M/S. S.N.Nandy & Co. vs M/S. Nicco Corporation Ltd.

Citation : 2011 Latest Caselaw 1075 Del
Judgement Date : 23 February, 2011

Delhi High Court
M/S. S.N.Nandy & Co. vs M/S. Nicco Corporation Ltd. on 23 February, 2011
Author: V. K. Jain
         THE HIGH COURT OF DELHI AT NEW DELHI
%             Judgment Reserved on: February 15, 2011
              Judgment Pronounced on: February 23, 2011

+      CS(OS) No. 2448/2000

M/S. S.N.NANDY & CO.                        .....Plaintiff
                           - versus -

M/S. NICCO CORPORATION LTD.                 .....Defendant

Advocates who appeared in this case:
For the Plaintiff:       Mr. S.D.Singh, Ms. Bharti
                        Tyagi, Mr. Rahul Kumar Singh,
                        Ms. Megha Bansiwal, Advs.
For the Defendant:    Mr. Rahul Gupta, Mr. Pinaki
                      Addy and Ms. Ira Gupta, Adv.
CORAM:-
HON'BLE MR JUSTICE V.K. JAIN

1. Whether Reporters of local papers may               Yes
   be allowed to see the judgment?

2. To be referred to the Reporter or not?              Yes

3. Whether the judgment should be reported             Yes
   in Digest?

V.K. JAIN, J

1.     This is a suit for recovery of Rs.92,20,562/-.         The

defendant-company, which was awarded the work for

Biological Oxidation Plant for Coal Chemical Effluents at

Rourkela Steel Plant (hereinafter referred to as "RSP),

assigned the civil work for the aforesaid plant to the plaintiff

for a lump sum amount of Rs.2,87,30,000/- vide Letter of



CS(OS)No.2448/2000                                    Page 1 of 51
 Intent (hereinafter referred to as LOI) dated 15th October,

1992. The scope of work as also the commercial terms for

its execution were annexed to the LOI. It is alleged that in a

meeting held in the last week of February, 1993, among the

plaintiff, defendant and the officials of RSP, some major

changes were made in the nature of civil work which was

assigned to the plaintiff and those changes involved extra

work and extra price implications. Some other extra works

were later entrusted to the plaintiff for execution.        The

plaintiff submitted a claim of Rs.32 lakhs to the defendant

for the extra work executed by it, which was later on

corrected and changed to Rs.42,04,500/-. It is alleged that

a sum of Rs.5 lakhs was paid by the defendant to the

plaintiff in February, 1994, which was adjusted towards

payment for the extra works. The amount payable by the

defendant to the plaintiff towards payment of the extra work

is alleged to have accumulated to Rs.57,18,500/.            The

plaintiff has claimed an amount of Rs.43,51,217/- as

principal sum from the defendant along with interest on

that amount at the rate of 24 % per annum, amounting to

Rs.48,69,345/- - till 31st March, 2000.

2.     The defendant has contested the suit. It has taken a

CS(OS)No.2448/2000                                  Page 2 of 51
 preliminary objection that a full and final payment of

Rs.9,36,900/- was made to the plaintiff on 29.8.1997 and

having accepted that amount, the plaintiff cannot claim any

further amount under the contract in question. The other

preliminary objection taken by the defendant is that the suit

is barred by limitation having been filed on 26.9.2000. On

merits, it has been alleged that the defendant has cleared all

the liabilities which were due to the plaintiff under contract

in question. It is also alleged that extra work claimed by the

plaintiff was already covered in the scope of price breakup

given by it on 15.3.1993 which was subsequently amended

on 19.3.1993.

       The defendant has denied for entrusting extra work to

the plaintiff and having assured payment for the alleged

extra work. It is claimed that the plaintiff, on his own did

the alleged extra work and got the same approved from RSP

because he was fully aware that under the contract he was

required to do that work.

3.     The following issues were framed on the pleadings of

the parties:-

              1.    Whether plaint has been signed and
              verified and suit instituted by a duly


CS(OS)No.2448/2000                                   Page 3 of 51
               authorized        person    on   behalf   of   the
              plaintiff?
              2.   Whether plaintiff executed extra
              work not covered by the letter dated 15th
              October 1992? If answer is in affirmative,
              of what amount?
              3.    Whether plaintiff is entitled to
              interest? If so, on which amount, at
              what rate and for which period?
              4.   Whether amount of Rs.9,36,900/-
              was received by the plaintiff by way of full
              and final payment as alleged in para No.1
              of the preliminary objection of written
              statement?
              5.      Whether suit is barred by time?
              6.    Whether      this    Court     has       no
              territorial jurisdiction to try the suit?
              7.      Relief.


Issue No.6

4.     During        arguments,     the   learned   counsel        for   the

defendant stated that he was not pressing this issue.

Accordingly, this issue is stuck off.

Issue No.1

5.     Mr. S.N.Nandy is the proprietor of S.N.Nandy & Co.

and the plaint has been signed and verified by him.

Institution of suit, and signing and verification of pleadings

by the proprietor of a partnership concern is perfectly legal

and valid. In fact, Mr.S.N.Nandy & Co. is only a trade name

adopted by him and the suit ought to have been filed by Mr


CS(OS)No.2448/2000                                             Page 4 of 51
 S.N. Nandy as its proprietor. The issue is decided against

the plaintiff and in favour of the defendant.

Issue No.2

6.     The plaintiff has examined himself as PW-1 whereas

the defendant has examined one witness Mr. Kartick Kumar

Chatterjee as DW-1.

7.     In his affidavit by way of evidence, the plaintiff has

stated that in the last week of February, 1993, a meeting

was     organized    between   him,   the defendant and      the

department of RSP and certain major changes in the scope

of civil work were made by RSP and accepted by the

defendant.       He accordingly wrote letter dated 2.3.1993 to

the defendant giving details of the extra works as well as the

price implication.       He claimed to have sent another

communication dated 17.6.1993 to the defendant in this

regard and has stated that the defendant had permitted him

to proceed with the work including extra and additional

work with promise and assurance that payment would be

made in due course.        He has further stated that in the

meetings held on 3.1.1994 and 6.1.1994, the defendant

acknowledged the extra works done by the plaintiff and also

accepted his entitlement for payment. He accordingly sent a

CS(OS)No.2448/2000                                   Page 5 of 51
 communication dated 7.1.1994 to the defendant in this

regard. He claimed that the defendant made promises and

assurances to clear his dues but failed to do so. According

to him, in the joint meeting held on 11.3.1994 and

12.3.1994, the issue with regard to extra work was

discussed and the defendant promised to scrutinize the

claim and make payment against the same.              Similar

promise, according to him, was made when he visited the

office of the defendant on 29.6.1994 and 14.7.1994. He has

stated that on 10.11.1994, Deputy Managing Director of the

defendant company came to Delhi and the issue about

payment of extra work was discussed and a promise was

made to make payment.         He further stated that a sum of

Rs.5 lakhs was received by him towards extra work on

15.02.1994.          He maintained that the extra work was

executed at the site with the consent and due information to

the defendant and on their assurance to make payment.

       He further stated that the defendant sent a cheque of

Rs.9,36,900/- being last 5% of the original contract value

and the payment towards extra work remained payable to

him. He has proved the comparative statement Ex.PW-1/51

prepared by him. Ex.PW-1/52, according to him are details

CS(OS)No.2448/2000                                  Page 6 of 51
 of change in scope of work.

8.     In rebuttal, Mr. Kartick Kumar Chatterjee who was

examined as DW-1 has stated that the plaintiff was

entrusted the work of design, construction and maintenance

of civil work in the Biological Oxidation Plant for coal

chemical effluents of RSP on turnkey basis, for a total lump

sum price of Rs.2,87,30,000/- as per the terms and

conditions stipulated in the LOI dated 15.10.1992. The LOI,

according to him, did not contemplate any extra work with

extra price implication nor did it contain any price variation

clause.      He has also proved the letter dated 15.3.1993

written by the plaintiff giving detailed item-wise price-wise

breakup and has stated that complete full and final

payment under the contract and LOI was made to the

plaintiff vide receipt dated 29.8.1997.      According to him,

nothing is left due to the plaintiff. He maintained that the

plaintiff never executed any extra item or extra work.

9.     Ex.PW-1/4 is the offer made by the plaintiff to the

defendant company for civil work of BOD plant at RSP.

Paras 2 and 3 of the letter read as under:-

              "We have gone through the entire scope of
              civil work and specifications furnished to
              us along with the enquiry. Our lumpsum

CS(OS)No.2448/2000                                     Page 7 of 51
               offer for entire civil work is based on M/s.
              NCL's scope of work, specifications and
              layout, and Flow diagram drawings sent
              to us.

              Our total lumpsum price consideration for
              the above job shall be Rs.275 lacks
              (Rupees two hundred seventy five lacs
              only) includes design, execution and
              supervision.   Our lumpsum price also
              includes cost of all materials and
              manpower required for the job. The price
              implication of WCT is not considered, by
              us."

10.    Ex.PW-1/5 is the letter of the plaintiff dated 6.8.1992

whereby, he submitted lump sum price quotation for

Earthern Sludge lagoon for a covered area of 800 sqm. and

providing       one   metre   wide   pavement.       A   sum        of

Rs.2,55,000/- was quoted for the sludge lagoon and

Rs.3,35,000/- was quoted for the pavement. Ex.PW-1/6 is

the letter dated 15.10.1992 whereby the work for the

design, engineering, drawing, construction and maintenance

of all the civil works in the Biological Oxidation Plant for

coal chemicals effluents etc. at RSP was awarded to the

plaintiff for a lump sum price of Rs.2,87,30,000/-.              The

scope of work covered by the letter and major chemical

terms and conditions were also enclosed to this letter. The

scope of work as defined in the annexure to this document


CS(OS)No.2448/2000                                       Page 8 of 51
 reads as under:-


              "SCOPE OF WORKS

                    The scope of work of this LOI covers
              the Design. Engineering preparation of
              Arrangement and Detailed Drawings,
              obtaining approval from RSP, construction
              in    accordance   with   the    approved
              drawings, Specifications and Instructions
              of RSP/NCL and maintenance of all the
              Civil-Works involved in the Biological
              Oxidation Plant for Coal Chemical
              Effluents at RSP.
                    The list of items of Civil-Works
              involved in the above project is shown in
              the enclosed Annexure No.1."


       Annexure-I gave detailed breakup of the scope of work

awarded to the plaintiff.

11.      It would thus be noticed that though the initial offer

made by the plaintiff was for Rs.2,75,00,000/-, the work

was     awarded        to   him     for   Rs.2,87,30,000/-   which      is

Rs.12,30,000/- more than the quotation given by him and

the difference between the price and the price at which the

work      was        awarded   is     more    than   the   amount       of

Rs.5,90,000/- which the plaintiff had claimed for extra

items/earthern sludge lagoon and bituminous pavement,

vide letter Ex.PW-1/5. This becomes important since

contention of the learned counsel for the defendant was that

CS(OS)No.2448/2000                                           Page 9 of 51
 value of the work was enhanced in order to pay for the extra

work involved in the execution of contract.

12.    Ex.DW-1/P-1 is the letter of the plaintiff dated

15.3.1993 whereby he sent detailed price breakup for the

civil work awarded to him. This breakup was sent by the

plaintiff in order to facilitate progressive payment to him

during the execution of the work. A perusal of the annexure

to this letter would show that the plaintiff had divided the

amount of Rs.2,87,30,000/- into various heads and sub-

heads.     This break up is important as no item-wise value

was given either in the quotation of the plaintiff or in the

LOI issued to him by the defendant. It is not open to the

plaintiff to say that the items mentioned in this break up

were not included in the scope of work awarded to him, nor

can he claim any amount higher than the amount assessed

by him for each item mentioned in this document.

13.    Admittedly, the work was awarded to the plaintiff on

turnkey basis and a composite amount of Rs.2,87,30,000/-

was to be paid to him for the whole of the work. Unless the

plaintiff is able to show that the work claimed by him as

extra work was beyond the scope of the composite work

awarded to him on turnkey basis, he will not be entitled to

CS(OS)No.2448/2000                                 Page 10 of 51
 any extra payment.     Since the break-up submitted by the

plaintiff as annexure to his letter Exhibit DW1/P1 was

based on the awarded amount, which was higher than the

amount initially awarded by him, he can claim payment

only for that work, which was not included in the break up

sent by him to the defendant.       Of course, he would be

entitled to payment of the work, which was not included in

the break-up given by him to the defendant as well as for

the quantity which exceeded the quantity indicated in the

break-up, provided he is able to make out either a

contractual obligation or a statutory obligation on the part

of the defendant to pay to him for that extra work/extra

quantity.

14.    The case of the plaintiff is that the extra works were

executed by him on the instructions of the defendant. The

case of the defendant, however, is that no extra work was

entrusted by it to the plaintiff and the works claimed as

extra work were included within the scope of the work

awarded to the plaintiff.

15.    In his cross-examination, the plaintiff has admitted

that no prior permission was taken before executing the

extra works. The next question which then comes up is as

CS(OS)No.2448/2000                                  Page 11 of 51
 to whether the defendant had impliedly consented to pay for

the works. Exhibit PW1/9 is the letter sent by the plaintiff

to the defendant on 2nd March, 1993, referring to the

discussions held with various departments of RSP and

stating therein that the defendant had agreed for some

major changes/incorporations in the scope of civil work

having substantial extra price implication on the agreed

lump sum value.      The details of the additional work with

extra price implications were annexed as Annexure A to this

letter. The items mentioned and included in Annexure A to

this letter were sludge drying beds in place of sludge

lagoons, treated effluent sump for increased capacity,

screed concrete in channels and plaster with WPC in all

RCC tank floors, providing anti-forming system, providing

fencing around MCC/Transformer rooms with gates and

bituminous pavement, providing additional aprons around

RCC tanks and pathways as approach to units and two

coats of Epoxy Paint inside Equalization tanks. Out of these

items, screed concrete in channels and plaster with WPC in

all RCC tank floors, anti-foaming system, fencing around

MCC/Transformer rooms and pathways as approach to

units and two coats of Epoxy Paint inside Equalization

CS(OS)No.2448/2000                                 Page 12 of 51
 tanks have not been shown either in Exhibit PW1/51 or in

Exhibit PW1/128, which indicates that either these works

were not actually executed or were treated to be within the

scope of the awarded work and that is why the plaintiff has

not claimed any payment from the defendant for these

works.     Exhibit PW1/12 is the letter of the plaintiff dated

17th June, 1993, informing the defendant that the works

mentioned in the letter would be treated as extra works and

payment for them shall have to be made separately to him

over and above the agreed lump sum value. The two items

mentioned in this letter were dry pump house attached with

the sump size of 5.00 M X 5.00 M and providing necessary

support foundation and walkway platform suitable for

installation of Cooling Tower Device on the top of the sump.

However, neither of these items has been claimed in Exhibit

PW1/51 or PW1/128. Vide letter dated 7th January, 1994,

which is exhibit PW1/17, the plaintiff sought outstanding

payment along with finalization of extra work, which were

claimed to be worth Rs.32 lakhs.       Vide letter dated 25 th

July, 1994, which is exhibit PW1/21, the plaintiff again

sought payment for the extra claim raised by him.          Vide

letter dated 30th September, 1994, which is exhibit PW1/26,

CS(OS)No.2448/2000                                   Page 13 of 51
 the plaintiff again requested the defendant for finalization of

his extra claims, which he had submitted on 31 st December,

1993. This request was reiterated vide fax massage dated

9th November, 1994, which is exhibit PW1/27, fax message

dated 29th November, 1994, which is exhibit PW1/29 and

fax letter dated 12th December, 1994, which is exhibit

PW1/33.

16.    A payment of Rs.5 lakhs was made by the defendant to

the plaintiff vide cheque No.251361 dated 15 th February,

1994 drawn on Hong Kong Bank.          Vide letter dated 30th

May, 1995, which is Exhibit PW1/D-2, the defendant

claimed that this payment was to be adjusted against

further R/A bills commencing from 10 th R/A bill onwards

but inadvertently that was not done.             The plaintiff

immediately replied to this letter vide his response dated 2nd

June, 1995, which is Exhibit PW1/35 and claimed that the

payment of Rs.5 lakhs was made as advance against extra

work carried out by him and had been released after he had

submitted his claim of Rs.41 lakhs towards extra work. He

maintained that this amount could be adjusted against

payment of extra work.     There was no response from the

defendant to this letter, which leads to the inference that

CS(OS)No.2448/2000                                   Page 14 of 51
 this payment was made towards extra work. Vide letter

dated 5th August, 1997, which is Exhibit PW1/44, the

plaintiff sought payment for the extra work executed by

him.     Vide fax message dated 18th July, 1996, which is

Exhibit PW1/38, the plaintiff again sought payment for the

extra work.          Vide letter dated 17 th June, 1997, which is

Exhibit      PW1/43,       the   plaintiff   demanded   a   sum        of

Rs.51,34,500/- from the defendant towards price of extra

work after deducting a sum of Rs.5 lakhs already received

by him as advance towards these extra works. The above

referred correspondence clearly indicates that some extra

works were executed by the plaintiff to the knowledge of the

defendant. Had the defendant not given an implied consent

to any extra work, it would have adequately responded to

the letters of the plaintiff and would not have paid Rs 5

lakhs to the plaintiff towards payment of extra works.

Silence on the part of the defendant, despite repeated

correspondence and claims from the plaintiff for the extra

works alleged to have been executed by him gives an

indication of an implied consent for some payment for the

extra works by him.

17.    Assuming, however, that the extra works claimed by

CS(OS)No.2448/2000                                          Page 15 of 51
 the plaintiff were not authorized by the defendant and,

therefore, the defendant is under no contractual obligation

to pay for those works, the plaintiff is entitled to get

reasonable payment for these works in view of the

provisions contained in Section 70 of the Contract Act,

1872, which reads as under:-

                     "70.    Obligation      of    person
                     enjoying      benefit     of    non-
                     gratuitous act.-- Where a person
                     lawfully does anything for another
                     person, or delivers anything to him
                     not intending to do so gratuitously,
                     and such other person enjoys the
                     benefit thereof, the latter is bound
                     to make compensation to the
                     former in respect of, or to restore,
                     the thing so done or delivered."

18.    A bare perusal of the above referred Section would

show that three conditions need to be fulfilled before benefit

of this provision can be invoked by a person.           The first

condition is that the claimant should either lawfully do

something for another person or deliver something to him.

The second condition is that while doing or delivering

something, the claimant must not be acting gratuitously

and thirdly, the person for whom something is done or to

whom something is delivered must enjoy the thing done for

or delivered to him as the case may be.

CS(OS)No.2448/2000                                      Page 16 of 51
         Invocation of Section 70 of the Contract Act was

disputed by learned counsel for the defendant on the

ground      that     the   plaintiff   has   not   pleaded   essential

requirement of the Section.            In support of his contention

that pleading ingredients of Section 70 is a pre-condition for

its invocation, the learned counsel for the defendant has

referred to Kotah Match Factory Kotah v. State of

Rajasthan, AIR 1970 Rajasthan 118, Hansraj Gupta &

Co. v. Union of India, AIR 1973 SC 2724, Union of India

v. Sita Ram Jaiswal, AIR 1977 SC 329 and Devi Sahai

Palliwal v. Union of India and another, AIR 1977 SC

2082.

19.    In Kotah Match Factory (supra), the Rajasthan High

Court noted that the plaintiff did not raise the plea for

compensation under Section 70 of the Contract Act nor was

any issue framed, nor were the parties given an opportunity

to lead any evidence on the point.            It was found that the

case of the appellant before the Court was based upon an

agreement. It was held that since the parties had not gone

on trial on the question of compensation under Section 70

of the Contract Act, if the benefit of the aforesaid provision

is allowed at this stage, it would amount to taking the

CS(OS)No.2448/2000                                           Page 17 of 51
 opposite party by surprise.          In    Hansraj Gupta &

Co.(supra), the Supreme Court was of the view that the

conditions for the applicability of the Section 70 must at

least be set out in the pleadings and proved. In Sita Ram

Jaiswal (supra), the Supreme Court, inter alia, observed as

under:-

                     "6.      The three ingredients to
                     support the cause of action under
                     Section 70 of the Indian Contract
                     Act are these: First, the goods to
                     be delivered lawfully or anything
                     has to be done for another person
                     lawfully. Second, the thing done
                     or the goods delivered is so done
                     or delivered "not intending to do so
                     gratuitously." Third, the person to
                     whom the goods are delivered
                     "enjoys the benefit thereof." It is
                     only when the three ingredients
                     are pleaded in the plaint that a
                     cause of action is constituted
                     under Section 70 of the Indian
                     Contract Act.      If any plaintiff
                     pleads the three ingredients and
                     proves the three features the
                     defendant is then bound to make
                     compensation in respect of or to
                     restore the things so done or
                     delivered."

        In Devi Sahai Palliwal (supra), the Supreme Court

found that there was no allegation in the plaint to support

any pleading in proceeding under Section 70 of the Indian

Contract Act. Relying upon its earlier decision in Sitaram

CS(OS)No.2448/2000                                      Page 18 of 51
 Jaiswal (supra), it was held that in the absence of proper

pleadings under Section 70 of the Indian Contract Act, the

plaint should not be entertained.

20.    The learned counsel for the plaintiff on the other hand

has referred to State of West Bengal v. M/s B.K. Mondal

and Sons, AIR 1962 SC 779, V.R. Subramanyam v. B.

Thayappa and others, 3 SCR 663 and Food Corporation

of India & Others v. Vikas Majdoor Kamdas Sahkari

Mandli Ltd., 2007 (13) Scale 126.               In the case of B.K.

Mondal and Sons (supra), the Supreme Court, after

reiterating the three conditions, which need to be satisfied

before invoking Section 70 of the Contract Act, was of the

view that when these conditions are satisfied, Section 70

imposes upon the person for whom something is done or to

whom       something    is   delivered,   the    liability   to   make

compensation in respect of or restore the thing done for or

delivered to him.      During the course of the judgment, the

Court, inter alia, observed as under:-

              "14.......If a person delivers something to
              another it would be open to the latter
              person to refuse to accept the thing or to
              return it; in that case S. 70 would not
              come into operation. Similarly, if a person
              does something for another it would be
              open to the latter person not to accept

CS(OS)No.2448/2000                                           Page 19 of 51
               what has been done by the former; in that
              case again S. 70 would not apply. In other
              words, the person said to be made liable
              under S. 70 always has the option not to
              accept the thing or to return it. It is only
              where he voluntarily accepts the thing or
              enjoys the work done that the liability
              under S. 70 arises. Taking the facts in the
              case before us, after the respondent

constructed the warehouse, for instance, it was open to the appellant to refuse to accept the said warehouse and to have the benefit of it. It could have called upon the respondent to demolish the said warehouse and take away the materials used by it in constructing it; but, if the appellant accepted the said warehouse and used it and enjoyed its benefit then different considerations come into play and S. 70 can be invoked. Section 70 occurs in Chapter V which deals with certain relations resembling those created by contract. In other words, this chapter does not deal with the rights or liabilities accruing from the contract. It deals with the rights and liabilities accruing from relations which resemble those created by contract..........Therefore, in cases falling under S. 70 the person doing something for another or delivering something to another cannot sue for the specific performance of the contract nor ask for damages for the breach of the contract for the simple reason that there is no contract between him and the other person for whom he does something or to whom be delivers something. All that Section 70 provides is that if the goods delivered are accepted or the work done is voluntarily enjoyed then the liability to pay compensation for the enjoyment of the said goods or the acceptance of the said work arises. Thus, where a claim for CS(OS)No.2448/2000 Page 20 of 51 compensation is made by one person against another under S. 70, it is not on the basis of any subsisting contract between the parties, it is on the basis of the fact that something was done by the party for another and the said work so done has been voluntarily accepted by the other party. That broadly stated is the effect of the conditions prescribed by S.

70."

21. In V.R. Subramanyam (supra), the Court reiteratd the settled proposition of law that if a party of a contract rendered service to other not intending to do so gratuitously and another person had obtained some benefit, the former is entitled to compensation for the value of the services rendered by him. It was further held that even if a person has failed to prove an express agreement in this regard , the Court may still award him compensation under Section 70 of the Contract Act and such a decree for compensation would be under the statute and not under a contract.

22. In Food Corporation of India (supra), the Supreme Court, inter alia, observed as under:-

"12.....A person who does work or who supplies goods under a contract, if no price is fixed, is entitled to be paid a reasonable sum for his labour and the goods supplied. If the work is outside the contract, the terms of the contract can have no application; and the contractor is entitled CS(OS)No.2448/2000 Page 21 of 51 to be paid a reasonable price for such work as was done by him.
13. If a party to a contract has done additional construction for another not intending to do it gratuitously and such other has obtained benefit, the former is entitled to compensation for the additional work not covered by the contract. If an oral agreement is pleaded, which is not proved, he will be entitled to compensation under Section 70. Payment under this section can also be claimed for work done beyond the terms of the contract, when the benefit of the work has been availed of by the defendant."

23. In the case before this Court, though the plaintiff has not specifically pleaded the provisions of Section 70 of the Contract Act, nor has any issue been framed by the Court on its applicability, he has pleaded all the ingredients necessary for invocation of the aforesaid statutory provision. In the plaint, the plaintiff has repeatedly alleged execution of extra work for the defendant. In fact, his entire claim in the suit is based on the extra works alleged to have been executed by him for the defendant. In para 7 of the plaint, he alleged that since changes in the scope of work involved extra work and extra price implications, the letter dated 2 nd March, 1993 was written by him giving details of additional work and price implication. In para 9 of the plaint, he CS(OS)No.2448/2000 Page 22 of 51 alleged that in his letter dated 17th June, 1993, he had clearly pointed out about the payment of extra work over and above the value of the contract. Thus, the plaintiff has made it quite clear in the plaint that the extra works were not executed gratuitously and that the defendant was obliged to make payment for those works. In para 19 of the plaint, it is alleged that the extra work executed by him was duly accepted by the defendant. In para 21, he again alleged that all the works executed by him were accepted by the parties. In para 27 of the plaint, the plaintiff reiterated that the extra work was duly executed by him and accepted by the defendant. The plaintiff has, thus, pleaded all the necessary ingredients of Section 70 of the Contract Act by claiming that (i) he had executed extra works for the defendant; (2) extra works executed by him were accepted by the defendant and (3) he had not executed extra work gratuitously. The defendant could have refused to accept the extra works/extra quantities executed by the plaintiff. In that event, it would not have been liable to pay for them. But, the defendant failed to do so and accepted these works. Therefore, even if it is presumed that the defendant had not consented to pay for the extra work by the plaintiff, it is CS(OS)No.2448/2000 Page 23 of 51 obliged in law to compensate him for the extra works, which were accepted by it, without any protest and without claiming that the plaintiff will not be paid for those works.

24. Ex.PW-1/51 is the comparative charge filed by the plaintiff showing change in scope of work in various units. The charts reads as under:-

"BOD PLANT AT RSP, ROURKELA
CHANGE OF SCOPE IN VARIOUS UNITS



Sl.No.    Units                   Original   Revised     Difference
                                  Scope      Scope
1         Pump House-I            128 m2     86.45 m2    (-)41.55 m2
2         Pump House-II           192 m2     90.00 m2    (-) 102.00 m2
3.        Office-cum-Lab          300 m2     330.77 m2   (+) 30.77 m2
4.        DAF Building            Nil        255.79 m2   (+) 255.79 m2
5.        MCC Building            Nil        200.16 m2   (+) 200.16 m2

                                                         343.17 m2
6.        Treated      Effluent   40 m3      100 m3      (+) 60 m2
          Sump
7.        Sludge                  800 m2     1080 m2     (+) 280 m2
          Lagoon/Drying Bed
8.        Influent Sump           Nil        35 m3       (+) 35 m2
9.        Pump      House    at              Nil 33 m2   (+)Nil 33 m2
          Common Catch Pit
10.       Cooling Tower Basin     Nil        30.67 m2    31 m2
          Over Common Catch
          Pit



Pump House I & II

25. A perusal of the above-referred chart would show that as far as item No.1 and 2 viz. Pump House-I and Pump CS(OS)No.2448/2000 Page 24 of 51 House-II are concerned, there was reduction in the quantity of the work, for which credit has to be given to the defendant.

As per Ex.PW-1/51, the quantity of Pump House-I as per the original scope of work is 128 sq.mt. but, on revision the quantity was reduced to 86.45 sq.mt. Since the plaintiff is claiming payment for the extra work as well as extra quantity executed by him, he is required to give adjustment to the defendant for the lesser quantity executed by him. A perusal of Ex.DW-1/P1 would show that the plaintiff had quoted Rs.4 Lacs for Pump House-I. If the value of 128 sq.mt was Rs.4 Lacs, the value of 41.55 sq. mt. which is the difference between the original quantity and the revised quantity comes to Rs.129843/-. The plaintiff is required to give adjustment of this amount to the plaintiff on account of reduction in the quantity of the work for Pump House-I.

The plaintiff had assessed the value of Pump House-II at Rs.3,50,000/- for 192 m2 in Ex.DW-1/P1. If the value of 192 sq.mt. was Rs.3,50,000/-, the value of difference between the original quantity and the revised quantity of 102 sq.mt. comes to Rs.185937/-. The plaintiff is required CS(OS)No.2448/2000 Page 25 of 51 to give adjustment for this amount to the defendant. DAF Building

26. As regards item No.4 DAF Building in chart Ex. PW1/51, the case of the plaintiff as indicated in the Chart is that this item was not included in the scope of work awarded to him. However, a perusal of the Annexure to plaintiff‟s letter Ex.DW-1/P-1 would show that DAF Unit was shown as item No.5 whereas DAF Dosing Pump House was shown as item No. 15 and the plaintiff had assessed value of DAF Unit at Rs.50,000/- and that of DAF Dosing Pump House at Rs.7 lakhs. There is no evidence on record to indicate that DAF Building was different from DAF unit and DAF Dosing Pump House. Nowhere has it been alleged in the plaint that DAF Building was a work different from DAF Unit and DAF Dosing Pump. In fact, the plaintiff has not specified any alleged extra item in the plaint. As a result, the defendant had no opportunity to rebut the case of plaintiff in respect of each item claimed to be extra item. In his affidavit, the plaintiff did not say that DAF Building was different from DAF Unit and DAF Housing Pump. No other evidence was led by him to prove that these are CS(OS)No.2448/2000 Page 26 of 51 different items. Since the defendant had claimed that all the works executed by plaintiff were included in the scope of LOI, it was incumbent upon the plaintiff to prove that this was a work different from the works included in Ex DW- 1/P1. In fact, there is no evidence during trial to even prove that any such work was actually executed by the plaintiff.

27. It was contended by the learned counsel for the plaintiff that since there is no cross-examination of the plaintiff in this regard, it is not open to the defendant to dispute the execution of the extra works or to say that these works were not extra works. In support of his contention, he has relied upon the decision of this Court in Uttam Kumar vs. State 2010(3) JCC 1946 and the decision of Punjab High Court in Chuni Lal Dwarka Nath v. Hartford Fire Insurance Co. Ltd. and Anr. AIR 1950 Punjab 440. In the case of Uttam Kumar (supra), which was a criminal appeal against conviction, it was found that no question was put to the police officer as to why he took six police men along with him. Observing, that without questioning a witness on a point of controversy and eliciting a response, no argument can be built on said controversy by hinging the controversy on surmises and conjectures, this Court felt that had the CS(OS)No.2448/2000 Page 27 of 51 witness been asked, an answer would have come and then there could have been some scope for a debate. It was also found that another witness Vibhor was not cross-examined with respect to the essential portion of his testimony, which had virtually gone unrebutted. This Court, then, referred to the observations made by Punjab High Court in Chuni Lal Dwarka Nath (supra) that a party should put to each of his opponent witness so much of his case as concerns that particular witness and if no such questions are put, the Court presumes that the witness account has been accepted. However, these judgments are of no help to the plaintiff for the simple reasons that in his affidavit by way of evidence, the plaintiff did not even depose with respect to execution of the alleged extra works. He did not say that DAF building was different from DAF Unit and DAF Dosing Pump House which were shown as Item No. 5 and 15 respectively in Ex.DW-1/P1. Had the plaintiff stated that he had constructed DAF Building and that work was different from DAF Unit and DAF Dosing Pump House, only then failure of the defendant to cross-examine him in this regard could have proved detrimental to the defendant and could have accrued to the benefit of the plaintiff. The case of the CS(OS)No.2448/2000 Page 28 of 51 defendant has all along been that all the alleged extra work was within the scope of the work awarded to the plaintiff.

Moreover, during the course of arguments, I gave an opportunity to the learned counsel for the plaintiff to satisfy me, from the drawings, if available on record that DAF Building was different from DAF Unit and DAF Dosing Pump House shown in Ex.DW-1/P1. No such attempt was, however, made. Hence, DAF Building cannot be considered to be an extra item and the plaintiff is not entitled to any extra amount for this work.

MCC BUILDING

28. Item No.4 shown in chart Ex.PW-1/51 is MCC Building. A perusal of the annexure to plaintiff‟s letter Ex.DW-1/P-1 would show that MCC-cum-transformer room was shown as item No.18 in this document and the plaintiff had assessed the value of this work at Rs.8 lakhs. Again, there is no material on record to indicate that MCC Building was different from MCC-transformer room. Also, there is no evidence produced during trial, to prove execution of this work. The plaintiff did not say about execution of this work in his affidavit. He did not claim that MCC Building was different from MCC Transformer Room. No attempt was CS(OS)No.2448/2000 Page 29 of 51 made to satisfy me, from drawings, etc. that these were two separate works. Consequently, this work cannot be treated as extra item and the plaintiff is not entitled to any amount from the defendant towards payment of this work. OFFICE CUM LAB

29. As regards office-cum-lab which is item No.3 in the Chart Ex.PW-1/51, according to the plaintiff there has been increase in the scope of work since the quantity had increased from 300 sq.m. to 330.77 sq.m., the increase being 30.77 sqm. The plaintiff had assessed the value of office-cum-lab building at Rs.11 lakhs in the annexure to his letter Ex.DW-1/P-1. If the cost of 300 sqm. was Rs.11 lakhs, the cost of the extra quantity measuring 30.77 quantity would come to about Rs.1,10,000/-. The plaintiff therefore cannot claim more than Rs.1,10,000/- for this extra work. Though in his affidavit, the plaintiff did not specifically say that the quantity of this item had increased from 300 m2 to 330.77m2, I do not propose to deny the payment, since during the course of arguments before me, the contention of the learned counsel for the defendant was that the plaintiff can claim for extra quantity, only as per value assessed in Ex.DW-1/P1. This was not his contention CS(OS)No.2448/2000 Page 30 of 51 that in fact the quantity did not exceed 300 m 2. TREATED EFFLUENT SUMP

30. As regards Treated Effluent Sump which is item No. 6 in the Chart Ex.PW-1/51, the quantity according to the plaintiff had increased from 40 cubic metre to 100 cubic metre, the increase being 60 cubic metre. The plaintiff has in annexure to letter Ex.DW-1/P-1 assessed the value for Treated Effluent Sump at Rs.2 lakhs. If this was the value for 40 cubic metre, he is entitled to only Rs.3 lakhs towards payment of the extra quantity. Though in his affidavit by way of evidence, the plaintiff did not refer to execution of extra quantity of this item, I am granting this payment to him, as the contention before me was that he cannot claim at a value higher than estimated by him, and this was not the contention that there was no excess quantity of this item.

SLUDGE LAGOON/DRYING BED

31. Item No.7 shown in the Chart Ex.PW-1/51 is sludge lagoon/Drying Bed. The quantity is alleged to have increased from 800 sqm. to 1080 sqm. the increase being 280 sqm. The case of the plaintiff is that he had given value of Rs.2,50,000/- for 800 sqm. for sludge lagoon whereas he CS(OS)No.2448/2000 Page 31 of 51 has constructed sludge lagoon/ sludge drying bed measuring 1080 sqm., price of which comes to Rs.17,28,000/-. The first question which comes up for consideration in this regard is whether sludge lagoon/sludge drawing bed is different from the sludge lagoon shown in Ex.DW-1/P-1 and if so, whether the plaintiff is entitled to any extra payment for this item. The heading of item No.14 in the annexure to letter Ex.DW-1/P- 1 is sludge lagoon/drawing bed. Same is the heading given in the comparative chart. The plaintiff, therefore, cannot say that the work executed by him was different from the work for which break up was given by him. By quoting Rs.3 lakhs for sludge lagoon/drawing beds, the plaintiff clearly indicated that there were alternative works and valued this work at Rs.3 lakhs irrespective of whether it was to be sludge lagoon or drawing bed.

The plaintiff has not told the Court how drawing beds are different from the sludge lagoons. More importantly, the work indicated in EX.DW-1/P-1 is not sludge lagoon but sludge lagoon/drawing bed and same is the work alleged to have been executed by the plaintiff. Therefore, the plaintiff is entitled only to the extra quantity measuring 280 sqm. CS(OS)No.2448/2000 Page 32 of 51 Calculated at the value assessed by the plaintiff himself in Ex.DW-1/P-1, the price for the extra quantity measuring 280 sqm. would come to Rs.1,05,000/-. The plaintiff is entitled to recover only this much amount in respect of this extra quantity. Here also, though the plaintiff did not claim execution of extra quantity, in his affidavit by way of evidence, I am inclined to allow payment for extra quantity as this was not the contention before me that no extra quantity was executed.

INFLUENT SUMP

32. Item No.8 in chart Ex.PW-1/51 is Influent Sump which the plaintiff claims to be a new item. However a perusal of annexure to letter Ex.DW-1/P1 would show that influent sump was shown as items No.3 in this document and the plaintiff had assessed its value at Rs.1,00,000/-. There is neither any pleading nor evidence before the Court to show that more than one influent sump were constructed by the plaintiff. NO attempt was made to show from drawings etc. that the plaintiff had constructed an additional influent sump. Therefore he is not entitled to any amount towards this item.

CS(OS)No.2448/2000 Page 33 of 51 PUMP HOUSE AT COMMON CATCH PIT

33. Item No.9 in chart Ex.PW-1/51 is Pump House at Common Catch Pit. Though Common Catch Pit has been shown as item No.21 in annexure to letter Ex.DW1/P1, the breakup of this item does not indicate any Pump House. Therefore, if the plaintiff had constructed a Pump House at Common Catch Pit, it would be an extra item and the plaintiff would be entitled to payment for this item. During arguments, this was not the contention of the defendant that no pump house at common catch pit was constructed by the plaintiff. The plaintiff has claimed a sum of Rs.1,85,000/- for this extra item. No evidence has been led by the defendant to prove that the value of this extra item would be less than Rs.1,85,000/-. I, therefore, hold that the plaintiff is entitled to recover a sum of Rs.1,85,000/- from the defendant towards payment of this extra item. COOLING TOWER BASIN OVER COMMON CATCH PIT

34. Item No.10 shown in chart Ex.PW-1/51 is Cooling Tower Basin over Common Catch Pit, which is not included in the work indicated under item No.2, Common Catch Pit in annexure to letter Ex.DW1/P1. Again this was not the contention of the defendant that no Cooling Tower Basin CS(OS)No.2448/2000 Page 34 of 51 was constructed by the plaintiff over Common Catch Pit. The plaintiff, therefore, is entitled to payment towards this extra item. He has claimed a sum of Rs.1,20,000/- for this extra item. There is no evidence led by the defendant to show that the cost of this extra item was less than Rs.1,20,000/-. I, therefore, see no reason to disbelieve the unrebutted evidence of the plaintiff in this regard and also that he is entitled to recover a sum of Rs.1,20,000/- from the defendant towards payment of this extra item. APRON AROUND RCC TANK

35. In his comparative statement Ex.PW-1/128, the plaintiff has also claimed Rs.80,000/- towards payment for Apron around the RCC Tank. A perusal of annexure to letter Ex.DW-1/P1 would show that the plaintiff was to construct Equalization Tank-TO1B, Aeration Tank-I T05 and Aeration Tank-II T07. Apron has been shown as one of the sub items of Equalization Tank-TO1A. The plaintiff had assessed its value at Rs.50,000/-. Aprons are also shows as a part of Equalization Tank-TO1B and its value has been assessed at Rs.50,000/- Aprons has also been included in the work shown under the heading Aeration Tank-I and the CS(OS)No.2448/2000 Page 35 of 51 plaintiff has assessed its value at Rs.92,000/- for the aprons/finishing. Aprons/finishing has also been shown under Aeration Tank-II against item No.10 and the plaintiff has assessed its value at Rs.1,68,000/-. The plaintiff has not told the Court how the Apron around the RCC Tank shown by him at item No.21 in Ex.PW-1/128 is an extra item when examined in the light of the fact that he has already included aprons while giving detailed breakup of Equalization Tank-TO1B, Aeration Tank-I T05 and Aeration Tank-II T07. No evidence has been led by the plaintiff to show how many aprons he was to construct in terms of the LOI and how many were actually constructed by him. No attempt was made to satisfy me from the drawings that the any additional apron was constructed by the plaintiff. He has, therefore, failed to prove that aprons around the RCC Tank were extra items. I, therefore, hold that the plaintiff is not entitled to any payment for Apron around the RCC Tank.

BOUNDARY WALL (EXTRA QUANTITY)

36. At serial No.22 of Ex.PW-1/128, the plaintiff has claimed a sum of Rs.75,000/- towards excess quantity CS(OS)No.2448/2000 Page 36 of 51 measuring 25 RM of boundary wall. The chart indicates that the quantity as per the work order was 345 RM whereas the quantity as per the approved drawing was 370 RM. During arguments, there was no claim by the defendant that the actual quantity was not 370RM. A perusal of annexure to letter Ex.DW-1/P1 would show that the plaintiff had assessed the value of boundary wall, gates/guard room at Rs.5 Lacs. The breakup of this item would show that a sum of Rs.25,000/- was claimed towards design and drawing, Rs.50,000/- towards guard rooms and Rs.20,000/- towards gates. This would mean that the value of the boundary wall was Rs.4,05,000/- (Rs.5Lac - Rs.25,000/- - Rs.50,000/- - Rs.20,000/-). If the value of 345 RM is taken as Rs.4,05,000/- the value of the excess quantity measuring 25 RM would come to Rs.29,347/-. The plaintiff is entitled to recovery of this amount from the defendant towards excess quantity of boundary wall. RECONSTRUCTION OF BOUNDARY WALL

37. In Ex.PW-1/128, the plaintiff has claimed Rs.153217.50 towards reconstruction of boundary wall in terms of his letter dated 30 th November 1994. A perusal of CS(OS)No.2448/2000 Page 37 of 51 Ex.PW-1/23, which is the letter written by the plaintiff to defendant on 27th August 1994 shows that there was some verbal discussion between the parties regarding reconstruction of boundary wall and Bio-Oxidation plant and the plaintiff quoted a price of Rs.1,55,000/- for this work. He also gave details of the price quoted by him for this item. A perusal of Ex.PW-1/25, which is the letter sent by the defendant to the plaintiff on 31st August 1994, shows that on receipt of the letter dated 27th August 1994, the defendant requested the plaintiff to start the reconstruction of boundary wall with immediate effect. This letter does not indicate that reconstruction of boundary wall was necessitated on account of some defect in the boundary wall earlier constructed by the plaintiff. Since the plaintiff quoted a sum of Rs.1,55,000/- for reconstruction of the boundary wall and the defendant asked him to go ahead with the work, the defendant is liable to pay for this work which has to be treated as an extra work. I, therefore, hold that the plaintiff is entitled to recover a sum of Rs.153217.50 from the defendant for reconstruction of the boundary wall.

CS(OS)No.2448/2000 Page 38 of 51

38. Thus the plaintiff is entitled to recover a sum of Rs 1,10,000/- for the extra quantity of the work involved in office-cum-lab, Rs 3 lakhs for the extra quantity of the work involved in Treated Effluent Sump. Rs 1,05,000/- for the extra work involved in Sludge Lagoon/Drying Bed. Rs 1,85,000 for the Pump House at Common Catch Pit. Rs 1,20,000 for Cooling Tower Basin over Common Catch Pit. Rs 29,347/- for the extra quantity of boundary wall and Rs 1,53,217.50/- for reconstruction of boundary wall. He is entitled to give adjustment of Rs 1,29,843/-to the defendant towards revised quantity of the work involved in Pump House-I and Rs 1,85,937/- towards reduction in the quantity of work involved in Pump House-II. The balance amount payable to the plaintiff for the extra work thus comes to Rs 6,86,784.50/-

39. This is plaintiff‟s own case that he had received a sum of Rs.5 lakhs from the defendant as an advance towards the extra work executed by him. After deducting the aforesaid amount of Rs.5 lakhs from the amount of Rs 6,86,784.50/- found payable to the plaintiff. The balance principal sum payable to him comes to Rs 1,86,784.50. The issue is CS(OS)No.2448/2000 Page 39 of 51 decided accordingly.

ISSUE NO.4

40. Relying upon the receipt dated 27th August, 1997, which is exhibit PW-1/D1 the defendant has claimed that payment of Rs.9,36,900/- was accepted by the plaintiff in full and final settlement of all his claims and having done so, he is now estopped from claiming any further amount from it towards payment of the extra works. The receipt Exhibit PW1/D1 reads as under:-

" "RECEIPT"
Received with thanks the full and final payment of Rs.936900.00 (being last 5% of our contract value) vide cheque no.668151, dated: 28-08-97 drawn on Allahabad Bank, Calcutta against Civil Works of our original contract value of Rs.2,87,30,000.00 for S.N. Nandy & Co.
              Date: 29-08-97           Sd/-
                                           (S.N. Nandy)
                                             Proprietor"

41. This document, to my mind, contains an admission that the plaintiff had received Rs.9,36,900/- from the defendant towards full and final payment of the work to the extent it was covered under the LOI Exhibit PW1/6 dated 15th October, 1992. This document does not apply to the CS(OS)No.2448/2000 Page 40 of 51 claim of the plaintiff for the extra works executed by him to the extent those works were beyond the scope of the LOI dated 15th October, 1992. On receipt of this payment, the plaintiff had no claim left against the defendant with respect to those works, which were included in the scope of work awarded vide LOI dated 15.10.1992, but, it does not preclude the plaintiff from making claim for payment of extra works, which he executed for the defendant. While executing this receipt, the plaintiff did not say that he had no claim left against the defendant company with respect to civil work for Biological Oxidation Plant at R.S.P. Rourkela nor did he say that he had received payment for whole of the work executed by him at the above referred plant. The scope of the receipt was confined to the civil works, which were awarded to him vide LOI dated 15th October, 1992 and there is no justification for enlarging the scope of this document beyond what is evident from its plain and natural reading. Use of the expression "being last 5% of our contract value" and "contract value of Rs.2,87,30,000/-" in this receipt clearly indicates that what the plaintiff acknowledged was full and final payment of the contracted value and not the price of the extra works, which he had CS(OS)No.2448/2000 Page 41 of 51 executed for the defendant.

In Bharat Coking Coal Ltd. V. Annapurna Construction, (2003) 8 SCC 154, the respondent before the Supreme Court had accepted the final bill. It was contended on behalf of the appellant that the respondent having accepted the final bill, a further claim by it was inadmissible. Rejecting the contention, it was held that acceptance of final bill would not mean that the respondent was not entitled to raise any claim since the respondent had not unequivocally stated that it would not raise any further claim. The Court was of the view that in the absence of such a declaration, the respondent cannot be held to be estopped or precluded from raising any claim.

In Pandit Construction Company v. Delhi Development Authority and another, 143 (2007) DLT 270, the petitioner had made the endorsement „accepted in full and final‟ on the final bill submitted to the DDA. The claim of the petitioner was rejected by the Arbitrator on the ground that the final bill had been accepted by the petitioner as full and final settlement. The petitioner, however, maintained that this was not full and final settlement of accounts. Accepting the contention of the CS(OS)No.2448/2000 Page 42 of 51 petitioner, this Court held that a settlement, to be binding, must be recorded in clear and unambiguous terms. The Court was of the view that the endorsement „accepted in full and final‟ could also be read to mean that the amount received was in respect of full amount of the bill on which endorsement was made.

The issue is accordingly decided in favour of the plaintiff and against the defendant.

ISSUE NO.5

42. Admittedly, the defendant company had been making payment to the plaintiff from time to time. The documents filed by the plaintiff show that the payments used to be made by cheques. The following payments were made by the defendant to the plaintiff between 1994-1997 :-

      Cheque No.            Date              Amount
                                                (Rs.)
       527145            18.01.1994          4,00,000/-
       527175            27.01.2994          5,43,670/-
       527338            04.02.1994          5,32,421/-
       527431            18.02.1994          5,00,000/-
       038274            15.03.1994          5,00,000/-
       038339            23.03.1994          4,00,000/-
       038628            20.04.1994          9,49,762/-
       490273            27.05.1994          3,27,945/-
       446810            04.08.1994          5,65,023/-


CS(OS)No.2448/2000                                    Page 43 of 51
        575449            13.10.1995           15,00,000/-
       575430            11.10.1995           3,00,000/-
       575450            13.10.1995           3,20,162/-
       212246            10.11.1995           2,54,749/-
       212247            10.11.1995           4,00,000/-
       650410            23.07.1996            83,659/-
       668151            28.08.1997           9,36,500/-



43. Section 19 of the Limitation Act, to the extent it is relevant, provides that where payment on account of a debt is made before the expiration of the prescribed period, by the person liable to pay the debt or by his agent duly authorized in this behalf, a fresh period of limitation would be computed from the time when the payment was made. The last payment having been made by the defendant is on 28th August, 1997, a fresh period of limitation if computed from this date would expire on 28th August, 2000. The suit having been filed on 26th May, 2000 is, therefore, well within time. Though it was contended by the learned counsel for the defendant that the payment on 28th August, 1997 was made after the limitation prescribed for filing a suit of this nature had expired, that obviously is incorrect since payments by way of cheques were made by the defendant from time to time and at no occasion there was gap of three CS(OS)No.2448/2000 Page 44 of 51 or more years between the two payments. In this regard, it would be pertinent to note that though the extra works executed by the plaintiff were out of the scope of work contained in the LOI dated 15th October, 1992, the amount payable by the defendant to the plaintiff towards the civil work executed by him at Biological Oxidation Plant at R.S.P. Rourkela was one debt and though having two components, one for the works covered in the scope of LOI and the other for the works which were beyond the scope of LOI cannot be said that the payment for the work included in the scope of work awarded vide LOI dated 15 th October, 1992 was one debt and payment for the extra work executed by the plaintiff was another debt. The project executed by the defendant for the plaintiff was one project, i.e., civil work at Biological Oxidation Plant at R.S.P. Rourkela and, therefore, payment for the entire quantity irrespective of whether for the work included within the scope of work indicated in the LOI or for the work beyond the scope of LOI, constituted one debt, which the defendant owed to the plaintiff. Therefore, even the payment was made by the defendant to the plaintiff towards price of the contractual work, which was included in the LOI it would extend the period of limitation also for CS(OS)No.2448/2000 Page 45 of 51 the extra work executed by the plaintiff while carrying out civil work at Biological Oxidation Plant at R.S.P. Rourkela. It would also be pertinent to note here that this is not the requirement of law that while making a payment, the debtor must make it towards part payment. Any payment, irrespective of, whether it is made as part payment or otherwise, would extend the period of limitation under Section 19 of the Limitation Act. In this regard I may refer to the decision of the Privy Council in Rama Shah v. Lal Chand, AIR 1940 Privy Council 63 where the Court, inter alia, observed as under:-

"In the Limitation Act, Section 19, which deals with acknowledgments, is not to be read as based upon the theory of implied promise: and it is difficult to see why Section 20, which deals with payments, should be regarded as based upon a theory of acknowledgment. The Indian Legislature may well have thought that a payment if made on account of the debt and evidenced by writing gave the creditor some excuse for further delay in suing, or was sufficient new proof of the original debt to make it safe to entertain an action upon it at a later date than would otherwise have been desirable. The words in Section 20 by which the matter must be judged are "where part of the principal of a debt is paid". As it is not prescribed by the Section that the payment should be intended by the debtor to go towards the principal debt at all, the words 'as such' CS(OS)No.2448/2000 Page 46 of 51 having no place in this part of the Section, it is not in their Lordships' view correct to require that the payment should have been made of part as part."

44. In support of his contention that the suit is barred by limitation, learned counsel for the defendant has referred to Major (Retd.) Inder Singh Rekhi v. Delhi Development Authority, (1988) 2 SCC 338, Satender Kumar v. Municipal Corporation of Delhi and another, 168 (2010) DLT 15, and Hansa Vision Pvt. Ltd. V. Dabur (India) Limited & Ors, 168 (2010) DLT 562.

45. In the case of Inder Singh Rekhi (supra), the Court was dealing with a petition under Section 20 of the Arbitration Act, 1940. During the course of judgment, the court observed that on completion of the work a right to get payment would normally arise but where the final bills have not been prepared, the cause of action would arise from the date when the assertion of the claim was made. It was further observed that a party cannot postpone the accrual of cause of action by writing reminders or sending reminders but where the bill has not finally prepared, the claim made by the claimant is the accrual of cause of action.

In the case of Satender Kumar (supra), this Court, CS(OS)No.2448/2000 Page 47 of 51 after referring to the decision of the Supreme Court in the case of Inder Singh Rekhi (supra), inter alia, held as under:-

"16(iii) As regards contracts for execution of building work, Article 18 comes into play in that when no specific date for payment is fixed, limitation commences and the cause of action accrues for the purpose of limitation on the completion of work.
(iv) In its application, Article 18 will cause different dates for accrual of causes of action in building works when a time period is fixed for submitting of a bill by the contractor and to which there is no response to the owner. Where a final bill is submitted and liability under the same, even if, in part, is admitted or some payment is made then such actions extend limitation in terms of Section 18 of the Limitation Act."

In the case of Hansa Vision Pvt. Ltd. (supra), this Court, referring to Article 113 of the Limitation Act, 1963, observed that the period of limitation is 3 years to be computed from the date when right to sue accrues, wherever the aforesaid Article applies.

All these judgments tend to support the contention of the learned counsel for the defendant that in a suit for price of work executed by contractor, Article 18 of the Limitation Act would be the relevant Article, which provides a period of CS(OS)No.2448/2000 Page 48 of 51 limitation of 3 years from the date when the work is done, where no time has fixed for payment. They also support his contention that a party cannot postpone the accrual of cause of action by writing letters and reminders seeking payment from the other party and once the period of limitation starts running, mere sending reminders would not postpone the accrual of cause of action even if the defendant does not dispute his liability in this regard. However, the benefit of Section 19 of Limitation Act cannot be denied to the plaintiff even if Article 18 of the Limitation Act is applied to the case. The issue is decided against the defendant and in favour of the plaintiff.

ISSUE NO.3

46. The plaintiff has claimed interest @ 18% per annum for the period from 31st December, 1993 to 31st March, 2000 on the amount of Rs.41,98,000/- and from 30th November, 1994 to 31st March, 2000 on the amount of Rs.1,53,217/- thereby making a total sum of Rs.48,69,345/- towards interest. The plaint does not disclose the basis on which interest has been claimed by the plaintiff. Admittedly, there is no agreement between the parties for payment of interest. No custom or usage of trade with respect to payment of CS(OS)No.2448/2000 Page 49 of 51 interest has either been pleaded or proved by the plaintiff. It is settled proposition of law that in a civil suit interest cannot be awarded as damages. However, interest can be awarded by the Court under the provisions of the Interest Act, 1978. Section 3 of the Interest Act, 1978, to the extent it is relevant, provides that in any proceedings for the recovery of any debt in which the claim of interest in respect of any debt is made, the Court may, if it thinks fit, allow interest to the person entitled to the debt on a rate not exceeding the current rate of interest. If the proceedings relate to a debt, which is not payable by virtue of a written instrument at a certain time, interest can be awarded for the period from the date mentioned in this regard in a written notice given by the person entitled or making the claim to the person liable that interest will be claimed, till the date of institution of the proceedings. Vide his letter dated 18th July, 1996, the plaintiff informed the defendant that the losses incurred by him were being worked out in terms of interest and the same shall be intimated to it. The details of interest were then sent by the plaintiff to the defendant vide its letter dated 20th July, 1996, which is Exhibit PW1/39. He claimed interest @ 24% per annum. I, CS(OS)No.2448/2000 Page 50 of 51 therefore, feel that interest should be awarded to the plaintiff from 20th July, 1996 till the date of filing of this suit at the rate of 12% per annum. Calculating accordingly the amount of interest at the rate of 12% per annum on the principal amount of Rs.1,86,784.50/-, interest for the period from 20th July, 1996 to 26th May, 2000 comes to Rs.86,294.44p. The plaintiff is entitled to recover total amount of Rs.2,72,078.94p from the defendant.

ORDER For the reasons given in the preceding paragraphs, a decree for a sum of Rs.2,72,078.94p with proportionate costs and pendente lite and future interest at the rate of 12% per annum is passed in favour of the plaintiff and against the defendant.

Decree sheet be prepared accordingly.

(V.K. JAIN) JUDGE FEBRUARY 23, 2011 bg/sn/AG/vkm' CS(OS)No.2448/2000 Page 51 of 51