fa212.08.odt 1/3
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
NAGPUR BENCH, NAGPUR
FIRST APPEAL No.212 OF 2008
1. The State of Maharashtra.
2. The Special Land Acquisition Officer,
Minor Irrigation Works, Buldana. : APPELLANTS
...VERSUS...
1. Manikrao Kaduba Tayade (dead)
Legal Representatives :
(1) Smt. Kasturabai Manikrao Tayade,
Aged 58 years.
(2) Sau. Lankabai Devidas Bawaskar,
Aged 38 years.
(3) Subhash Manikrao Tayade,
Aged 35 years.
(4) Sau. Sugandhabai Subhash Raut,
Aged 33 years.
(5) Sau. Ushabai Dattatraya Bhonde,
Aged 30 years.
(6) Ku. Asha Manikrao Tayade,
Aged 25 years.
(7) Ku. Manisha Manikrao Tayade,
Aged 20 years.
(8) Ku. Jijabai Uttamrao Dahatonde,
Aged 43 years.
(9) Chandrakala w/o. Ambadas Kanadje,
Aged 58 years.
Smt. Kasturbai Manikrao Tayade,
All R/o. Kardi, Tq. & Distt. Buldana. : RESPONDENTS
=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-
Shri M.A. Kadu, Asstt. Government Pleader for the Appellant.
None appears for respondents
=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-
::: Uploaded on - 06/12/2017 ::: Downloaded on - 08/12/2017 01:14:35 :::
fa212.08.odt 2/3
CORAM : S.B. SHUKRE, J.
th DATE : 30 NOVEMBER, 2017.
ORAL JUDGMENT :
1. This is an appeal which challenges the legality and correctness of the judgment and order dated 13.4.2004 commonly passed in about 81 land acquisition cases by the Civil Judge, Senior Division, Buldhana. This appeal arises out of the Land Acquisition Case No. 60 of 1996, decided by the Reference Court.
2. The acquired land in the present case forms a chunk of all the lands acquired for the purpose of construction of a water tank at mouza Kardi, Tahsil and District Buldhana. In First Appeal No. 153 of 2008 and First Appeal No. 209 of 2008, decided on 29th November 2017, arising out of the same judgment and order, as impugned herein, this Court has confirmed the rates of land, well and trees determined by the Reference Court. The rate of land with irrigation facility has been determined by the Reference Court to be at Rs. 90,000/- per hectare while it is ::: Uploaded on - 06/12/2017 ::: Downloaded on - 08/12/2017 01:14:35 ::: fa212.08.odt 3/3 determined at Rs. 75,000/- per hectare for dry-crop land and these rates have been confirmed by this Court.
3. The acquired land in the present case, as stated earlier, is a part of the larger chunk of the lands acquired for water tank project at mouza Kardi. It was a land having irrigation facility where there were standing trees and well. It being similar to those lands as are involved in First Appeal No. 153 of 2008, there is no reason for this Court to take a different view of the matter. The facts of this case and the facts involved in the said appeals, particularly, FA No. 153 of 2008, are not disputed by learned Assistant Government Pleader for the appellant-State and so, this appeal would have to be decided on the similar lines.
4. In the circumstances, I find that this appeal deserves to be dismissed and it is dismissed accordingly. No costs.
S. B. SHUKRE, J joshi ::: Uploaded on - 06/12/2017 ::: Downloaded on - 08/12/2017 01:14:35 :::