Tuesday, 09, Jun, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Smt. Seetha Sulochana vs The State Of Telangana
2021 Latest Caselaw 2313 Tel

Citation : 2021 Latest Caselaw 2313 Tel
Judgement Date : 10 August, 2021

Telangana High Court
Smt. Seetha Sulochana vs The State Of Telangana on 10 August, 2021
Bench: Hima Kohli, B.Vijaysen Reddy
           HIGH COURT FOR THE STATE OF TELANGANA

         THE HON'BLE THE CHIEF JUSTICE HIMA KOHLI
                                    AND
         THE HON'BLE SRI JUSTICE B. VIJAYSEN REDDY

                   WRIT APPEAL No.220 of 2021


                              Date: 10.08.2021
BETWEEN

Smt. Seetha Sulochana.


                                                         ... APPELLANT
AND


The State of Telangana,
Rep. by its Principal Secretary,
Revenue Department,
Secretariat, Hyderabad
and others.

                                                      ...RESPONDENTS

Counsel for the Appellant : Mr. Srikanth Hariharan

Counsel for the Respondents : GP for Revenue

The Court made the following:

JUDGMENT: (Per Hon'ble Sri Justice B. Vijaysen Reddy)

This writ appeal is filed challenging the order of the learned

Single Judge dated 13.05.2021 dismissing WP.No.11582 of 2020, filed

by the appellant.

2. The parties herein are referred to as arrayed before the learned

Single Judge. The brief facts of the case are as under:

(a) The petitioner is the owner, possessor and pattadar of

agricultural land admeasuring Ac.4.29 guntas in Sy.No.98 and Ac.7.38

guntas in Sy.No.99, situated in Damarkunta Village, Markuk Mandal,

Siddipet District, having purchased the same under a registered sale

deed dated 12.03.2021, for a valuable consideration. Pattadar pass

book and title deeds were also issued in her favour. The land has 1600

mango trees, 700 red sandal wood trees, 800 teak trees, 100 guava

trees and various other vegetable crops. The petitioner received a

notice dated 06.04.2000, issued by the Authorized Officer and

Revenue Divisional Officer, Gajwel/respondent No.2 informing her that

an extent of Ac.0.14 guntas in Sy.No.98 and Ac.0.11 guntas in

Sy.No.99 (subject land) has been notified to be acquired for

construction of a canal from Kondapochamma Reservoir of the

Kaleswaram Project at Thurkapally.

(b) It is the case of the petitioner that she was straightaway

called upon to receive the compensation for acquisition from the

Tahsildar/respondent No.3 on 07.05.2020. The petitioner did not

received any notice of acquisition nor was she granted a hearing. She

was not aware of any paper publication in the newspaper, allegedly

made. On 07.05.2020, she submitted objections before the Tahsildar,

followed by the objections dated 20.05.2020 submitted to the RDO;

further objections dated 17.06.2020 were submitted before the

Engineer-in-Chief, Irrigation Department/respondent No.4 as well as to

the Executive Engineer, KPCD-2 Department/respondent No.5. In her

objections, the petitioner stated that that large extent of Government

land is available on the western and northern side of her land and if

the canal alignment is taken through the side of the Government land,

a huge saving in land acquisition can be made besides saving valuable

land and her mango, guava and teak garden. The land to be acquired

in such a case would be only marginal, the re-alignment of the canal,

in such circumstances, would be minimal and no prejudice would be

caused to any party.

(c) On an enquiry by the petitioner, she came to know that a

notification dated 19.07.2019 was published in the Andhra Prabha, a

Telugu daily newspaper proposing to acquire the subject land.

Notification dated 02.03.2020 was published in Manam, a Telugu daily

newspaper wherein it was mentioned that Ac.0.14 guntas in Sy.No.98

and Ac.0.11 guntas in Sy.No.99 would be acquired out of the

petitioner's land. There is contradiction and confusion with regard to

the extent of land to be acquired, which was not clarified. Notice dated

06.04.2020 issued by the respondent No.2 makes another

contradictory claim calling upon petitioner to receive compensation for

Ac.0.14 guntas in Sy.No.98 and Ac.0.11 guntas in Sy.No.99. The

petitioner stated that the alignment of canal was being changed for

oblique reasons and in an arbitrary fashion.

(d) It was further stated that the RDO had highhandedly issued

a notice No.D4/1382/2019 dated 30.06.2020 under Section 23 and 30

of the Right to Fair Compensation and Transparency in Land

Acquisition, Rehabilitation and Resettlement Act, 2013 (for short 'the

Act of 2013') through whatsapp on 14.07.2020, calling upon the

petitioner to collect the cheque for compensation within seven days

from the date of receipt of the said notice. She went to submit a reply

but the officials refused to receive the same. She was constrained to

post the reply through RPAD. The petitioner filed a rough sketch plan

along with a petition and submitted that as against the red colour

marked a "proposal", if the green colour marked, as "earlier proposal",

is taken into consideration, her land would be affected partially. She

has also shown a yellow colour proposal for realignment, by which

there would be least impact on the cost of acquisition thereby saving

her valuable land. The said representation of the petitioner was

however not considered.

(e) A counter affidavit was filed by the respondent No.2 stating

inter alia that the preliminary notification under Section 11(1) of the

Act of 2013 was issued and published on 19.09.2019 in the two daily

newspapers i.e. the Andhra Prabha and the Times of India on

19.09.2019 notifying Ac.1.20 guntas in Sy.Nos.43, 98 and 99 of

Damarkunta Village, Markuk Mandal, which includes the subject land of

the petitioner. Insofar as Sy.No.98 is concerned, Ac.0.14 guntas of

patta land belonging to the petitioner was notified and insofar as

Sy.No.99 is concerned, Ac.0.14 guntas was notified in the name of

seven persons jointly, based on the enjoyment and the revenue

records. Subsequently, the Grama Sabha was conducted under Section

11(2) of the Act of 2013 on 14.02.2020. Neither during the Grama

Sabha or within 60 days from the date of issuance of the preliminary

notification, was any objection received from the petitioner or by any

of her representatives. Declaration under Section 19(1) was published

in two daily newspapers i.e. "Manam" and "The Hans India" on

02.03.2000. The same was also published in the District Gazette

No.120/2020 dated 25.02.2020 and duly uploaded on the District

website for an extent of Ac.1.17 guntas as against Ac.1.20 guntas

notified in the preliminary notification, as Ac.0.03 guntas of land in

Sy.No.43 was resumed, being assigned land. In the said declaration,

Ac.0.14 guntas of patta land belonging to the petitioner in Sy.No.98

was declared for acquisition and in Sy.No.99, only Ac.0.11 guntas was

declared for acquisition in the name of the petitioner, for the reason

that the remaining extent of Ac.0.03 guntas was found to be in

possession and patta in the name of Smt. Guduru Padma. Thus, there

was a variation of Ac.0.03 guntas in the preliminary notification and

the final declaration in the name of the petitioner.

(f) Notices were issued to the concerned land losers including

the petitioner on 06.04.2020, to attend the Award enquiry on

07.05.2020 at the Office of the Tahsildar, Markook Mandal. During the

said enquiry, the petitioner filed a petition and requested for a change

of the alignment of the proposed canal. The said objections were

considered as per Section 23 of the Act of 2013 and were rejected.

Accordingly, the draft award to an extent of Ac.1.17 guntas was

prepared on 15.06.2020 and submitted to the District Collector,

Siddipet, for approval. The same was approved by the District

Collector and the award was pronounced on 29.06.2020. The

respondent stated that notices dated 30.06.2020 have been issued to

the concerned land losers including the petitioner, requesting them to

receive the award compensation within seven days.

3. The learned Single Judge dismissed the writ petition holding that

the subject land of the petitioner was acquired by duly complying with

the provisions of the Act of 2013. There was substantial compliance of

mandatory requirements under Sections 11 and 19 of the Act of 2013.

The petitioner did not file any objection for issuance of Section 11

notification. Therefore, the question of dealing with the objections

under Section 58 of the Act of 2013, does not arise. It was further

observed that the Court sitting under Article 226 of the Constitution of

India cannot go into technical aspects with regard to the alignment of

the canal. It is for the technical experts to deal with the technical

aspects and not for the Courts to propose some other alternate route

or design.

4. Mr. Srikanth Hariharan, learned counsel for the appellant,

submitted before the court that the impugned acquisition proceedings

are illegal and contrary to the provisions of the Act of 2013. The

notification of acquisition of the land was not affixed or published at

conspicuous places in the affected area, which is a mandatory

requirement under the Act of 2013. The learned Single Judge has

erred in holding that there is substantial compliance. The provisions of

the Act of 2013 have to be strictly followed and they are mandatory in

nature. Hence, there is a violation of Article 300-A of the Constitution

of India. Change in alignment as proposed by the appellant, is not a

technical aspect of acquisition. In fact, it reduces the cost of

acquisition. He contended that the respondents have unilaterally

changed the alignment of the canal without notice to the appellant.

The provisions of the Act of 2013 have not been complied with. Mere

affixation of notice in the Gram Panchayat Office is not sufficient

compliance. It was also submitted that the judgment of the Supreme

Court in J & K HOUSING BOARD v. KUNWAR SANJAY KRISHAN

KAUL1 has not been considered by the learned Single Judge.

5. On the other hand, the learned Government Pleader submitted

that the subject lands of the appellant had been acquired strictly in

compliance with the provisions of the Act of 2013. The appellant was

(2011) 10 SCC 714

aware of the acquisition proposed; notices were served on her; she

had submitted objections and participated in the award enquiry. Thus,

the allegation of the appellant about non-compliance of the provisions

of the Act of 2013, is without any basis and there are no merits in the

writ appeal.

6. We may note from the facts of the case that the preliminary

notification under Section 11(1) of the Act of 2013 was issued

proposing to acquire the subject lands of the appellant. The same was

published in the "the Andhra Prabha" and "the Times of India", daily

news papers on 19.09.2019, which was followed by a declaration

under Section 19(1) of the Act of 2013 published in two daily

newspapers "Manam" and "The Hans India". Notice of award enquiry

dated 06.04.2020 was issued personally to the appellant. It is not in

dispute that the appellant had received the said notice. There is no

denial to the statement of the respondent No.2 made in the counter,

that the Grama Sabha was conducted on 14.02.2020 under Section

11(2) of the Act of 2013 and no objections were received from the

appellant during the meeting of the Grama Sabha or within 60 days

from the date of the preliminary notification. After receipt of a notice

dated 06.04.2020 issued under Section 21(4) of the Act of 2013 and

Rule (26) of the Rules framed thereunder, the appellant submitted

objections on 07.05.2020. Subsequently, objections dated 20.05.2020

were submitted by her before the respondent No.2. Later, further

objections were filed by the appellant on 03.06.2020. In her

objections, the appellant stated that the alignment of the canal can be

changed, as there is dry land available towards southern and western

side of her land and the western land belongs to the Government. It

needs to be noted that in none of these three objections did the

appellant raise any grievance regarding non-compliance of the

provisions of the Act of 2013.

7. In view of the above, this Court is of the opinion that the

mandatory procedure, as contemplated under the Act of 2013, has

been duly complied with by the respondents. The appellant was

afforded reasonable opportunity to submit her objections. After receipt

of the award enquiry notice, the appellant chose to submit three

representation/objections seeking a change of alignment. The

judgment of the Supreme Court in J & K HOUSING BOARD's case

(1 supra) is of no help to the appellant as there is no violation of the

provisions of the Act of 2013. As pointed out by the learned Single

Judge, the Court cannot enter into the realm of technicalities. It is for

the technical experts to deal with the alignment and designs. The

argument of the learned counsel for the appellant that Article 300-A of

the Constitution of India has been violated, is without any basis. The

record discloses that the provisions of the Act of 2013 have been

complied with. There is no scope for this Court to interfere with the

impugned acquisition proceedings and the order of the learned Single

Judge.

8. The writ appeal is found to be devoid of merits and it is

accordingly dismissed. Pending miscellaneous petitions, if any, shall

stand closed with no order as to costs.

_____________ HIMA KOHLI, CJ

__________________ B. VIJAYSEN REDDY, J

August 10th, 2021

DSK

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : MAIMS

 
 
Latestlaws Newsletter