1
PNR,J& JSR,J
COMCA.No.34 OF 2022
HONOURABLE SRI JUSTICE P. NAVEEN RAO
AND
HONOURABLE SRI JUSTICE J. SREENIVAS RAO
COMCA.No.34 OF 2022
Date: 10.02.2023
Between:
M/s Sree Durga Estates
A registered Partnership Firm
With Registration No.2148/2011
Rep. By its Managing Partner
Boppana Ramesh, S/o. Sri Sai Chowdhary
R/o. Villa No.006, Indu Fortune Fields,
13th Phase KPHB Colony,
Kukatpally Hyderabad.
.....Appellant
And
J.A.S. Padmaja, W/o. J. Venkata Ramudu
Aged about 59 years, Occ : Housewife
R/o. Villa No.1018, Mallikarjuna Krinss Villa
Sy.Nos.282 & 283, Puppalaguda Village,
Gandipet Mandal, Ranga Reddy District
And 7 others
.....Respondents
The Court made the following:
2
PNR,J& JSR,J
COMCA.No.34 OF 2022
HONOURABLE SRI JUSTICE P. NAVEEN RAO
AND
HONOURABLE SRI JUSTICE J. SREENIVAS RAO
COMCA.No.34 OF 2022
JUDGMENT:{Per the Hon'ble Sri Justice J. Sreenivas Rao}
The appellant filed this COMCA No.34 of 2022 under Section
13 of the Commercial Courts Act, 2015 R/w Section 37 of the
Arbitration and Conciliation Act 1996 (hereinafter referred to as 'the
Act, 1996') aggrieved by the order dated 12-09-2022 passed by the
learned Special Judgefor Trial and Disposal of Commercial Disputes
Court, Ranga Reddy District at L.B. Nagar in C.O.P. No.3 of 2022.
2. For the sake of convenience, hereinafter the parties will be
referred to as "petitioner" and "respondents", as they were arrayed
before the trial Court.
3. That the respondents in COP No.3 of 2022 are the absolute
owners of the land admeasuring to an extent of Acs.5.02 guntas in
Sy.Nos.128 and 132 situated at Bachupally Village, Quthbullapur
Mandal, Ranga Reddy District. Petitioner and respondents have
entered into registered Development Agreement-Cum-General Power
of Attorney, hereinafter called as "DAGPA" vide registration No.6750
3
PNR,J& JSR,J
COMCA.No.34 OF 2022
of 2017 dated 30.06.2017 in respect of land to an extent of
Acs.4.24.8 guntas for development of the said land into a gated
community with independent villas and another development
agreement vide registration document No.6751 of 2017 in respect of
land Ac.00-17.2 guntas for development of commercial building.
While things stood thus, disputes arose between the parties. The
respondent Nos.1 and 2 cancelled the development agreement by
issuing a legal notice on 09.12.2019. When the petitioner rejected
the advances by respondent Nos.1 and 2 for cancellation of the
development agreement the respondents have invoked arbitration
clause and filed Arbitration Application No.43/2020 for seeking
appointment of Arbitrator before this Hon'ble Court and the same
was allowed and 8th respondent herein was appointed as 'sole
Arbitrator' for adjudication of the disputes between the parties by its
order dated 04.08.2020.
4. Before the Arbitral Tribunal the respondents have filed claim
petitionin Arbitration Application No.43 of 2020 for seeking the
following reliefs:
4
PNR,J& JSR,J
COMCA.No.34 OF 2022
"(i) Declare the Development Agreement-cum-General Power
of Attorney dated 30.06.2017, vide document No.6751/2017
as invalid and cancelled.
(ii) Direct the Respondent to execute a Deed of Cancellation
of the Development Agreement-cum-General Power of
Attorney, dated 30.06.2017 vide document No.6751/2017.
(iii) Direct the Respondent to deliver the possession of the
schedule property to the claimants.
(iv) Direct the respondent to pay damages of Rs.2,00,00,000/-
(Rupees Two Crores only) for breach of contract.
(v) To award costs of this claim and also to pass an order or
orders which this Hon'ble Court deem fit in the circumstances
of this case".
4.1. In the said claim petition the respondents stated that
in terms of the DAGPA dated 30-06-2017 the respondent Nos.1 &
2 and Late Inturi Lakshmi Prasanna are the owners and they are
entitled to 50% of built-up area and the petitioner as developer is
entitled for the remaining 50% of the built-up area to be
constructed over the said property. The petitioner has agreed to
complete the entire project within 30 months with a grace period
of 6 months. The petitioner as a professional developer verified
such land use in the proposed master plan which is also evident
from land use information furnished by Hyderabad Metropolitan
Development Authority. The petitioner undertook to obtain
5
PNR,J& JSR,J
COMCA.No.34 OF 2022
required permissions from all the concerned authorities for
deletion of 30 meters road from the proposed master plan.
4.2. It is further stated that the petitioner promised to obtain
all such required permissions from the concerned authorities and
necessary sanction for the construction of the proposed building
within a period of 9 months from the date of DAGPA as the
respondent Nos.1 & 2 and Late Inturi Lakshmi Prasanna have
already made necessary application to the Hyderabad
Metropolitan Development Authority for deletionof 30 meters
road. The petitioner as a professional developer promised to
pursue such application before the concerned authorities at his
cost and expense.
4.3. The respondents further stated that the petitioner
failed to obtain necessary orders for deletion of 30 feet road from
the proposed master plan though more than 3 years have lapsed
from the date of DAGPAs. In the absence of deletion of 30 meters
road, the said property is not viable for development into a
commercial building and independent villas. Thus, both the
6
PNR,J& JSR,J
COMCA.No.34 OF 2022
DAGPAs stood frustrated and became unenforceable. The
petitioner always sought time to get the necessary clearances 'and
permissions to commence the project citing vague reasons. In
those circumstances, the respondents were compelled to cancel
DAGPAs by issuing Notice through their Advocate on 09.12.2019.
But the petitioner did not give any reply, on the other hand he
refused to execute a Registered Deed of Cancellation of
Development Agreement Cum General Power of Attorney. At that
stage the respondents have invoked Arbitration Clause to resolve
the disputes.
4.4. Respondents further stated that basing upon the
DAGPA the petitioner is claiming physical possession of the
subject property, though actual physical possession of the
property was not delivered to the petitioner. The petitioner
however after filing of COP No.17 of 2019 for grant of injunction
against the respondents erected a watchman room without the
knowledge of the respondents and on such basis claimed
possession over the said property. In view of the same the
7
PNR,J& JSR,J
COMCA.No.34 OF 2022
respondents sought recovery of possession from the petitioner and
also claimed damages an amount of Rs.2,00,00,000/-
4.5 The Claimants herein are also subjected to such mental
agony due to the inordinate delay made by Respondent. The
Claimant Nos.1 & 2 also planned to invest the sale proceeds to be
realized from the sale of their share of villas in a profitable
manner but could not do so due to the breach of Agreement
committed by Respondent. The claimants therefore are entitled to
claim compensation for such breach of contract committed by the
Respondent. The Respondent is therefore liable to pay a sum of
Rs.50,00,000/- (Rupees Fifty Lakhs only) towards compensation
for the breach of contract.
5. Before the Learned Arbitrator the petitioner filed statement of
defence denying the claim made by the respondents, inter alia
contending that at the time of execution of DAGPA only the
respondents have delivered physical possession of the property to
petitioner and they encircled Compound Wall, partly fenced with
Barbed Wire, Constructed Rooms for Watchmen and Security and
8
PNR,J& JSR,J
COMCA.No.34 OF 2022
the petitioner is in physical possession and enjoyment of above
said land in the capacity of its Developer without any
interferences or obstructions from whomsoever. The petitioner
further submits that with an intention to develop the subject
property as per the terms of DAGPA, he had applied and
approached the Authorities by spending huge amounts apart from
securing and safeguarding the said property. Thus, the petitioner
all through is waiting for the approvals from the concerned
Authorities to commence construction and complete the project at
the earliest. But the respondents in spite of having complete
knowledge about the persuasion of petitioner having seen the
escalation of prices indulged in unlawful acts like issuing the
Legal Notices to harass thepetitioner and to cause wrongful loss
thereon.
5.1 That the petitioner further stated that they have filed
C.O.P.No.17 of 2019 on the file of Hon'ble XIII Additional District
Judge-cum-Commercial Court, Ranga Reddy District at L.B.
Nagar U/Sec.9 of the Act, 1996 for grant injunction restraining
9
PNR,J& JSR,J
COMCA.No.34 OF 2022
Inturi Lakshmi Prasanna and the respondents 1 and 2 from
alienating and interfering with the peaceful possession and
enjoyment of petitioner over the said property. Upon consideration
the learned judge was pleased to passed order directing both the
parties to maintain status quo and the said orders are still
subsisting" and prayed for dismissal of the claim made by the
respondents.
6. The learned Arbitral Tribunal basing on the claim statement
and statement of defence of the respective parties framed the
following points of disputes.
"(i) Whether the respondent constructed compound
wall(partly) and fenced with barbed wire around the subject
Property?
(ii) Whether the respondent failed to discharge its obligation
of obtaining necessary orders from the authorities concerned
for deletion of 30 Meter Road, and construction permission?
(iii) Whether the respondent knew of the existence of 30
Meter Road in the subject land in the year 2013 itself?
(iv) Whether the respondent committed the breach of its
obligations and thus frustrated the performance of
Development Agreement-cum-General Power of Attorney
dated 30.06.2017 bearing document No.6751/2017?
(v) Whether the respondent is liable to execute a Deed of
Cancellation of Development Agreement-cum-General Powerof
Attorney dated 30.06.2017 bearing document No.6751/2017?
10
PNR,J& JSR,J
COMCA.No.34 OF 2022
(vi) Whether the respondent is obliged to deliver the
possession of the subject land?
(vii) Whether the respondent is liable to pay damages of
Rs.2,00,00,000/- (Rupees Two Crore only) to the claimant for
the reason of committing breach of contract?
(viii) To what relief the claimant is entitled to?".
7. Before the Arbitral Tribunal on behalf of the respondents CW.1
to CW.3 are examined and Exs.C1 to C13 documents were marked
and on behalf of petitioner RWs.1 to RW.3 are examined and Exs.R1
to R.29 documents were marked. The learned Arbitral Tribunal after
considering the contentions of the respective parties, documentary
evidence on record and also after hearing both the parties passed
award on 04.08.2020 by giving cogent findings in respect of each
point. With regard to Point No.1, the learned Arbitral Tribunal held
that the petitioner has failed to establish that he constructed
compound wall around the subject property existed on the date of
execution of Ex.C.5. Insofar as Point Nos.2 to 4 are concerned the
learned Arbitral Tribunal after giving cogent reasons in Paras 6.2.2
to 6.2.14 of the Award, holds that the respondents/claimants have
to pay an amount of Rs.2,39,79,579/- to the petitioner/developer.
In respect of Point Nos.5 & 6 are concerned, the learned Arbitral
Tribunal was pleased to hold that Ex.C.5 development agreement
11
PNR,J& JSR,J
COMCA.No.34 OF 2022
DAGPA becomes void and petitioner has to execute the deed of
cancellation of the same and deliver the possession of the property to
the respondents/claimants and further held that the
petitioner/developer is not liable to pay damages an amount of
Rs.2,00,00,000/- to the respondents. The learned Arbitral Tribunal
granted the following relief:
a). The petitioner/developer will execute the deed of cancellation
ofEx.C.5 DAGPA dated 30.06.2017 document bearing No.6751/2017
and deliver possession of subject property to the
respondents/claimants on as is whether is condition within three
months from the date of the Award.
b). An order with regard to refund of the advance amount and
reimbursement of expenses are considered in Arbitration Application
No.40/2020 and therefore, there is no need of giving a separate relief
in this A.A. No.43 of 2020.
c). The respondents/claimants and petitioner/developer shall
bear their own costs.
8. Questioning the award, passed by the learned Arbitral Tribunal
petitioner filed COP No.3 of 2022 under Section 34 of the Act, 1996
before Special Court for Trial and disposal of Commercial Disputes,
Ranga Reddy District, at L.B. Nagar. The learned Special Judge,
after considering the grounds raised by the petitioner, evidence on
record, Hon'ble Apex Court judgments as well as High Court
12
PNR,J& JSR,J
COMCA.No.34 OF 2022
Judgments and also the provisions of Section 34 of the Act, 1996
dismissed the COP No.3 of 2022 by its order dated 12.09.2022.
9. Aggrieved by the order passed by the Principal Special Court
for Tribal and Disposal of Commercial Disputes, Ranga Reddy
District at L.B. Nagar in COP.No.3/2022 dated12.09.2022 the
petitioner filed the above COMCA.No.34/2022.
10. Learned Senior Counsel Sri V. Ravinder Rao appearing on
behalf of the petitioner vehemently contended that the Court below
without properly appreciating the contentions/grounds raised by the
petitioner, and also evidence on record erroneously dismissed
COP.No.3/2022 and simply confirmed the Award of the Arbitral
Tribunal. He further submits that the respondents have invoked the
provisions of Section 56 of the Indian Contract Act, 1872, though the
same is not applicable to the facts and circumstances of the case.
He also contended that the Commercial Court as well as learned
Arbitrator failed to consider the Ex.R.5 which clearly demonstrates
that the application submitted by the respondents for deletion of 30
meter wide road to the HMDA is pending till date and further
13
PNR,J& JSR,J
COMCA.No.34 OF 2022
demonstrates that the application under consideration does not
result in an impossibility to perform the contract as it had not
attained finality. In view of the same, the effect of Section 56 of the
Indian Contract Act, 1872 could not have been applied. He further
contended that the Court below ought to have considered that the
time was not the essence of the contract not only because Ex.C.5
never contemplated such an obligation but the jurisprudence and
past precedents expressly hold that time is never the essence in a
contract relating to an immovable property. He further contended
that the Court below as well as learned Arbitral Tribunal not
appreciated the judicial precedents submitted by the petitioner.
11. In support of his contention the learned Senior Counsel relied
upon the following judgments:
1. Delhi Development Authority Versus Kenneth Builders and
Developers Private Limited and Others1
2. State of Chhattisgarh and Another Versus Sal Udyog Private
Limited2
3. Ssangyong Eng.& Construction Company Limited Versus
National Highways Authority of India (NHAI)3
1(2016) 13 SCC 561
2(2022) 2 SCC 275
3(2019) 15 SCC 131
14
PNR,J& JSR,J
COMCA.No.34 OF 2022
4. Associate Builders Versus Delhi Development Authority4
12. On the other hand, Sri B. Adinarayana Rao, learned Senior
Counsel representing on behalf of respondents contended that the
appeal filed by the petitioner is not maintainable under law and the
Court below after considering the contentions of the respective
parties, documentary evidence on record and also after hearing both
the parties rightly dismissed the COP.No.3/2002 by giving cogent
reasons by its order dated 12.09.2022 and upheld the Award dated
23.12.2021 passed by the Arbitral Tribunal in A.A. No.43 of 2020.
He further contended that scope of Section 37 of the Act is very
limited. The learned Senior Counsel further contended that the
Arbitral Tribunal passed the award dated 23.10.2021 within the
parameters of the dispute between the parties only and the Arbitral
Tribunal has not committed any illegality, irregularity in the
impugned award. The Court below after considering all the grounds
raised by the petitioner passed the impugned order confirming the
award passed by the Arbitral Tribunal, and there are no grounds to
interfere with the impugned order and the appeal filed by the
4(2015) 3 SCC 49
15
PNR,J& JSR,J
COMCA.No.34 OF 2022
petitioner is not maintainable under law and the same is liable to be
dismissed.
13. After hearing the rival contentions of the parties to the
appeal, the points that predominantly emerge for consideration
are as follows:
(1) Whether the order passed by the Commercial Court in
COP No.3 of 2022 confirming the Award passed by learned
Arbitral Tribunal dated 23.10.2021, is valid under law?
(2) Whether the Court below rightly exercised the powers
conferred under Section 34 of the Act while upholding the
Award of the learned Arbitral Tribunal?
(3) To what relief?"
POINT NOS.1 AND 2
14. The pleadings, submissions and documentary evidence on
record disclose that the respondents are the absolute owners of the
land admeasuring an extent of Acs.5.02 guntas in Sy.Nos.128 and
132 situated at Bachupally Village, Quthbullapur Mandal, Ranga
Reddy District. Petitioner and respondents have entered into
registered Development Agreement-Cum-General Power of Attorney,
herein after called as "DAGPA" vide registration No.6750 of 2017
16
PNR,J& JSR,J
COMCA.No.34 OF 2022
dated 30.06.2017 in respect of land to an extent of Acs.4.24.8
guntas for development of the said land into a gated community with
independent villas and another development agreement vide
registration document No.6751 of 2017 in respect of land Ac.00-17.2
guntas for development of commercial building. While things stood
thus, disputes arose between the parties. The respondent Nos.1 and
2 cancelled the development agreement by issuing a legal notice on
09.12.2019. As the petitioner did not accept the cancellation of the
development agreement, the respondents have invoked arbitration
clause and filed Arbitration Application No.43/2020 for seeking
appointment of Arbitrator before this Hon'ble Court and the same
was allowed and 8th respondent herein was appointed as 'sole
Arbitrator' for adjudication of the disputes between the parties by its
order dated 04.08.2020.
15. The respondents have filed claim petition before the learned
Arbitral Tribunal seeking (i) to declare the DAGPA dated
30.06.2017, as invalid and cancelled; (ii) to direct the petitioner to
execute a Deed of Cancellation of the DAGPA; (iii) to direct the
petitioner to deliver the possession of the schedule property to the
17
PNR,J& JSR,J
COMCA.No.34 OF 2022
respondents; (iv) to direct the respondent to pay damages of
Rs.2,00,00,000/- (Rupees Two Crores only) for breach of contract.
16. Petitioner filed defence statement denying the claim made by
the respondents. The learned Arbitral Tribunal after considering the
claim statement and defence statement of the petitioner and
respondents and also after examining the documentary evidence
Ex.C.1 to Ex.C.13 and Exs.R.1 to Ex.R.29 and also after hearing
parties passed the Award on 23-10-2021. Questioning the same,
petitioner filed C.O.P. No.3 of 2022 by invoking the provisions of
Section 34 of the Act to set aside the arbitral award passed by the
learned Arbitral Tribunal. The Court below after considering the
grounds raised by the petitioner, evidence on record and after
hearing both the parties dismissed the COP No.3 of 2022 by its order
dated 12.09.2022 and upheld the Award passed by the Arbitral
Tribunal, holding that there is no material irregularity, illegality or
error in the impugned award passed by the Arbitral Tribunal.
18
PNR,J& JSR,J
COMCA.No.34 OF 2022
17. The scope of consideration of appeal under Section 37 has
been lucidly explained by the Hon'ble Supreme Court in the
following decisions:
17.1. In Delhi Development Authority (supra) it is observed as
under:
30. The interpretation of Section 56 of the Contract Act came up
for consideration in Satyabrata Ghose v. MugneeramBangur&
Co. [Satyabrata Ghose v. MugneeramBangur& Co., AIR 1954 SC
44: 1954 SCR 310] It was held by this Court that the word
"impossible" used in Section 56 of the Contract Act has not been
used in the sense of physical or literal impossibility. It ought to be
interpreted as impracticable and useless from the point of view of
the object and purpose that the parties had in view when they
entered into the contract. This impracticability or uselessness
could arise due to some intervening or supervening circumstance
which the parties had not contemplated. However, if the
intervening circumstance was contemplated by the parties, then
the contract would stand despite the occurrence of such
circumstance. In such an event, "there can be no case of
frustration because the basis of the contract being to demand
performance despite the happening of a particular event, it cannot
disappear when that event happens". This is what this Court had
to say: (AIR pp. 46-49, paras 9-10 & 17)
17.2 In State of Chhattisgarh and Another (supra) wherein it is
observed as under:
11. Per contra, Mr Pranav Malhotra, learned counsel for the
respondent Company argued that the appellant State having failed
to raise any objection relating to deduction of "supervision
charges" in its Section 34 petition, it must be assumed that it had
waived its right to take any such plea in the Section 37 petition
filed in the High Court and for that matter, before this Court. He
cited State of Maharashtra v. Hindustan Construction Co.
Ltd. [State of Maharashtra v. Hindustan Construction Co. Ltd.,
(2010) 4 SCC 518: (2010) 2 SCC (Civ) 207] to substantiate such an
objection.
19
PNR,J& JSR,J
COMCA.No.34 OF 2022
24. We are afraid, the plea of waiver taken against the appellant
State on the ground that it did not raise such an objection in the
grounds spelt out in the Section 34 petition and is, therefore,
estopped from taking the same in the appeal preferred under
Section 37 or before this Court, would also not be available to the
respondent Company having regard to the language used in
Section 34(2-A) of the 1996 Act that empowers the Court to set
aside an award if it finds that the same is vitiated by patent
illegality appearing on the face of the same. Once the appellant
State had taken such a ground in the Section 37 petition and it
was duly noted in the impugned judgment, the High Court ought
to have interfered by resorting to Section 34(2-A) of the 1996 Act, a
provision which would be equally available for application to an
appealable order under Section 37 as it is to a petition filed under
Section 34 of the 1996 Act. In other words, the respondent
Company cannot be heard to state that the grounds available for
setting aside an award under sub-section (2-A) of Section 34 of the
1996 Act could not have been invoked by the Court on its own, in
exercise of the jurisdiction vested in it under Section 37 of the
1996 Act. Notably, the expression used in the sub-section is "the
Court finds that". Therefore, it does not stand to reason that a
provision that enables a Court acting on its own in deciding a
petition under Section 34 for setting aside an award, would not be
available in an appeal preferred under Section 37 of the 1996 Act.
17.3 In Ssangyong Eng..& Construction Company Limited (supra)
it is held as under:
20. It is first necessary to survey the law insofar as it relates to the
ground of setting aside an award if it is in conflict with the public
policy of India, as it existed before the Amendment Act, 2015.
In Associate Builders v. DDA [Associate Builders v. DDA, (2015) 3
SCC 49 : (2015) 2 SCC (Civ) 204] (Associate Builders), this Court
referred to the judgment in Renusagar Power Co. Ltd. v. General
Electric Co. [Renusagar Power Co. Ltd. v. General Electric Co., 1994
Supp (1) SCC 644] (Renusagar), as follows : (Associate Builders
case [Associate Builders v. DDA, (2015) 3 SCC 49 : (2015) 2 SCC
(Civ) 204] , SCC pp. 67-68, para 18)
24. Yet another expansion of the phrase "public policy of India"
contained in Section 34 of the 1996 Act was by another judgment
of this Court in Western Geco [ONGC v. Western Geco International
Ltd., (2014) 9 SCC 263 : (2014) 5 SCC (Civ) 12] , which was
explained in Associate Builders [Associate Builders v. DDA, (2015)
3 SCC 49 : (2015) 2 SCC (Civ) 204] as follows : (SCC pp. 73-77,
paras 28-34)
"28. In a recent judgment, ONGC v. Western Geco
International Ltd. [ONGC v. Western Geco International Ltd.,
20
PNR,J& JSR,J
COMCA.No.34 OF 2022
(2014) 9 SCC 263 : (2014) 5 SCC (Civ) 12] , this Court added
three other distinct and fundamental juristic principles
which must be understood as a part and parcel of the
fundamental policy of Indian law. The Court held : (SCC pp.
278-80, paras 35 & 38-40)
'35. What then would constitute the "fundamental policy of
Indian law" is the question. The decision
in ONGC [ONGC v. Saw Pipes Ltd., (2003) 5 SCC 705] does
not elaborate that aspect. Even so, the expression must, in
our opinion, include all such fundamental principles as
providing a basis for administration of justice and
enforcement of law in this country. Without meaning to
exhaustively enumerate the purport of the expression
"fundamental policy of Indian law", we may refer to three
distinct and fundamental juristic principles that must
necessarily be understood as a part and parcel of the
fundamental policy of Indian law. The first and foremost is
the principle that in every determination, whether by a court
or other authority that affects the rights of a citizen or leads
to any civil consequences, the court or authority concerned
is bound to adopt what is in legal parlance called a "judicial
approach" in the matter. The duty to adopt a judicial
approach arises from the very nature of the power exercised
by the court or the authority does not have to be separately
or additionally enjoined upon the fora concerned. What
must be remembered is that the importance of a judicial
approach in judicial and quasi-judicial determination lies in
the fact that so long as the court, tribunal or the authority
exercising powers that affect the rights or obligations of the
parties before them shows fidelity to judicial approach, they
cannot act in an arbitrary, capricious or whimsical manner.
Judicial approach ensures that the authority acts bona fide
and deals with the subject in a fair, reasonable and objective
manner and that its decision is not actuated by any
extraneous consideration. Judicial approach in that sense
acts as a check against flaws and faults that can render the
decision of a court, tribunal or authority vulnerable to
challenge.
38. Equally important and indeed fundamental to the policy of
Indian law is the principle that a court and so also a quasi-
judicial authority must, while determining the rights and
obligations of parties before it, do so in accordance with the
principles of natural justice. Besides the
celebrated audialteram partem rule, one of the facets of the
principles of natural justice is that the court/authority
deciding the matter must apply its mind to the attendant
facts and circumstances while taking a view one way or the
other. Non-application of mind is a defect that is fatal to any
adjudication. Application of mind is best demonstrated by
disclosure of the mind and disclosure of mind is best done
21
PNR,J& JSR,J
COMCA.No.34 OF 2022
by recording reasons in support of the decision which the
court or authority is taking. The requirement that an
adjudicatory authority must apply its mind is, in that view,
so deeply embedded in our jurisprudence that it can be
described as a fundamental policy of Indian law.
39. No less important is the principle now recognised as a
salutary juristic fundamental in administrative law that a
decision which is perverse or so irrational that no
reasonable person would have arrived at, the same will not
be sustained in a court of law. Perversity or irrationality of
decisions is tested on the touchstone
of Wednesbury [Associated Provincial Picture Houses
Ltd. v. Wednesbury Corpn., (1948) 1 KB 223 (CA)] principle
of reasonableness. Decisions that fall short of the standards
of reasonableness are open to challenge in a court of law
often in writ jurisdiction of the superior courts but no less in
statutory processes wherever the same are available.
40. It is neither necessary nor proper for us to attempt an
exhaustive enumeration of what would constitute the
fundamental policy of Indian law nor is it possible to place
the expression in the straitjacket of a definition. What is
important in the context of the case at hand is that if on
facts proved before them the arbitrators fail to draw an
inference which ought to have been drawn or if they have
drawn an inference which is on the face of it, untenable
resulting in miscarriage of justice, the adjudication even
when made by an Arbitral Tribunal that enjoys considerable
latitude and play at the joints in making awards will be open
to challenge and may be cast away or modified depending
upon whether the offending part is or is not severable from
the rest.'
29. It is clear that the juristic principle of a "judicial approach"
demands that a decision be fair, reasonable and objective.
On the obverse side, anything arbitrary and whimsical
would obviously not be a determination which would either
be fair, reasonable or objective.
30. The audi alteram partem principle which undoubtedly is a
fundamental juristic principle in Indian law is also
contained in Sections 18 and 34(2)(a)(iii) of the Arbitration
and Conciliation Act. These sections read as follows:
S.18. Equal treatment of parties.The parties shall be
treated with equality and each party shall be given a full
opportunity to present his case.
***
S.34. Application for setting aside arbitral award. --
(1) * * *
22
PNR,J& JSR,J
COMCA.No.34 OF 2022
(2) An arbitral award may be set aside by the court only if--
(a) the party making the application furnishes proof that--
***
(iii) the party making the application was not given proper notice
of the appointment of an arbitrator or of the arbitral proceedings or was otherwise unable to present his case;'
31. The third juristic principle is that a decision which is perverse or so irrational that no reasonable person would have arrived at the same is important and requires some degree of explanation. It is settled law that where:
(i) a finding is based on no evidence, or
(ii) an Arbitral Tribunal takes into account something irrelevant
to the decision which it arrives at; or
(iii) ignores vital evidence in arriving at its decision,
such decision would necessarily be perverse.
32. A good working test of perversity is contained in two judgments. In Excise and Taxation Officer-cum-Assessing Authority v. Gopi Nath & Sons [Excise and Taxation Officer- cum-Assessing Authority v. Gopi Nath & Sons, 1992 Supp (2) SCC 312] , it was held : (SCC p. 317, para 7) '7. ... It is, no doubt, true that if a finding of fact is arrived at by ignoring or excluding relevant material or by taking into consideration irrelevant material or if the finding so outrageously defies logic as to suffer from the vice of irrationality incurring the blame of being perverse, then, the finding is rendered infirm in law.' In Kuldeep Singh v. Commr. of Police [Kuldeep Singh v. Commr. of Police, (1999) 2 SCC 10 : 1999 SCC (L&S) 429] , it was held : (SCC p. 14, para 10) '10. A broad distinction has, therefore, to be maintained between the decisions which are perverse and those which are not. If a decision is arrived at on no evidence or evidence which is thoroughly unreliable and no reasonable person would act upon it, the order would be perverse. But if there is some evidence on record which is acceptable and which could be relied upon, howsoever compendious it may be, the conclusions would not be treated as perverse and the findings would not be interfered with.'
33. It must clearly be understood that when a court is applying the "public policy" test to an arbitration award, it does not act as a court of appeal and consequently errors of fact cannot be corrected. A possible view by the arbitrator on 23 PNR,J& JSR,J COMCA.No.34 OF 2022 facts has necessarily to pass muster as the arbitrator is the ultimate master of the quantity and quality of evidence to be relied upon when he delivers his arbitral award. Thus, an award based on little evidence or on evidence which does not measure up in quality to a trained legal mind would not be held to be invalid on this score. Once it is found that the arbitrator's approach is not arbitrary or capricious, then he is the last word on facts. In P.R. Shah Shares & Stock Brokers (P) Ltd. v. BHH Securities (P) Ltd. [P.R. Shah Shares & Stock Brokers (P) Ltd. v. BHH Securities (P) Ltd., (2012) 1 SCC 594 : (2012) 1 SCC (Civ) 342] , this Court held : (SCC pp. 601-02, para 21) '21. A court does not sit in appeal over the award of an Arbitral Tribunal by reassessing or reappreciating the evidence. An award can be challenged only under the grounds mentioned in Section 34(2) of the Act. The Arbitral Tribunal has examined the facts and held that both the second respondent and the appellant are liable. The case as put forward by the first respondent has been accepted. Even the minority view was that the second respondent was liable as claimed by the first respondent, but the appellant was not liable only on the ground that the arbitrators appointed by the Stock Exchange under Bye-law 248, in a claim against a non-member, had no jurisdiction to decide a claim against another member. The finding of the majority is that the appellant did the transaction in the name of the second respondent and is therefore, liable along with the second respondent. Therefore, in the absence of any ground under Section 34(2) of the Act, it is not possible to re-examine the facts to find out whether a different decision can be arrived at.'
34. It is with this very important caveat that the two fundamental principles which form part of the fundamental policy of Indian law (that the arbitrator must have a judicial approach and that he must not act perversely) are to be understood."
34. What is clear, therefore, is that the expression "public policy of India", whether contained in Section 34 or in Section 48, would now mean the "fundamental policy of Indian law" as explained in paras 18 and 27 of Associate Builders [Associate Builders v. DDA, (2015) 3 SCC 49 : (2015) 2 SCC (Civ) 204] i.e. the fundamental policy of Indian law would be relegated to "Renusagar" understanding of this expression. This would necessarily mean that Western Geco [ONGC v. Western Geco International Ltd., (2014) 9 SCC 263 : (2014) 5 SCC (Civ) 12] expansion has been done away with. In short, Western Geco [ONGC v. Western Geco International Ltd., (2014) 9 SCC 263 : (2014) 5 SCC (Civ) 12] , as explained in paras 28 and 29 of Associate 24 PNR,J& JSR,J COMCA.No.34 OF 2022 Builders [Associate Builders v. DDA, (2015) 3 SCC 49 : (2015) 2 SCC (Civ) 204] , would no longer obtain, as under the guise of interfering with an award on the ground that the arbitrator has not adopted a judicial approach, the Court's intervention would be on the merits of the award, which cannot be permitted post amendment. However, insofar as principles of natural justice are concerned, as contained in Sections 18 and 34(2)(a)(iii) of the 1996 Act, these continue to be grounds of challenge of an award, as is contained in para 30 of Associate Builders [Associate Builders v. DDA, (2015) 3 SCC 49 : (2015) 2 SCC (Civ) 204] .
35. It is important to notice that the ground for interference insofar as it concerns "interest of India" has since been deleted, and therefore, no longer obtains. Equally, the ground for interference on the basis that the award is in conflict with justice or morality is now to be understood as a conflict with the "most basic notions of morality or justice". This again would be in line with paras 36 to 39 of Associate Builders [Associate Builders v. DDA, (2015) 3 SCC 49 : (2015) 2 SCC (Civ) 204] , as it is only such arbitral awards that shock the conscience of the court that can be set aside on this ground.
37. Insofar as domestic awards made in India are concerned, an additional ground is now available under sub-section (2-A), added by the Amendment Act, 2015, to Section 34. Here, there must be patent illegality appearing on the face of the award, which refers to such illegality as goes to the root of the matter but which does not amount to mere erroneous application of the law. In short, what is not subsumed within "the fundamental policy of Indian law", namely, the contravention of a statute not linked to public policy or public interest, cannot be brought in by the backdoor when it comes to setting aside an award on the ground of patent illegality".
39. To elucidate, para 42.1 of Associate Builders [Associate Builders v. DDA, (2015) 3 SCC 49: (2015) 2 SCC (Civ) 204] ,namely, a mere contravention of the substantive law of India, by itself, is no longer a ground available to set aside an arbitral award. Para 42.2 of Associate Builders [Associate Builders v. DDA, (2015) 3 SCC 49: (2015) 2 SCC (Civ) 204], however, would remain, for if an arbitrator gives no reasons for an award and contravenes Section 31(3) of the 1996 Act, that would certainly amount to a patent illegality on the face of the award.
40. The change made in Section 28(3) by the Amendment Act really follows what is stated in paras 42.3 to 45 in Associate Builders [Associate Builders v. DDA, (2015) 3 SCC 49 : (2015) 2 SCC (Civ) 204] , namely, that the construction of the terms of a contract is primarily for an arbitrator to decide, unless the 25 PNR,J& JSR,J COMCA.No.34 OF 2022 arbitrator construes the contract in a manner that no fair-minded or reasonable person would; in short, that the arbitrator's view is not even a possible view to take. Also, if the arbitrator wanders outside the contract and deals with matters not allotted to him, he commits an error of jurisdiction. This ground of challenge will now fall within the new ground added under Section 34(2-A).
41. What is important to note is that a decision which is perverse, as understood in paras 31 and 32 of Associate Builders [Associate Builders v. DDA, (2015) 3 SCC 49 : (2015) 2 SCC (Civ) 204] , while no longer being a ground for challenge under "public policy of India", would certainly amount to a patent illegality appearing on the face of the award. Thus, a finding based on no evidence at all or an award which ignores vital evidence in arriving at its decision would be perverse and liable to be set aside on the ground of patent illegality. Additionally, a finding based on documents taken behind the back of the parties by the arbitrator would also qualify as a decision based on no evidence inasmuch as such decision is not based on evidence led by the parties, and therefore, would also have to be characterised as perverse.
44. In Renusagar [Renusagar Power Co. Ltd. v. General Electric Co., 1994 Supp (1) SCC 644] , this Court dealt with a challenge to a foreign award under Section 7 of the Foreign Awards (Recognition and Enforcement) Act, 1961 (the Foreign Awards Act). The Foreign Awards Act has since been repealed by the 1996 Act. However, considering that Section 7 of the Foreign Awards Act contained grounds which were borrowed from Article V of the Convention on the Recognition and Enforcement of Foreign Arbitral Awards, 1958 (the New York Convention), which is almost in the same terms as Sections 34 and 48 of the 1996 Act, the said judgment is of great importance in understanding the parameters of judicial review when it comes to either foreign awards or international commercial arbitrations being held in India, the grounds for challenge/refusal of enforcement under Sections 34 and 48, respectively, being the same.
17.4 In Associate Builders (supra) it is observed as under:
"27. Coming to each of the heads contained in Saw Pipes [(2003) 5 SCC 705 : AIR 2003 SC 2629] judgment, we will first deal with the head "fundamental policy of Indian law". It has already been seen from Renusagar [Renusagar Power Co. Ltd. v. General Electric Co., 1994 Supp (1) SCC 644] judgment that violation of the Foreign Exchange Act and disregarding orders of superior courts in India would be regarded as being contrary to the fundamental policy of Indian law. To this it could be added that the binding effect of the 26 PNR,J& JSR,J COMCA.No.34 OF 2022 judgment of a superior court being disregarded would be equally violative of the fundamental policy of Indian law".
17.5 The Hon'ble Supreme Court in the case of MMTC Ltd. v.
Vedanta Ltd.,5 discussed the scope of interference of the Courts under Section 37 of Arbitration and Conciliation Act, 1996. Wherein the Hon'ble Apex Court held that Court under Section 37 cannot travel beyond the restrictions laid down by the Section 34. That the jurisdiction of the Section 37 Court is only limited to determining the legality of the order passed under Section 34 of the Act. The relevant portions of the judgment are extracted as under:
13. It is relevant to note that after the 2015 amendments to Section 34, the above position stands somewhat modified. Pursuant to the insertion of Explanation 1 to Section 34(2), the scope of contravention of Indian public policy has been modified to the extent that it now means fraud or corruption in the making of the award, violation of Section 75 or Section 81 of the Act, contravention of the fundamental policy of Indian law, and conflict with the most basic notions of justice or morality. Additionally, sub-section (2A) has been inserted in Section 34, which provides that in case of domestic arbitrations, violation of Indian public policy also includes patent illegality appearing on the face of the award. The proviso to the same states that an award shall not be set aside merely on the ground of an erroneous application of the law or by re-appreciation of evidence.
14. As far as interference with an order made under Section 34, as per Section 37, is concerned, it cannot be disputed that such interference under Section 37 cannot travel beyond the restrictions laid down under Section 34. In other words, the Court cannot undertake an independent assessment of the merits of the award, and must only ascertain that the exercise of power by the Court under Section 34 has not exceeded the scope of the provision.
Thus, it is evident that in case an arbitral award has been confirmed by the Court under Section 34 and by the Court in an appeal under Section 37, this 5 (2019) 4 SCC 163 27 PNR,J& JSR,J COMCA.No.34 OF 2022 Court must be extremely cautious and slow to disturb such concurrent findings.
18. From the precedent decisions it emerges that the scope of application under Section 37 of the Act is very limited and this Court cannot re-examine or re-assess the evidence. As per the provisions of Sec.37 of the Act, this Court has to examine whether the Court below while exercising the powers conferred under Section 34 of the Act, rightly considered the grounds raised by the petitioner and whether the Arbitral Tribunal committed any illegality, irregularity while passing the arbitral award.
19. In the instant case, the learned Arbitral Tribunal after considering the contentions of the parties, after examining the evidence on record and also after hearing both the parties passed the Award dated 23.10.2021 in AA No.43 of 2020 by giving cogent reasons holding that as per Ex.C5 DAGPA cannot be proceeded with unless '30 meterwide proposed Master Plan road' is realigned. The parties to the Ex.C5 DAGPA are not in a position to get '30 meter wide proposed Master Plan road' realigned and in view of the same, 28 PNR,J& JSR,J COMCA.No.34 OF 2022 the Ex.C.5 DAGPA has become frustrated because the 30-meter wide proposed Master Plan road is passing through the subject property and hence the Ex.C5 DAGPA becomes void. The Arbitral Tribunal further held that the petitioner has to execute the deed of cancellation of the same and deliver the possession of property to the respondents.
20. On due consideration of all aspects the Commercial Court rightly confirmed the award of the learned Arbitral Tribunal.
21. We see no illegality, irregularity, jurisdictional error in the impugned order passed by the Commercial Court upholding the Award passed by the Arbitral Tribunal and this Court finds no merit in the appeal filed by the petitioner and the same is liable to be dismissed. Both Point Nos.1 & 2 are answered against the petitioner and in favour of the respondents.
29PNR,J& JSR,J COMCA.No.34 OF 2022 POINT NO.3
22. In view of the discussion on Point Nos.1 & 2, the COMCA 34 of 2022 is accordingly dismissed without costs. As a sequel, miscellaneous applications pending if any, shall stand disposed of.
___________________________ JUSTICE P. NAVEEN RAO _____________________________ JUSTICE J. SREENIVAS RAO 10-02-2023 Skj 30 PNR,J& JSR,J COMCA.No.34 OF 2022 31 PNR,J& JSR,J COMCA.No.34 OF 2022 HONOURABLE SRI JUSTICE P. NAVEEN RAO AND HONOURABLE SRI JUSTICE J. SREENIVAS RAO COMCA.NO.34 OF 2022 Date : 10-02-2023.
Skj