R/CIVIL APPLICATION (FOR CONDONATION OF DELAY) NO. 1968 of
2025
In F/CIVIL REVISION APPLICATION NO. 8377 of 2025
==========================================================
EXECUTIVE ENGINEER SARDAR SAROVAR NARMADA NIGAM LTD
Versus
WARDEN KOOL CONSULTANTS PVT LTD & ANR.
==========================================================
Appearance:
NILAY H PATEL(7856) for the Applicant(s) No. 1
NOTICE SERVED for the Respondent(s) No. 2
SERVED BY RPAD (N) for the Respondent(s) No. 1
==========================================================
CORAM:HONOURABLE MR.JUSTICE SANJEEV J.THAKER
Date : 28/07/2025
ORAL ORDER
The present application has been filed for condoning the delay of 153 days in preferring the revision application arising out of judgment dated 11.07.2024 passed by the Gujarat Public Works Contracts Dispute Arbitration Tribunal at Ahmedabad in Arbitration Reference No. 63 of 1996.
The learned advocate for the appellant has stated that in view of the review application filed on 22.11.2024 and the same was allowed on 20.02.2025, a certified copy o the same was received on 04.03.2025 and, therefore, the present delay has been occurred.
Having heard the learned advocate for the appellant and having considered the application, sufficient reasons are stated towards the delay of 153 days in preferring the revision application. Accordingly, the present application for condonation of delay is hereby allowed and delay of 153 days in preferring the revision application is hereby condoned.
(SANJEEV J.THAKER,J) JIGAR J RABARI Page 1 of 1 Uploaded by MR.JIGAR JIVANBHAI RABARI(HCD0067) on Wed Jul 30 2025 Downloaded on : Wed Jul 30 22:29:48 IST 2025