Citation : 2012 Latest Caselaw 6849 Del
Judgement Date : 30 November, 2012
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ ARB.P. 123/2012
M/S MFAR CONSTRUCTIONS PVT. LTD. ..... Petitioner
Through: Ms. Indu Malhotra, Sr. Adv.
with Ms. Mahalakshmi Pavani,
Mr. G. Balaji, Mr. Vanshdeep
Dalmia and Mr. Kush
Chaturvedi, Advocates.
versus
DIRECTOR GENERAL
(Married Accommodation Project) ..... Respondent
Through: Mr. Anuj Agarwal with
Mr. Gaurav Khanna,
Advocates.
% Date of Decision : November 30, 2012
CORAM:
HON'BLE MS. JUSTICE REVA KHETRAPAL
JUDGMENT
: REVA KHETRAPAL, J.
1. The abovementioned petition has been filed by the petitioner
under Section 11 of the Arbitration and Conciliation Act, 1996
praying for the appointment of a sole Arbitrator to adjudicate on the
arbitrable disputes, which have arisen between the petitioner and the
respondent.
2. The aforesaid disputes, which have arisen between the
petitioner and the respondent relate to a Work Order bearing No.
0012/GPR/BHUB/Contractors/Pkg-14/03 dated 27.07.2010 for the
construction of 897 dwelling units at Bhubaneswar and Gopalpur for
the Married Accommodation Project (hereinafter referred to as
"MAP").
3. The contract entered into between the petitioner and the
respondent was for the total value of Rs. 91,63,37,224.50 only
(Rupees Ninety one crores sixty three lacs thirty seven thousand two
hundred twenty four and fifty paisa only). The overall period of
completion was fixed for a period of 25 months, as the petitioner was
required to commence the work on 02.08.2010 and complete it by
01.09.2012.
4. Clause 60 of the General Conditions of Contract stipulated that
in case of disputes arising between the parties, the parties shall refer
the matter to arbitration. The relevant extract of the aforesaid Clause
60 is reproduced hereinbelow:-
"60. Arbitration
All disputes, between the parties to the contract (other than those for which the decision of the DG MAP or
any other person is by the contract expressed to be final and binding) shall, after written notice by either party to the contract to the other of them, be referred to the sole arbitration of serving officer having degree in Engineering or equivalent or having passed Final/Direct Final Examination of Sub Division II of Institution of Surveyors (India) recognized by the Govt of India to be appointed by the Engineer-in- Chief, Army Headquarters, New Delhi or in his absence, the officer officiating as Engineer-in-Chief or Director General of Works if specifically delegated in writing by Engineering-in-Chief, Army Headquarters, New Delhi whose decision shall be final, conclusive and binding. The Arbitration shall be governed by the Arbitration and Conciliation Act, 1996.
Unless both parties agree in writing, such reference shall not take place until after the completion or alleged completion of the Works or termination or determination of the Contract under Condition Nos. 49 and 50 hereof.
Provided that in the event of abandonment of the works or cancellation of the Contract under Conditions Nos. 46, 47 or 48 hereof, such reference shall not take place until alternative arrangements have been finalized by the Government to get the Works completed by or through any other Contractor or Contractors or Agency or Agencies.
Provided always that commencement or continuance of any Arbitration proceedings hereunder or otherwise shall not in any manner militate against the Government's right of recovery from the Contractor as provided in Condition 57 hereof............". (emphasis supplied)
5. Disputes having arisen between the parties, the petitioner
invoked the aforesaid Arbitration Clause through various letters dated
26.04.2011, 12.05.2011 and 13.06.2011 written by the petitioner. The
petitioner was finally constrained to determine the Contract with the
respondent by a letter dated 21.09.2011 without completion of the
project, stating therein that the petitioner had suffered huge losses in
view of the failure of the projects solely due to the negligent act of the
respondent in not handing over all the sites for construction and once
again requesting the respondent for appointment of an Arbitrator. The
respondent replied to the aforesaid letter on 27.10.2011, refusing to
appoint an Arbitrator by stating:-
"9. It is an agreed condition that arbitration cannot be invoked unless the work is physically completed without mutual consent of both the parties. Since no ambiguity existed in the disputes raised by you no decision is pending from the Accepting Officer, our concurrence remained a tacit refusal."
6. In view of the aforesaid refusal of the respondent to initiate
arbitration proceedings, the petitioner was left with no option except
to file the present petition on 15.03.2012 for appointment of an
arbitrator.
7. The respondent filed its affidavit opposing the prayer made in
the petition, paragraph 4 whereof states as follows:-
"4. That by way of this Short Affidavit, the Respondent submits that the Arbitrator in the present matter, may be ordered to be appointed, in terms of theArbitration Clause i.e. Clause 60 of the General Conditions of the Contract, by the Engineer-in-Chief, Army Headquarters, New Delhi or in his absence, the officer officiating as Engineer-in-Chief or Director General of Works if specifically delegated in writing by Engineering-in-Chief, Army Headquarters, New Delhi."
8. Arguments were addressed by Ms. Indu Malhotra, learned
senior counsel on behalf of the petitioner and Mr. Anuj Agarwal,
learned counsel on behalf of the respondent. It was submitted by Ms.
Indu Malhotra that the right of the respondent to appoint the arbitrator
stands forfeited on the petitioner filing the present petition for
appointment of an arbitrator before this Court. Specific reliance was
placed by her on the judgment of the Hon‟ble Supreme Court in Datar
Switchgears Ltd. vs. Tata Finance Ltd. and Another (2000) 8 SCC
151, wherein it is held as under:-
"19. So far as cases falling under Section 11 (6) are concerned - such as the one before us - no time limit has been prescribed under the Act, whereas a period of 30 days has been prescribed under Section 11 (4) and Section 11 (5) of the Act. In our view, therefore, so far
as Section 11 (6) is concerned, if one party demands the opposite party to appoint an arbitrator and the opposite party does not make an appointment within 30 days of the demand, the right to appointment does not get automatically forfeited after expiry of 30 days. If the opposite party makes an appointment even after 30 days of the demand, but before the first party has moved the Court under Section 11, that would be sufficient. In other words, in cases arising under Section 11(6), if the opposite party has not made an appointment within 30 days of demand, the right to make appointment is not forfeited but continues, but an appointment has to be made before the former files application under Section 11 seeking appointment of an arbitrator. Only then the right of the opposite party ceases. We do not, therefore, agree with the observation in the above judgments that if the appointment is not made within 30 days of demand, the right to appoint an arbitrator under Section 11 (6) is forfeited." (emphasis supplied)
9. Ms. Malhotra also placed reliance upon a three-Judge Bench
decision of the Supreme Court in Punj Lloyd Ltd.Vs. Petronet MHB
Ltd. (2006) 2 SCC 638 in which the judgment in Datar Switchgears
Ltd. (supra) has been reaffirmed. Reference was also made by her to
the judgment of the Hon‟ble Supreme Court in Denel (Proprietary)
Limited Vs. Ministry of Defence (2012) 2 SCC 759. In the said case,
applying the dicta laid down in Datar Switchgears Ltd.'s case
(supra), it has been held by the Hon‟ble Supreme Court that the
respondents had lost the right to appoint an arbitrator as the
respondents had failed to appoint an arbitrator before the petitioner
moved the Court for such appointment. Hence, the appointment of
arbitrator by the respondents subsequent to the filing of the petition
was held to be unsustainable and was set aside, and an independent
arbitrator was appointed as sole arbitrator to decide all the disputes
between the parties.
10. It is submitted by Ms. Malhotra that the respondent‟s contention
that only a serving officer can be appointed by the Engineer-in-Chief,
Army Headquarters, New Delhi as an arbitrator in the present case is
wholly devoid of any merit, and deserves to be rejected for the
following reasons:-
(a) Firstly, the respondent‟s right to appoint its own Officer as an
Arbitrator stands forfeited for the reason indicated hereinabove.
(b) Secondly, any serving Officer of Indian Army appointed as an
arbitrator is bound to be subordinate in rank to the Director General,
MAP who himself is a senior serving Officer in the Indian Army. The
petitioner has genuine and serious apprehensions about the
impartiality and independence of a serving Officer being appointed as
an Arbitrator. In the case of Denel (Proprietary) Limited vs. Bharat
Electronics Ltd. and Anr. (2010) 6 SCC 394, the Hon‟ble Supreme
Court while appointing an independent Arbitrator other than the
Managing Director of the respondent Company, opined as under:-
"21. However, considering the peculiar conditions in the present case, whereby the arbitrator sought to be appointed under the arbitration clause, is the Managing Director of the Company against whom the dispute is raised (the Respondents). In addition to that, the said Managing Director of Bharat Electronics Ltd. which is a "Government Company", is also bound by the direction/instruction issued by his superior authorities. It is also the case of the respondent in the reply to the notice issued by the respondent, though it is liable to pay the amount due under the purchase orders, it is not in a position to settle the dues only because of the directions issued by the Ministry of Defence, Government of India. It only shows that the Managing Director may not be in a position to independently decide the dispute between the parties."
11. Per contra, learned counsel for the respondent in the course of
his submissions sought to place reliance on the proviso to Clause 60 of
the Contract which is reproduced hereunder for the facility of ready
reference:-
"Provided that in the event of abandonment of the works or cancellation of the Contract under Condition Nos. 46, 47 or 48 hereof, such reference shall not take place until alternative arrangements have been finalized by the Government to get the Works completed by or through any other Contractor or Contractors or Agency or Agencies."
12. It was submitted that as per the aforesaid proviso to Clause 60
of the General Conditions of Contract, in the event of abandonment of
the works or cancellation of the contracts under Condition Nos. 46, 47
or 48 thereof, the reference as stipulated in Clause 60 of the General
Conditions of Contract is not liable to take place until alternative
arrangements are finalized by the Government to get the works
completed by or through any other contractor or contractors or agency
or agencies. It was thus submitted that the present petition is
misconceived as no occasion has arisen so far for reference of disputes
to arbitration, in that, although the respondent has already issued „Risk
and Cost‟ tender to get the balance work executed at the risk and cost
of the respondent, yet the exact amount of such loss can only be
ascertained after finally awarding the said tender, which process is still
to be completed.
13. On a specific query put by this Court to the counsel for the
respondent with reference to Condition Nos.46, 47 and 48 of the
General Conditions of Contract, which relate to the cancellation of
contract for insolvency of the contractor, sub-letting of the contractor,
contractor‟s default and contractor‟s death, learned counsel for the
respondent was unable to demonstrate that any of the aforesaid
conditions existed to enable the Accepting Officer to cancel the
contract. On the other hand, the learned counsel for the petitioner
pointedly stated that the contract had been cancelled not by the
respondent but by the petitioner/contractor on account of non-
availability of sites. As a matter of fact, it is the case of the petitioner
that the handing over of the sites was supposed to be completed by
27.07.2010, but on the said date only one site was handed over to the
petitioner, and the respondent has not handed over the sites at
Bhubaneshwar to the petitioner even till date.
14. Learned counsel for the petitioner in rejoinder contended that
the respondent was guilty of suppression of material facts in so far as
the fact that the respondent was not in possession of the sites was not
disclosed to the petitioner at the time of entering into the contract.
Since it was a time bound contract to be completed within 25 months
from the date of commencement, that is, 02.08.2010, if the respondent
had indicated that the sites were not in their possession on the date of
inviting the tenders, the petitioner would not have entered into the
contract at all. A perusal of the tender documents reveals that various
clauses represented that the Sites Were Ready For Handing Over.
15. Be that as it may, it clearly emerges from the affidavit of the
respondent and in fact it was candidly stated by the counsel for the
respondent at the time of hearing that an Arbitrator may be appointed
by this Court in terms of Clause 60 of the General Conditions of the
Contract. The only bone of contention, however, was that while the
petitioner wanted an independent and impartial arbitrator to be
appointed, the respondent insisted upon the appointment of an
arbitrator by the Engineer-in-Chief, Army Headquarters, New Delhi or
in his absence, the officer officiating as Engineer-in-Chief or Director
General of Works if specifically delegated in writing by the Engineer-
in-Chief, Army Headquarters, New Delhi and that too a serving officer
having a degree of Engineering or equivalent or having passed
Final/Direct Final Examination of Sub-Division II of Institution of
Surveyors (India) recognized by the Government of India.
16. While this Court is conscious of the fact that while exercising
jurisdiction under Section 11 of the Arbitration and Conciliation Act,
1996, the Court has to give „due regard‟ to any qualifications, which
the Arbitrator is required to possess under the contract between the
parties and of the fact that the aforesaid requirement is explicitly laid
down in Section 11(8) read with Sections 12(3)(b) & 34(2)(a)(v) of
the Arbitration and Conciliation Act, 1996, at the same time the law is
well settled that it is not incumbent upon the Court to appoint the
arbitrator(s) named in the agreement [See Northern Railway
Administration, Ministry of Railway, New Delhi Vs. Patel
Engineering Co. Ltd., (2008) 10 SCC 240 wherein it is held that in
exercise of its jurisdiction under Section 11 of the Arbitration and
Conciliation Act, 1996, which the Court has to give „due regard‟ to
any qualifications which the Arbitrator is required to possess under the
contract between the parties as mandated by the two cumulative
conditions contained in Section 11(8)(a) and 11(8)(b), appointment of
the arbitrator or arbitrators named in the agreement is not a must].
The provisions of Section 11(8)(a) and (b) which are opposite read as
follows:-
"The Chief Justice or the person or institution designated by him, in appointing an arbitrator, shall have due regard to -
(a) any qualifications required of the arbitrator by the agreement of the parties; and
(b) other considerations as are likely to secure the appointment of an independent and impartial arbitrator."
17. A perusal of Clause 60 (supra) in the present case specifies that
the only qualifications, which an arbitrator is required to possess under
the present agreement between the parties are:-
(a) a degree of Engineering or equivalent; or
(b) having passed Final/Direct Final Examination of Sub-Division II of Institution of Surveyors (India) Recognized by the Govt. of India.
18. In view of the aforesaid legal and factual position, and having
regard to the serious apprehension of the petitioner as to the non-
impartiality of a serving officer being appointed as an arbitrator, the
insistence of the respondent for the appointment of a serving officer
by the Engineer-in-Chief or Director General of Works, Army
Headquarters and that too after the forfeiture of respondent‟s rights to
appoint its own officers, in the opinion of this Court, is wholly
misconceived. Accordingly, this Court appoints Mr. Amrit Lal
Aggarwal, retired Chief Engineer, MCD, resident of Block No.C-4-A,
Flat No.1-A, Janak Puri, New Delhi-58 (Mob.9811100361) as an
arbitrator to arbitrate upon the disputes between the parties. The
arbitration shall take place under the aegis of Delhi High Court
Arbitration Centre. The fees of the Arbitrator shall be in terms of the
Delhi High Court Arbitration Centre (Arbitrator‟s Fees) Rules.
19. The petition stands disposed of in the above terms. List before
the Delhi High Court Arbitration Centre on 10.12.2012.
REVA KHETRAPAL JUDGE November 30, 2012 sk
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!