Thakor Gandaji Harchandji vs Isub Bachubhai Sindhi

Citation : 2025 Latest Caselaw 6951 Guj
Judgement Date : 25 September, 2025

Gujarat High Court

Thakor Gandaji Harchandji vs Isub Bachubhai Sindhi on 25 September, 2025

                                                                                                                  NEUTRAL CITATION




                              C/CA/4914/2025                                      ORDER DATED: 25/09/2025

                                                                                                                  undefined




                                 IN THE HIGH COURT OF GUJARAT AT AHMEDABAD

                      R/CIVIL APPLICATION (FOR CONDONATION OF DELAY) NO. 4914
                                               of 2025

                                          In F/FIRST APPEAL NO. 28799 of 2025

                      ==========================================================
                                          THAKOR GANDAJI HARCHANDJI & ANR.
                                                       Versus
                                            ISUB BACHUBHAI SINDHI & ORS.
                      ==========================================================
                      Appearance:
                      NISHIT A BHALODI(9597) for the Applicant(s) No. 1,2
                      ==========================================================

                         CORAM:HONOURABLE MR.JUSTICE MOOL CHAND TYAGI

                                                         Date : 25/09/2025

                                                                ORAL ORDER

1. The present application has been preferred for seeking condonation of delay of 245 days caused in preferring the appeal against the impugned judgment and award.

2. Heard learned advocate for the applicant.

3. Learned advocate for the applicant submitted that the delay of 245 days has occasioned owing to the reasons that the applicant is a poor labourer and he could not arrange the finance for preferring the appeal. He further submitted that the delay is neither intentional nor malafide but has occasioned owing to the reasons as stated in paragraph 3 and 5 of the application.

Page 1 of 2 Uploaded by MR.CHIRAG DESHRAJ PAL(HCD0072) on Fri Sep 26 2025 Downloaded on : Sat Sep 27 02:12:46 IST 2025

NEUTRAL CITATION C/CA/4914/2025 ORDER DATED: 25/09/2025 undefined

4. Having considered the submissions of the learned advocate for the applicant and having regard to the ground for delay pressed into service, I am of the considered view that the delay has been sufficiently explained and the same deserves to be condoned. Accordingly, the delay is condoned subject to the condition that the claimant shall not be entitled for the interest on the enhanced amount of compensation, in case the appeal is allowed. No order as to costs.

(MOOL CHAND TYAGI, J) CDP Page 2 of 2 Uploaded by MR.CHIRAG DESHRAJ PAL(HCD0072) on Fri Sep 26 2025 Downloaded on : Sat Sep 27 02:12:46 IST 2025