Tuesday, 09, Jun, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Kurra Somayya vs The Ponnur Municipality
2024 Latest Caselaw 371 AP

Citation : 2024 Latest Caselaw 371 AP
Judgement Date : 9 January, 2024

Andhra Pradesh High Court - Amravati

Kurra Somayya vs The Ponnur Municipality on 9 January, 2024

     IN THE HIGH COURT OF ANDHRA PRADESH:: AMARAVATI

          THE HON'BLE SRI JUSTICE V.GOPALA KRISHNA RAO

                     APPEAL SUIT NO.578 OF 2008

JUDGMENT:

-

The Appeal, under Section 96 of the Code of Civil Procedure, 1908

[for short „the C.P.C.‟], is filed by the Plaintiff challenging the Decree and

Judgment, dated 17.03.2008, in O.S.No.110 of 2005 passed by the Senior

Civil Judge, Bapatla, [for short „the trial Court']. The Respondent herein

is the defendant in the said Suit.

2. Both the parties in the Appeal will be referred to as they are

arrayed before the trial Court.

3. The brief averments of the plaint, in O.S.No.110 of 2005, are as

under:-

4. Plaintiff is the Civil Contractor. The defendant called for tenders for

construction of drains from Kondamudi Road to Railway Over Bridge and

from Kondamudi Road to Repalle Road and the agreement was executed

on 27.03.1999 for the estimated value of Rs.13,89,135/- and he has

deposited an amount of Rs.87,000/- as a security. The plaintiff completed

the work on 11.05.2000. The part payment of an amount of

VGKR, J

Rs.21,80,000/- was made in three installments. As per the normal

practice, the balance amount due by the date of completion of contract

shall be paid within two (2) months after the date of completion of the

contract and the security deposit amount shall be paid within six (6)

months after the completion of the work. So, the amount shall be paid by

the end of July, 2000. But, the defendant paid the amount in the year

2005. So, the plaintiff is entitled for damages on delayed payments with

interest at the rate of 24% per annum. Subsequently, after completion of

the contract, the defendant is due for the work done and the security

deposit of Rs.87,000/-. There was further delay in payment of balance

due; as such, the plaintiff got issued a registered notice to the defendant

claiming amounts and filed the suit for damages for an amount of

Rs.7,53,430/-.

5. The defendant filed written statement denying all the allegations

made by the plaint. The defendant pleaded that as per the work order,

the plaintiff has to complete the work within a period of sixty (60) days

i.e., by 18.05.1999, but he did not do so and completed the work with a

delay of one year. The defendant further pleaded that as per

Clause 59 (b) of Preliminary Specification to Andhra Pradesh Detail

VGKR, J

Standard Specifications penalty at the rate of 5% on the contract value is

to be levied at Rs.1,69,457/- from the contractor with regard to the delay

in completion of the work. But the defendant has not levied the said

amount with an intention to complete the work by the plaintiff in a

smooth manner. The defendant further pleaded that the entire amount is

paid by the defendant. So, the plaintiff is not entitled for such damages

with interest at the rate of 24% per delayed payments without completing

the work within a stipulated time and the plaintiff is not entitled to claim

any such damages.

6. Based on the above pleadings, the trial Court framed the following

issues:

i) Whether the plaintiff is entitled for recovery of damages as prayed for in the plaint?

ii) Whether there is no clause stipulated either in the work order or in the agreement that the contract is entitled for damages on the delayed payments?

iii) Whether the plaintiff has not protested for any damages or interest and in fact waived his claim for damages and received the final payment in full and final satisfaction of all his claims?

iv) Whether the defendant need not pay any amount to the plaintiff?

VGKR, J

v) Whether there is no cause of action to file this suit and whether the suit claim is false and vexatious one?

vi) To what relief?

7. During the course of trial in the trial Court, on behalf of the

Plaintiff, he himself was examined as PW1 and got marked as Exs.A1 to

A3 documents. On behalf of the defendant/The Ponnur Municipality, the

Officials of defendant Municipality were examined as DW1 and DW2 and

got marked Exs.B1 to B4 documents.

8. Heard both learned counsel.

9. Learned counsel for the appellant would contend that the judgment

passed by the trial Court is contrary to law and instead of granting

damages to the plaintiff, the trial Court came to a wrong conclusion and

dismissed the suit.

10. Per contra, learned counsel for the respondent would contend that

on appreciation of entire evidence on record, the trial Judge rightly

dismissed the suit filed by the plaintiff and there are no merits in the

present appeal.

VGKR, J

11. Now the point for determination is:-

"Whether the Decree and Judgment passed by the trial

Court needs any interference? If so, to what extent"?

P O I N T:-

12. As per the case of the plaintiff, he is a Civil Contractor and the

Defendant/The Ponnur Municipality called for tenders for construction of

drains from Kondamudi Road to Repalle Road and an agreement was

executed on 27.03.1999, for the estimated value of Rs.13,89,135/-.

13. It is not in dispute that the defendant paid total amount but he

paid within three installments. Learned counsel for the appellant would

contend that the defendant paid an amount of Rs.20,00,000/- in the year

2003 and so also, an amount of Rs.2,00,423/-, which is the balance

amount, in the year 2004, after receipt of legal notice and there was a

delay on the part of the defendant and that the plaintiff is entitled to claim

damages.

14. The plaintiff approached the Court seeking damages against the

defendant/The Ponnur Municipality, therefore, the burden is on the

plaintiff to prove his case by producing the oral and documentary

VGKR, J

evidence. The plaintiff himself alone was examined as P.W1 to discharge

his burden, the plaintiff relied on Exs.A1 to A3 documents marked in his

favour. Ex.A1 is the nothing but office copy of Legal Notice, Ex.A2 is the

Postal Acknowledgment and Ex.A3 is the copy of the work order.

15. In order to prove the case of the plaintiff, the plaintiff relied on his

sole testimony as P.W1. The plaintiff is claiming for damages of

Rs.7,53,430/- for delayed payments made by the plaintiff. Admittedly, the

plaintiff instituted a suit for damages for delayed payments made by the

defendant/Municipality for the plaint schedule work undertaken by him

given by the defendant/Municipality. The evidence of P.W1 clearly goes

to show that he started the work in the month of May, 1999. The

material on record clearly goes to show that the entire work was

completed by the plaintiff on 11-05-2000 and part payment was made in

the year 2004 and the final payment was made in the year 2005. The

plaintiff accepted the final payment in the year 2005, without any protest.

16. In order to prove the case of the plaintiff he also relied on

Exs.A1 to A3. Ex.1 is the copy of the Legal Notice, A2 is the Postal

Acknowledgement and A3 is the Copy of the work order. The chief

VGKR, J

affidavit of P.W1 is nothing but contents in the plaint filed by the plaintiff.

In cross-examination when it was elicited, the plaintiff admitted that the

agreement did not disclose about the entitlement of damages for the

delayed payments and there is no interest clause for the delayed

payments. Therefore, the burden rests on the plaintiff to prove under

what provision of law or under what circumstances the plaintiff is entitled

for damages with interest.

17. Per contra, to discharge its liability the defendant/Municipality

relied on the evidence of D.Ws.1 and 2, who are none other than the

officials of the defendant/Municipality. As per the work order Ex.B3, the

plaintiff has to complete the work within a period of sixty (60) days. As

stated supra, the plaintiff commenced the work in the month of May, 1999

and completed his work on 11-05-2000. The defendant/Municipality relied

on Ex.B3 work order. There is a specific recital in Ex.B3 that the work has

to be completed within a period of sixty (60) days by the

contractor/plaintiff. The plaintiff did not produce any proof to show that

he completed the work within a period of sixty (60) days and there are no

latches on the part of the plaintiff. As seen from the Ex.A4 agreement

which is executed in between the plaintiff and defendant/municipality,

VGKR, J

there is no specific clause for damages and interest for the delayed

payment. The plaintiff accepted the Ex.B4 agreement by accepting the

conditions mentioned in the Ex.B4 agreement and he cannot go back by

the terms of Ex.B4 agreement.

18. Admittedly, the work was undertaken by the contractor with the

financial assistance of Central Government and State Government and so

also with other financial institutions. Therefore, the fund has to be

released by the Government. Admittedly, the delay occurred due to

release of funds by the Government with a delay and there are no willful

latches on the part of the defendant for making delayed payments. As

stated supra, the plaintiff accepted the final installment in the year 2005

without any protest. The evidence of D.Ws.1 and 2 and Exs.B2 to B4

clearly proves the defense of the defendant/municipality. As stated supra,

there was an agreement in between both the parties i.e., plaintiff and

defendant and in that agreement, there is no clause with regard to the

rate of interest or damages in respect of the delayed payments made by

the defendant/municipality. Therefore, there are no latches on the part of

the defendant for making delayed payments.

VGKR, J

19. The trial Court on appreciation of entire evidence on record rightly

dismissed the Suit and there is no illegality in the said finding given by the

trial Court. There are no merits in the appeal, therefore there is no need

to interfere with the Judgment and Decree passed by the trial Court.

Accordingly, the point is answered.

20. In the result, the Appeal Suit is dismissed confirming the

Judgment and Decree, dated 17.03.2008 passed in O.S. No.110 of 2005

by the Senior Civil Judge, Bapatla. No order as to costs.

As a sequel, miscellaneous petitions, if any, pending in the Appeal

shall stand closed.

_________________________ V.GOPALA KRISHNA RAO, J Date: 09.01.2024 CVD

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : MAIMS

 
 
Latestlaws Newsletter