K.M.Shafi vs District Collector, Kasaragod

Citation : 2025 Latest Caselaw 2219 Ker
Judgement Date : 4 August, 2025

Kerala High Court

K.M.Shafi vs District Collector, Kasaragod on 4 August, 2025

                                                  2025:KER:58206


          IN THE HIGH COURT OF KERALA AT ERNAKULAM

                           PRESENT

              THE HONOURABLE MR. JUSTICE S.MANU

   MONDAY, THE 4TH DAY OF AUGUST 2025 / 13TH SRAVANA, 1947

                   WP(C) NO. 21326 OF 2016

PETITIONER:

    1    *K.M.SHAFI
         S/O.MOHAMMED, AGED 70 YEARS, MELPARAMBA,
         KALANAD P.O., KASARAGOD.
         *DECEASED. LEGAL HEIRS IMPLEADED
    2    *ADDL.P2 ABDUL MAJEED K.S
         AGED 47 YEARS, S/O. (LATE) K.M. SHAFI, NOOR MAHAL,
         THOTTIL, DELI, KALANAD, KASARAGOD,PIN - 671317
         *IS IMPLEADED AS ADDL.P2 AS PER ORDER DATED
         30/06/2025 IN IA 1/2025

    3    *ADDL.P3 MOHAMMED ASHKAR
         AGED 43 YEARS, S/O. LATE K.M. SHAFI, THODE HOUSE
         DELI, KALANAD, KASARAGOD, PIN - 671317
         *IS IMPLEADED AS ADDL.P3 AS PER ORDER DATED
         30/06/2025 IN IA 1/2025

    4    *ADDL.P4 KADEEJATH RAZEENA
         AGED 36 YEARS,D/O. LATE K.M. SHAFI, THODE HOUSE
         DELI, KALANAD, KASARAGOD, PIN - 671317
         *IS IMPLEADED AS ADDL.P4 AS PER ORDER DATED
         30/06/2025 IN IA 1/2025)

    5    *ADDL.P5 ASIATH RELIATH
         AGED 33 YEARS, D/O. LATE K.M. SHAFI, THODE HOUSE,
         DELI, KALANAD, KASARAGOD, PIN - 671317
         *IS IMPLEADED AS ADDL.P5 AS PER ORDER DATED
         30/06/2025 IN IA 1/2025

    6    *ADDL.P6 ZOHARA
         AGED 63 YEARS, W/O. LATE K.M. SHAFI, THODE HOUSE,
         DELI, KALANAD P.O., KASARAGOD, PIN - 671317
         *IS IMPLEADED AS ADDL.P6 AS PER ORDER DATED
         30/06/2025 IN IA 1/2025
                                                                 2025:KER:58206
                                         2
W.P.(C) No.21326 of 2016




             BY ADVS.
             SHRI.K.V.PAVITHRAN
             SHRI.JAYANANDAN MADAYI PUTHIYAVEETTIL
             SRI.NIAS MOOPAN
             SHRI.P.SAJU



RESPONDENTS:

     1       DISTRICT COLLECTOR, KASARAGOD

     2       TAHSILDAR
             REVENUE RECOVERY, KASARAGOD.

     3       EXECUTIVE ENGINEER
             PWD, BUILDINGS DIVISION, KASARAGOD.

     4       SUPERINTENDING ENGINEER
             PWD BUILDINGS (NORTH) CIRCLE, KOZHIKODE.

     5       CHIEF ENGINEER
             PWD BUILDINGS, THIRUVANANTHAPURAM.

     6       STATE OF KERALA
             REPRESENTED BY SECRETARY, PUBLIC WORKS DEPARTMENT,
             THIRUVANANTHAPURAM.


             BY ADV.

             SRI.TONY AUGUSTINE, GOVERNMENT PLEADER


      THIS WRIT PETITION (CIVIL) HAVING BEEN FINALLY HEARD
ON   04.08.2025,      THE   COURT   ON       THE   SAME   DAY   DELIVERED   THE
FOLLOWING:
                                                      2025:KER:58206
                                    3
W.P.(C) No.21326 of 2016


                           JUDGMENT

Original writ petitioner was awarded the work of construction of Sub Registrar office building at Rajapuram in Kasaragode under an agreement dated 01.02.2006. Period fixed for completion of the work was nine months and the probable amount of contract was Rs.7,60,395/-. Original writ petitioner could not carry out the work within the period of nine months. He fell ill. On account of his poor health condition, he made a request to relieve him. During the pendency of this Writ petition, the original petitioner expired and wife and children got impleaded to prosecute the Writ Petition further.

2. It was contended that the delay in conducting the work and completing the same was on account of the change of design and time taken for obtaining revised administrative sanction. Contractor approached the Hon'ble Minister for Public Works and submitted a representation requesting to relieve him from the contract without any liabilities.

3. On 09.03.2012, the 3rd respondent issued Ext.P6 notice to the contractor fixing a liability of Rs.13,06,726/-. Contractor submitted a reply to Ext.P6 on 28.03.2012. He again addressed 2025:KER:58206 4 W.P.(C) No.21326 of 2016 the Hon'ble Minister. However, the 4th respondent issued final notice and terminated the contract. By the letter dated 31.10.2015 issued in this regard, liability of Rs.25,83,698/- was fixed on the contractor/original petitioner after deducting the security deposit of Rs.39,000/-. Ext.P8, the PAC after rearrangement of the work has been shown as Rs.33,83,093/-. Original PAC before rearrangement was Rs.7,60,395/-. Final liability was calculated as Rs.26,22,698/-. Less security, the liability was fixed at Rs.25,83,698/-. Work was thereafter rearranged. Revenue recovery proceedings were initiated for recovery of the amount as fixed in Ext.P8. The Writ Petition was filed challenging Ext.P8 and P10 revenue recovery notice. The 3 rd respondent filed a detailed counter affidavit disputing the contentions of the petitioner.

4. Heard the learned counsel appearing for the petitioner and the learned Government Pleader for the respondents.

5. Learned counsel for the petitioner mainly raised a contention that the work was rearranged in 2015 following the schedule of rates in 2012. The learned counsel pointed out that the original work was as per the schedule of rates of 2004. He 2025:KER:58206 5 W.P.(C) No.21326 of 2016 submitted that it is highly unjust and improper to calculate the risk and cost and fix liability on the basis of the revised schedule of rates as the original work was awarded following the schedule of rates of 2004 which was much less. The learned counsel relied on circular dated 08.08.2023 issued by the PWD wherein it has been stated that balance estimate of the work terminated at the risk and cost needs to be prepared using the same schedule of rates with which the original estimate was prepared. The learned counsel also pointed out that in the PWD Manual also it has been provided that rearrangement of works should be done as expeditiously as possible and there should not be any substantial changes in the specifications on the balance works rearranged. The learned counsel further contended that only 38 items of work were included in the original agreement whereas in the revised agreement total number of 54 items of works were included. Hence he contended that the PAC after rearrangement of work was for 54 items of work instead of 38 items of work which were originally contemplated. He hence submitted that the calculation of final liability is therefore incorrect, unjust and improper. He 2025:KER:58206 6 W.P.(C) No.21326 of 2016 submitted that Ext.P8 and further proceedings for recovery are not legally sustainable.

6. The learned Government Pleader submitted that the petitioner failed to execute the work within the stipulated time limit without any justifiable reasons. Other than the poor health condition, no reason sufficient for excusing the petitioner from the responsibility was pointed out. He submitted that as narrated in the counter affidavit, the petitioner did not start the work within the agreement period and hence the work was terminated by order dated 04.12.2007. On the basis of the request of the original petitioner, the termination was revoked. Even after revocation, he didn't turn up to start the work. Thereafter he explained his inability to execute the work. Hence the contract was terminated with cost by proceedings dated 15.11.2010. The learned Government Pleader pointed out that as per the provisions of the contract vide Clause No.13 of notice inviting tender, the contractor was liable for the cost of rearrangement of the work. The learned Government Pleader further submitted that as per the terms of the contract, the contractor was liable to pay for the loss sustained by the Government for rearrangement of the work. He 2025:KER:58206 7 W.P.(C) No.21326 of 2016 also pointed out that there was no delay on the part of the Department in obtaining administrative sanction as contended in the Writ Petition. He made specific reference to the contents of paragraph No.5 of the counter affidavit in this regard.

7. After hearing the learned counsel for the petitioner as also the learned Government Pleader, I am of the view that in view of the specific contentions raised by the leaned counsel for the petitioner that more items of work were included when the work was rearranged and the entire amount for rearrangement of work, calculated on the basis of the 54 items of work was not liable to be taken into account as the original agreement was only for 38 items of work needs to be considered by the Executive Engineer. It is not discernible on a reading of Ext.P8 as to whether the inclusion of additional items of work was taken into account by the Executive Engineer while fixing liability on the contractor.

8. It is also to be noted that the learned counsel for the petitioner pointed out the circular issued by the Department on 08.08.2023 which stipulates that the balance estimate of the works terminated at the risk and cost needs to be prepared using the same SOR in which the original estimate was prepared.

2025:KER:58206 8 W.P.(C) No.21326 of 2016

9. The learned Government Pleader submitted that the said circular was issued only in 2014 and therefore the benefit of the circular cannot be claimed by the petitioners. Learned counsel for the petitioner responded stating that the said practice was followed before the issuance of the circular and the Executive Engineer overlooked the same while issuing Ext.P8. This aspect also needs to be considered by the Executive Engineer.

10. To facilitate such a reconsideration of the entire issue by the Executive Engineer, I set aside Ext.P8. The Executive Engineer shall reconsider the matter and take a fresh decision. In order to ensure fairness in the decision making process, I direct that the Executive Engineer shall provide opportunity of hearing to the additional petitioners or their representative before taking a fresh decision in the matter. Additional petitioners shall be free to raise all available contentions before the Executive Engineer. All relevant aspects shall be taken note of by the Executive Engineer before taking a fresh decision. The Executive Engineer shall issue notice to the additional petitioners after fixing a date for hearing. The entire exercise shall be completed and a fresh decision shall be taken within a period of four months from the date of receipt of 2025:KER:58206 9 W.P.(C) No.21326 of 2016 a copy of this judgment. Needless to say, as I set aside Ext.P8, revenue recovery proceedings initiated on the basis of same shall also stand quashed.

With the above directions, the Writ Petition is disposed of.

Sd/-

S.MANU JUDGE PV 2025:KER:58206 10 W.P.(C) No.21326 of 2016 APPENDIX OF WP(C) 21326/2016 PETITIONER EXHIBITS EXHIBIT P1 TRUE COPY OF THE SCHEDULE OF WORKS TO BE DONE ALONG WITH PLAN.

EXHIBIT P2 TRUE COPIES OF THE MEDICAL REPORTS OF THE PETITIONER.

EXHIBIT P3 TRUE COPY OF THE LETTER DT.19-2-2009 OF R3 TO R4 TO TAKE DECISION TO RELIEVE THE PETITIONER FOR CONTRACT.

EXHIBIT P4 TRUE COPY OF THE LETTER DT.27-2-2009 OF R4 TO R5 TO RELIEVE THE PETITIONER FOR THE CONTRACT.

EXHIBIT P5 TRUE COPY OF THE REPRESENTATION DT.6-2- 2009 OF PETITIONER ADDRESSED TO THE HON'BLE MINISTER.

EXHIBIT P6                 TRUE COPY OF THE LETTER DT.9-3-2012 OF R3
                           TO   THE    PETITIONER   INTIMATING   THE
                           LIABILITY AS RS.13,06,726/-
EXHIBIT P6A                TRUE COPY OF THE REPLY DT.28-3-2012 OF
                           THE PETITIONER ADDRESSED TO R3.
EXHIBIT P7                 TRUE COPY OF THE REPRESENTATION TO THE
                           HON'BLE MINISTER THROUGH THE MLA
EXHIBIT P8                 TRUE COPY OF THE LETTER DT.31-10-2015 OF
                           R3 FIXING THE LIABILITY AS RS.25,83,698/-
EXHIBIT P9                 TRUE COPY OF THE AGREEMENT SCHEDULE AND
                           PLAN OF THE SUBSEQUENTLY ARRANGED WORK.
EXHIBIT P10                TRUE COPY OF THE DEMAND NOTICE DT.31-5-
                           2016 ISSUED BY R2 UNDER REVENUE RECOVERY
                           ACT.