Citation : 2022 Latest Caselaw 3380 Tel
Judgement Date : 5 July, 2022
THE HON'BLE SRI JUSTICE A.ABHISHEK REDDY
ARBITRATION APPLICATION Nos.86 and 169 of 2021
COMMON ORDER:
These applications are filed under the provisions of the
Arbitration and Conciliation Act, 1996 (for short 'the Act'),
seeking appointment of an Arbitrator.
2. It is the case of the applicant that three companies,
namely, SEW Infrastructure Limited (respondent in AA.No.86 of
2021), M/s. Navayuga Engineering Company Limited
(respondent in AA.No.169 of 2021) and IVRCL Infrastructure &
Projects Limited, formed a Consortium and entered into a joint
venture agreement for executing the portion of electro-
mechanical work pertaining to various pump houses relating to
Sripada Sagar Project Stage-II Phase-I. The Consortium, in
turn, has initially awarded a work to the applicant for carrying
out survey, design, model, study, manufacturing, supply,
erection, testing, commissioning, operation and maintenance of
complete Electro Mechanical works relating to the Project, vide
work order dated 27.12.2008, and the same has been accepted
by the applicant in terms thereof. Accordingly, the applicant
has started execution of the work on time and has raised
Running Account (RA) bills. However, the Consortium, despite
several reminders and requests, has failed to release the
amounts due to the applicant even after receiving the same from
its employer. Therefore, with the intervention of the employer,
the Consortium and the applicant entered into a Settlement
Agreement and pursuant thereto, the respondents have made
part payments. While so, on 16.04.2016 the Consortium has
issued a fresh work order for supervision charges in favour of
the applicant and again committed default in payment of
supervision charges. Despite several reminders, the respondents
herein did not respond. Therefore, the applicant has issued
notices to the respondents invoking arbitration clause. The
respondent in AA.No.86 of 2021, after receipt of the notice
issued reply dated 22.12.2020, denying the allegations raised by
the applicant and rejecting the nomination of senior advocate as
Sole Arbitrator and instead, sought consent to nominate and
appoint a former Judge of High Court of Madras as Sole
Arbitrator to adjudicate the dispute. Whereas, the respondent
in AA.No.169 of 2021, after receipt of the notice, did not issue
any reply, however gave its consent to appoint an Arbitrator or
in alternate to nominate an Arbitrator of its choice. In those
circumstances, the applicant has filed the present Arbitration
Applications.
3. Learned counsel for the applicant has stated that as per
the Settlement Agreement dated 11.03.2016 entered into
between the parties, in particular Sub-Clause (12) of Clause 8,
in case there is any dispute between the parties, the same shall
be referred to a Sole Arbitrator. Learned counsel has also
drawn the attention of the Court to Sub-Clause (10) of Clause 8
the Settlement Agreement and has laid special emphasis on the
word "severally" to buttress his contention that even though the
Settlement Agreement is between the applicant on the one hand
and the Consortium of three companies, consisting of
M/s. IVRCL Limited, M/s. Navayuga Engineering Company
Limited and M/s. SEW Infrastructure Limited on the other
hand, the present arbitration applications are filed only against
M/s. SEW Infrastructure Limited (respondent in AA.No.86 of
2021) and M/s. Navayuga Engineering Company Limited
(respondent in AA.No.169 of 2021). Learned counsel has
further stated that the liability of the individual members of
Consortium has been clearly segregated and defined in Clause
(6) of the Settlement Agreement, which provides that the
individual partner shall pay its respective portion of the
retention amount to the applicant within seven days from the
date of receipt the same. Learned counsel has stated that the
applicant has rightly invoked the arbitration clause and
moreover the respondents while agreeing for arbitration, have
suggested a different Arbitrator other than the one proposed by
the applicant, however subsequently, after filing of the present
Arbitration Applications, the respondents have taken a
somersault and are opposing the same stating that the
Settlement Agreement is entered into between all the
constituents of the Consortium jointly on the one hand and the
applicant on the other hand and not between the individual
constituents of the Consortium, therefore, the arbitration clause
cannot be invoked, as against the individual member of the
Joint Venture and the same is legally untenable in view of the
Clause (6) and Sub-Clause (12) of Clause (8) of the said
Settlement Agreement.
4. Per contra, learned counsel appearing on behalf of the
respondents has vehemently opposed the arbitration
applications in the present form and stated that there is no
written agreement between the individual constituents of the
Consortium/Joint Venture and therefore, there is no liability of
the single constituent against whom the Agreement can be
invoked. The applicant cannot invoke the arbitration clause
against the individual constituents of the Consortium but only
against the Joint Venture. He submits that the remedy
available to the applicant is to file a Civil Suit before the Civil
Court against the Individual Member of the Consortium and not
the present arbitration applications. Learned counsel has laid
special emphasis on Section 7 of the Act and has also relied on
the judgment of the Bombay High Court in the case of Larsen &
Toubro Ltd. vs. Mumbai Metropolitan Region1 to buttress his
contention that the present applications are not maintainable
and are liable to be dismissed.
5. In order to appreciate the various contentions raised by
the learned counsel for the parties, it is necessary to extract the
relevant portion of the Settlement Agreement, more particularly
Clauses (6) and Sub-Clauses (10) and (12) of Clause (8), which
read as under:-
"(6). It is further clarified that each of the JV partners shall pay to KBL its respective portion of the said Retention amount, as more particularly described in this Agreement, within 7 days from the day the individual Partner receives it from the department namely I & CADD.
8(10). This Agreement shall be legally enforceable and valid till the completion of the Project and release of all the above stated amounts to KBL by the said IVRCL, NEC and SEW, as the case may be severally- and this Agreement shall not be terminated by either Party for whatsoever reasons.
8(12). In the case of any dispute between the Parties herein with respect to the interpretation of the contents of this Agreement, then the Senior Executives of the Parties herein shall endeavour to settle the dispute through a mutual dialogue. If, however the dispute remains unresolved for a period of 15 days, the same will be referred to Arbitration under Arbitration & Conciliation Act, 1996, and/or any modifications and amendments thereto and the same shall be conducted by a sole Arbitrator appointed mutually by all the Parties
2016 SCC OnLine Bom 13348
herein within the next 10 days. If the parties are not able to decide upon a single Arbitrator within these 10 days, then they will approach a court of competent jurisdiction, for appointment of this sole Arbitrator. The language of Arbitration shall be English. It is agreed that the Award of the Arbitrator shall be binding on all the Parties herein."
(Emphasis added)
6. A combined reading of the above Clauses clearly shows
that irrespective of the fact whether the present arbitration
applications are filed against the individual constituents of the
Consortium or against the Consortium as a whole, a plain
reading points to the fact that the arbitration clause can be
invoked against the individual constituent of the Consortium,
more so as the liability of the individual partner is segregated,
quantified and defined in the Settlement Agreement and as per
Sub-Clause (10) of Clause (8) of the Settlement Agreement
which provides that the agreement is legally enforceable
"severally". Moreover, in reply to the notices issued by the
applicant invoking the arbitration clause, the respondents have
themselves agreed for appointment of Arbitrator but only sought
for appointment of a different person from the one proposed by
the applicant.
7. Having regard to the above, the contention of the learned
counsel for the respondents that there is no enforceable written
agreement between the parties and the only remedy available to
the applicant is to file a Civil Suit before the Civil Court is not
correct. Even the judgment relied on by the learned counsel for
the respondents in Larsen & Toubro Ltd.'s case (supra) is
clearly distinguishable with that of the facts in the present case
and the same has no application. As a matter of fact, the
learned Single Judge in that very same judgment, relying on the
judgment rendered by that very High Court in the case of Oil
and Natural Gas Corporation Ltd. vs. Saw Pipes Ltd., has
held as under:-
"...wherein similar objection has been turned down by this Court by holding that the petition filed by one of the members of the consortium was maintainable. In the judgment cited this Court at paras 12 and 13, extensively referred to the terms for the contract between the parties before it and on the basis thereof concluded that the claim in the arbitral proceedings was restricted. The constituents of the consortium in fact under the agreement itself were entitled to different and exclusive payments for each. As such the claim in the arbitral proceedings was restricted to the claim to which the constituent of the Consortium alone was entitled to. It did not form part of the claim relating to any amount which was due and outstanding to the other constituent of the Consortium. Hence, the arbitral proceedings were held to be correctly initiated by a constituent. The facts of the case on hand are exactly contrary."
Therefore, the contention of learned counsel for the respondents
that the arbitration clause cannot be invoked against the
individual constituent of the Joint Venture/Consortium is
without any legal basis, more so, as the individual liability of the
Joint Venture partners is clearly defined.
8. In the aforesaid fact situation, and in view of Section 10 of
the Act, a sole Arbitrator is required to be appointed. Since the
parties are not in agreement as to the identity of the Arbitrator,
this Court has to take requisite measure under Section 11(6) of
the Act to make such appointment.
9. In the result, the Arbitration Applications are ordered
appointing Sri Justice A. Rajasheker Reddy, retired Judge of the
High Court for the State of Telangana, as the sole Arbitrator to
arbitrate on the disputes between the applicant and the
respondents and the said Arbitrator shall enter on reference and
proceed with, as enjoined by the Act.
10. The learned Arbitrator shall fix his remuneration as per
the statutory provisions. He shall also fix the costs and
expenses of the secretarial assistance for the arbitration
proceedings upon deliberation and consultation with the
parties. All the costs and expenses of the arbitration
proceedings shall be borne by both the parties in equal share.
The Learned Arbitrator is requested to complete arbitration
proceedings, and pass an award at the earliest, preferably
within six months from the date of commencement of the
arbitral proceedings.
Miscellaneous Applications, if any, pending in the
Arbitration Applications, shall stand closed. No order as to
costs.
_________________________ A.ABHISHEK REDDY, J
05.07.2022 JSU
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!