   However,     learned   Single   Judge   after

entertaining the writ petition as being maintainable went into
                                    4



the merit and held that appellant had failed to complete the

contract work within the agreed time. On notice, learned

Single Judge held as follows:

            35.   It is relevant to note that entire tender
      process and re-tendering process, submission of tender is
      online through respondent's e-mail ID. The aforesaid
      notices were placed in IRWMS site of the respondent
      Railways. However, the petitioner herein has filed copies
      of 7 days and 48 hours notice. Therefore, petitioner
      cannot contend that the said notices were not served on
      him. Therefore, according to this Court, there is no
      irregularity in terminating the aforesaid contracts by the
      respondents Railways and forfeiting the bank guarantee.


10.   Government of India in the Ministry of Railways

(Railway Board) has approved the new Indian Railways

Standard General Conditions of Contract, July 2020. While

Part I thereof lays down Regulations for Tenders and

Contracts, Part II provides for Standard General Conditions

of Contract. Clause 4 of the Standard General Conditions of

Contract reads as follows:

            4.    Communications to be in writing: All
      notices, communications, reference and complaints made
      by the Railway or the Engineer or the Engineer's
      Representative or the Contractor inter-se concerning the
      works shall be in writing or e-mail on registered e-mail
      IDs   and   no   notice,   communication,   reference   or
                                     5


       complaint not in writing or through e-mail, shall be
       recognized.



11.   From the above, it is seen that as per the Standard

General Conditions of Contract all communications are to be

in writing.     All notices, communications, reference and

complaints made by the Railways or the Engineer or the

Engineer's     Representative       or   the   Contractor     inter-se

concerning the works shall be in writing or e-mail on

registered e-mail IDs. No notice, communication, reference or

complaint     not    in   writing   or   through   e-mail   shall   be

recognized.


12.   In the writ affidavit, appellant specifically pleaded in

paragraph 9 that while it was waiting for approval of thrust-

bed drawings and alternate solution, it had received a call

from respondent No.4 on 02.05.2022 evening that it had been

served with 48 hour notices for several bridges.            Appellant

had addressed a letter on 06.05.2022 to respondent No.4 and

questioned illegal termination of contract without notice. In

paragraph 12, this was elaborated upon by the appellant by

stating that termination of contract and forfeiture of bank
                                      6



guarantee was without any notice and hearing and thus being

in violation of the principles of natural justice. Paragraphs 9

and 12 of the writ affidavit of the appellant reads as follows:

              9.    While so, we got a call from respondent No.4
       on 02.05.2022 evening that we have been served with 48
       hour notices for several bridges.          Immediately we
       addressed a detailed letter on 06.05.2022 stating that the
       work is in progress and requested for alternative steel
       design in place of 28 mm steel, and specifically stated
       that we did not receive any notice from them since
       01.04.2022, much less 48 hours notice, and requested to
       revoke the termination of contract, if initiated.

              ***

12. I submit that termination of contract and forfeiture of the BG by the respondent No.5, without issuing any notice and without any fault on the part of our company, is totally illegal, arbitrary and high handed and in violation of principles of natural justice and Article 19(1)(g) of Constitution of India. Due to such forfeiture and abrupt terminations of contracts, the Company went to deep financial crisis and unable to pay the vendors and meet the salaries of the workmen who are already deployed at the respective work sites and also huge material procedure at the work sites is at risk. 7

13. This was contested by the respondents in their application for vacate stay which was treated as the counter affidavit by stating as follows:

7. In reply to paras 1 to 3 of the petitioner affidavit filed in support of above writ petition, it is to submit that all the notices have been sent to the petitioner ID in Indian Railway - Works Contract Management System (IR-WCMS) (online platform for making agreements, recording bills, paying bills, granting extension of currency, issuing notices, etc.). The petitioner having participated in the tender and after getting the Letter of Acceptance is supposed to get all the agreements, bills, variation, currency extensions, etc., in Indian Railway - Works Contract Management System. The maintenance of their account, correctness of information being furnished is their responsibility and is as per Clause 6 of Annexure-V of General Conditions of Contract (GCC) submitted by the Tenderer at the time of participation in the said tender.

14. From the above, it is seen that stand taken by the respondents was that all notices were uploaded on IRWCMS i.e., the online platform. Appellant having participated in the tender and after obtaining Letter of Acceptance was supposed to get all agreements, bills, extensions etc., through the aforesaid online portal; it is the responsibility of the appellant to obtain such information.

8

15. Learned Single Judge observed that the termination notice was placed in the IRWCMS site. Appellant had filed copies of seven (7) days and forty-eight (48) hours notice which were issued prior thereto and therefore, appellant cannot contend that the said notices were not served upon the appellant. Learned Single Judge held that there was no irregularity in terminating the aforesaid contract by the respondents.

16. Before we proceed to deal with the above conclusion of the learned Single Judge, our attention has also been drawn to clause 64 of the Standard General Conditions of Contract which provides for arbitration. It is another matter that learned Single Judge has held the writ petition to be maintainable notwithstanding availability of the remedy of arbitration. Having entertained the writ petition, we are of the view that learned Single Judge instead of entering into the merit as to the justification for cancellation of contract, ought to have confined the deliberation to the decision making process. After all, judicial review is primarily concerned with the decision making process and not with the decision per se. 9 If the writ court feels that the decision making process is vitiated by non-compliance to the procedural requirements and violation of the principles of natural justice etc., certainly a writ court would be entitled to entertain a writ petition in exercise of its power of judicial review notwithstanding availability of alternative remedy. When clause 4 of the Standard General Conditions of Contract clearly provides that all notices, communications etc., should be in writing or on registered e-mail IDs, it means that the notices would have to be sent to the affected party in writing or to the registered e- mail ID of the affected party. Otherwise, clause 4 would have mentioned that such a notice would be uploaded or posted in IRWCMS portal. That having not been done, we are of the view that there is violation of the principles of natural justice inasmuch as due notice and adequate opportunity of hearing was not granted to the appellant before cancellation of contract.

17. Having said that we are of the view that appellant should be relegated to the forum of respondent No.4. Now that appellant is aware of the reasons for termination of 10 contract, let the appellant appear before respondent No.4 on 20.03.2023 at 11.00 am whereafter respondent No.4 shall take a fresh decision in accordance with law. All contentions are kept open. Needless to say, if the appellant is aggrieved by any decision that may be taken by respondent No.4, it will be open to the appellant to avail the remedy as provided in clause 64 of the Standard General Conditions of Contract.

18. This disposes of the writ appeal. However, there shall be no order as to costs.

Miscellaneous applications pending, if any, shall stand closed.

_______________________ UJJAL BHUYAN, CJ ______________________ N.TUKARAMJI, J 10.03.2023 vs