Citation : 2022 Latest Caselaw 1359 AP
Judgement Date : 21 March, 2022
HON'BLE SRI JUSTICE U.DURGA PRASAD RAO
I.A.No.1 of 2021
in
Writ Petition No.24461 of 2021
ORDER:
The petitioner prays to direct 2nd respondent to release the power
supply to the petitioner in pursuance of the sanctioned order issued in
Lr.No.SE/O/NLR/EE-T/DEE-C/F/D No.C1828/21 dated 16.08.2021
forthwith pending disposal of W.P.No.24461/2021.
2. W.P.No.24461/2021 is filed by the petitioner declaring the action of
2nd respondent in not releasing power supply to the petitioner even though
the conditions mentioned in the sanctioned order in Lr.No.SE/O/NLR/EE-
T/DEE-C/F/D No.C1828/21 dated 16.08.2021 were complied with by the
petitioner as illegal and arbitrary and for a consequential direction to 2nd
respondent.
3. The case of the petitioner succinctly is thus:
The petitioner is a partnership firm and purchased the property i.e.,
land, building, plant and machinery of M/s. Om Sri Sai Ferroy Alloys
Private Limited (OSSFAPL) located at Sy.No.298, Thimmanagaripalem
Village, Chillakur Mandal, SPSR Nellore District pursuant to the auction
conducted by the State Financial Corporation (SFC) as per the auction
notification dated 16.03.2020. After purchase of the property, the petitioner
made an application to the Distribution Company for release of power
supply and the respondents have informed that there are electricity dues of
OSSFAPL and unless the dues of the previous customer are paid, the power
supply would not be released to the petitioner‟s premises. As those dues
were on higher side and payment of such huge amount would not be
financially viable for the petitioner firm, the petitioner has decided to locate
the unit at a different place and has purchased the land in Sy.Nos.259 and
259-A of Thimmanagaripalem Village, Chillakur Mandal, SPSR Nellore
District. After obtaining necessary approvals, the petitioner made an
application to the Distribution Company for release of power supply to the
proposed unit in Sy.Nos.259 and 259-A of Thimmanagaripalem Village,
Chillakur Mandal, SPSR Nellore District with a contracted maximum
demand of 2,600 KVA and the said application was given registration
No.31111H327102021MAR03 dated 03.03.2021. Thereafter, the petitioner
made number of representations to the respondents for release of power
supply to the proposed new unit as the petitioner has already expended about
Rs.5.00 Crores for establishment of the unit. In spite of his representations,
the respondents did not release the power supply on the sole ground that the
petitioner purchased the machinery in public auction belonging to OSSFAPL
and the machinery is being used for the proposed new unit. Hence, the
petitioner filed W.P.No.10859/2021 before this Court. When the matter
came up for hearing, the petitioner was informed by the office of 1 st
respondent that the proposals were sent by the Superintending Engineer
dated 14.07.2021 for release of power supply to the petitioner and the
estimate was prepared and respondent No.2 was directed to collect the
documents and undertaking from the petitioner‟s firm for withdrawal of the
Court case before releasing the service. The 2nd respondent issued a letter in
SE/O/NLR/EE-T/DEE-C/F/D No.C1828/21 dated 16.08.2021 intimating the
amounts to be paid before execution of the work. In pursuance thereof, the
petitioner has withdrawn the writ petition and the same was dismissed on
17.08.2021. Pursuant to the proceedings of 2nd respondent, the petitioner
paid development charges of Rs.33,88,588/- on 18.08.2021, security deposit
of Rs.39,00,000/- on 17.09.2021 and submitted other compliances on
05.10.2021 and requested the respondents to release the power supply.
Though the entire amount as demanded by the Distribution Company was
paid and necessary certificates were produced for release of the power
supply, the 2nd respondent has not so far released the power supply to the
petitioner which is illegal and untenable. The petitioner made several
representations dated 21.09.2021, 25.09.2021 to the Executive Engineer and
dated 05.10.2021 to the Superintending Engineer and dated 11.10.2021 to 1st
respondent, but of no avail.
Hence, the writ petition.
4. The 2nd respondent filed counter on behalf of the respondents and
contending thus:
(a) Firstly, it contended that the writ petition is not maintainable in
view of the availability of efficacious and alternate remedy before the
Consumer Greivance Redressal Forum (CGRF) at Tirupati as per condition
No.14.4 & 14.8 of General Terms and conditions of Power Supply (GTCS).
It is further contended that on the complaint of P.Rajkumar Reddy to the
Andhra Pradesh Electricity Regulatory Commission (for short, „APERC‟), a
detailed report was called for from 1st respondent under the provisions of the
CGRF, Vidyut Ombudsman and Consumer Assistance Regulations, 2016
and report was submitted and the same is pending for consideration before
the APERC and therefore, writ petition is not maintainable.
(b) Initially, the respondents did not know that the petitioner has
purchased the unit of OSSFAPL in public auction. However, the said fact
came to the notice of the respondents after filing of W.P.No.10859/2021 by
the petitioner. When one P.Koti Reddy representing petitioner firm
approached the respondents seeking supply of electricity for the abutting
premises by utilizing the machinery which they have got purchased in
auction, the same was denied since there are outstanding arrears of more
than Rs.9.00 Crores in the name of OSSFAPL. The petitioner filed
W.P.No.10859/2021 challenging the action of the respondents in not
supplying the power and appropriate defence was placed on record by way
of counter affidavit. For the reasons best known to the petitioner, he has
withdrawn the writ petition.
(c) Nextly, while admitting that the respondents addressed letter dated
16.08.2021, it is however contended that the respondents came to know that
one P.Raj Kumar Reddy made a complaint stating that OSSFAPL
established the petitioner firm through P.Koti Reddy and others and
therefore, the petitioner firm is benami for OSSFAPL. Therefore, the
respondents have engaged a team of Engineers to enquire into those facts.
The Chief Vigilance Officer completed the internal enquiry over the issue of
benami transactions and concluded in his report that to evade the legal dues
to the respondents, OSSFAPL and the petitioner colluded together and
committed cheating. Apart from that B.Surendar Reddy on behalf of
OSSFAPL made a request to the respondents for settlement of outstanding
arrears of Rs.9,71,91,151/- through one time settlement for the HT SC
No.NLR422 which stands in the name of OSSFAPL. In view of these facts,
the petitioner has withdrawn the W.P.No.10859/2021. It is further
contended that as per the law laid down by the Hon‟ble Apex Court, it is the
liability of the auction purchaser to clear the outstanding dues of the
electricity and the APSPDCL is well within its right to demand the arrears
due by the auction purchaser accrued from the previous owner. It is further
contended that already the District collector, Nellore has initiated
proceedings under the Revenue Recovery Act vide OLNLR/DSED/237/2018
SA(DS) REV COL dated 07.12.2018 and served Form 1, 2 and 3 against
OSSFAPL by seizing its plant, building, machinery and structures and also
issued directions to Tahsildar, Chillakur Mandal to auction the property. In
that view, the petitioner‟s act of shifting the plant, building, machinery and
structures unauthorizedly amounts to illegal conspiracy. The contention of
the petitioner that the petitioner is a new plant is totally false. The petitioner
has shifted the plant and machinery equipment from the old premises i.e.,
OSSFAPL to the adjacent premises purchased to evade payment of dues and
registered under another application on 03.03.2021. Hence, the petitioner
being successful bidder is liable to pay dues of previous owner to
respondents and therefore, the writ petition is liable to be dismissed.
5. Heard the arguments of Sri O.Manoher Reddy, learned counsel for
petitioner, and Sri Y.Nagi Reddy, Standing Counsel for the respondents.
6. Both the counsel reiterated their respective pleadings in their
arguments.
7. While it is the submission of the petitioner that the petitioner firm is
only a purchaser of the plant and machinery and other assets of OSSFAPL in
public auction conducted by the SFC and except that it has nothing to do
with the said company and after purchase of the unit the machinery was
relocated at different place in Sy.Nos.259 and 259-A of Thimmanagaripalem
Village, Chillakur Mandal, SPSR Nellore District and after obtaining
necessary revenue permits, the petitioner filed an application to the
Distribution Company for release of the power supply at a contracted
maximum demand of 2600 KVA and in view of the non-response from the
respondents, the petitioner filed W.P.No.10859/2021 and on their promise
that the petitioner‟s request for supply of power was under consideration and
power would be supplied if he withdraws his writ petition, the petitioner has
withdrawn W.P.No.10859/2021 and later the 2nd respondent issued letter
dated 16.08.2021 informing the petitioner about the amounts to be paid
before the execution of the work and accordingly, the petitioner deposited
the development charges, security deposit and other amounts necessary for
release of the power supply and in spite of the petitioner‟s due compliance of
the instructions and directions of the respondents, it is argued, the
respondents have not supplied the power on an untenable argument that
petitioner is a benami of the OSSFAPL and the petitioner is liable to clear
the dues of the said former company.
8. In oppugnation, the contention of the respondents is that the petitioner
is not a new firm or company, but it is only a benami company of OSSFAPL
and since the petitioner purchased the unit of the OSSFAPL, the petitioner,
under law laid down by the Hon‟ble Apex Court, is obligated to discharge
the liabilities of OSSFAPL and when the respondents demanded the
petitioner to pay the said amount for release of power, OSSFAPL has
stealthily relocated the unit at different place under the guise of forming a
new unit and applied for energy. Thus it is the vehement contention of the
respondents that the petitioner is liable to pay dues of OSSFAPL of more
than Rs.9.00 Crores before seeking power supply from the respondents.
9. I gave my anxious consideration to the above respective arguments.
The material papers filed along with writ petition by the petitioner contain
the copy of the Memo No.CGM/O&M/GM/EE/C/F.e-257720/D.No.1182/21
dated 06.08.2021 issued by the Chief General Manager / O & M,
APSPDCL, Tirupati. This memo shows that the Superintending Engineer/
Operation / Nellore - 2nd respondent submitted a proposal for extension of
new HT service connection to the petitioner firm at an estimated cost of
Rs.17,90,587/-. The proposal is for release of HT service connection for
CMD of 2600 KVA potential. The Superintending Engineer also mentioned
the amounts under various heads to be collected from the consumer / writ
petitioner. The Memo reads that on careful consideration of the proposals, it
was instructed to the Superintending Engineer / 2nd respondent to collect the
memo mentioned documents from the petitioner and also an undertaking
from the petitioner for withdrawal of the Court case in W.P.No.10859/2021
for release of the supply. The Superintending Engineer was ultimately
requested to take up the work under turnkey basis by following certain
conditions enumerated in the memo. Pursuant to the said memo, the
Superintending Engineer / 2nd respondent addressed a letter in
SE/O/NLR/EE-T/DEE-C/F/D No.C1828/21 dated 16.08.2021. While
referring the memo addressed by the Chief General Manager, O & M,
APSPDCL, Tirupati, the 2nd respondent informed to the petitioner that the
proposal for issue of service connection for CMD of 2600 KVA with
connected load of 2600 KW at 33 KV potential under HT Cat-3C to the
petitioner firm was sanctioned under turnkey basis. The 2nd respondent in
his letter requested the petitioner to pay an amount of Rs.33,88,588/- under
two heads i.e., the development charges of Rs.31,20,000/- and administrative
overhead charges of Rs.2,68,588/- payable through Demand Draft from a
nationalized bank. In his letter he has further stated that the petitioner has to
follow the following conditions.
1. The consumer is requested to submit the following documents and an undertaking letter for withdrawal of court case filed before releasing of the service:
a) Land conversion approved documents from Revenue department is to be submitted for 2Nos. Sale deeds enclosed as proof of ownership documents.
b) NUDA approvals from NUDA authorities for 2 Nos. Sale deeds enclosed as proof of ownership documents.
c) Registered Partnership documents is to be submitted.
2. It is the responsibility of the concerned Executive Engineer / Operation and Deputy Executive Engineer / Operation to look over the quality of the work.
3. It is the responsibility of the Executive Engineer / Construction / Nellore to check measure the materials at the site before commencement of the said work duly collecting the bills for all the materials.
4. The original purchase bills shall be submitted to the concerned Executive Engineer / Operation.
5. The work is to be executed by the approved contractors of APSPDCL, duly following all other departmental procedures in vogue.
6. Further you are requested to pay the above amounts within one month from the date of this letter otherwise your application will be deleted without any further notice and the work under Turnkey basis will be valid upto 3 months only. Hence the consumer is requested to complete the Turnkey work within the time frame otherwise the approval will be invalid and
a fresh application has to be registered for further course of action.
(a) Thus, the above memo and letter of 2nd respondent would depict
that on two main conditions the respondents agreed to release the power
with connected load of 2600 KW at 33 KV potential to the petitioner unit.
Firstly, on the condition of the petitioner depositing the amounts enumerated
in the memo and letter and secondly the petitioner shall withdraw the
pending Court case i.e., W.P.No.10859/2021. The other conditions are
incidental to the supply of power and they are not germane for our
discussion. According to the petitioner, he duly followed the instructions
contained in the letter dated 16.08.2021 and deposited the amounts. It
should be noted that in para 6 of the counter, the respondents admitted the
factum of addressing letter dated 16.08.2021 to the petitioner for release of
power and the respondents also admitted that the petitioner paid the amounts
on receiving the aforesaid letter. It is important to note that neither in the
Memo dated 06.08.2021 nor in the letter dated 16.08.2021, it was mentioned
that the petitioner is only a benamdar of OSSFAPL and that unless he
deposits the amount payable by the former company, his request for supply
of power cannot be considered. In the counter, for the first time, the
respondents raised that plea and also contended that in view of the judgment
of the Hon‟ble Supreme Court in Civil Appeal No.1815/2020 dated
01.06.2020 [Telangana State Southern Power Distribution Company
Limited v. M/s. Srigdhaa Beverages], the petitioner being purchaser of the
unit of OSSFAPL, it is liable to pay electricity consumption dues of
OSSFAPL.
10. It should be noted that at this juncture, this Court is only considering
the interlocutory application which is filed for a direction to 2nd respondent
to release the power supply to the petitioner pending writ petition. The
Court is aware of the fact that the averments and counter averments made by
both parties require a detailed hearing for resolution in accordance with law.
Therefore, at this juncture, a detailed discussion cannot be made with regard
to the relevant issues i.e., (1) whether the petitioner firm is a benamdar of
OSSFAPL? (2) whether the petitioner being the auction purchaser of the unit
of OSSFAPL, liable to pay the electricity consumption dues of the said
company? However, only a peripheral observation to the extent required
can be made.
11. So far as the first issue is concerned, the respondents along with its
counter filed certain material papers which contain copy of the Vigilance
Report dated 03.07.2021 forwarded by the Inspector of Police, Vigilance &
A.P.T.S. P.S, Nellore to the Joint Managing Director, Vigilance & Security,
AP Transco, Vijayawada, wherein, with regard to certain allegations made
against M/s. Om Sri Sai Ferro Alloys and the writ petitioner, he conducted
enquiry and forwarded the said report. The allegation No.2 is to the effect
that the company of OSSFAPL was auctioned by the A.P. State Financial
Corporation and unit was taken over by M/s. Sri Venkateswara Ferro Alloys
(writ petitioner), benami company of the respondent floated by Sri
P.Kotireddy and others. In respect of this allegation, the finding of the
Inspector of Police, Vigilance & A.P.T.S. P.S. is as follows:
"In view of the above, it is clear that the company of M/s. Om Sri Sai Ferro Alloys was auctioned by APSFC and the unit was taken over by M/s. Sri Venkateswara Ferro Alloys. The petitioner has mentioned the above allegation was true. But there is no specific evidence available to
prove that M/s. Venkateswara Ferro Alloys is a binami company of the respondent."
It is true that the effect of the above report requires to be heard during the
course of arguments in the main writ petition. However, the above finding
prima facie shows that there is no specific evidence to prove that the writ
petitioner is a benami company of M/s. Om Sri Sai Ferro Alloys.
12. So far as the second issue relating to the liability of the petitioner to
pay the electricity consumption charges of OSSFAPL is concerned, in the
decision of the Hon‟ble Supreme Court in Telangana State Southern
Power Distribution Company Limited's case (supra), the question before
the Apex Court was whether the auction purchaser (a unit owned by M/s. SB
Beverage Private Limited) was liable to discharge the previous electricity
dues of the last owner. In that context, taking into consideration the e-
auction notice in question wherein the existence of the electricity dues,
whether quantified or not, has been specifically mentioned as a liability of
the purchaser and also, as the sale was on "AS IS WHERE IS, WHATEVER
THERE IS AND WITHOUT RECOURSE BASIS", the Hon‟ble the Apex Court
observed that the auction purchaser is liable to pay the electricity dues of the
previous owner.
13. In the instant case, at this stage, this Court has no advantage of seeing
the auction notification issued by the A.P. State Financial Corporation,
basing on which the writ petitioner purchased the unit of OSSFAPL.
Neither party produced the auction notification and conditions of the
auction. Therefore, at present it is not possible to decide whether the
petitioner is liable to pay electricity dues of the previous owner.
14. Therefore, at the outset, the two important issues raised by the
respondents in its counter are concerned, they have to be resolved only after
hearing the arguments in the main writ petition, but not at this stage. As the
matter stands, the prima facie there is no material to show that the petitioner
is a benamdar of OSSFAPL. If the impasse were to be continued, the
respondents will lose its revenue and petitioner for want of electricity,
cannot start production, which in my considered view, is not good for either.
Therefore, in the interests of justice it is apposite to direct the respondents to
release the electricity power to the petitioner as requested by him and as
mentioned in the letter dated 16.08.2021 addressed by 2nd respondent to the
petitioner on the condition of the petitioner depositing (1) usual charges as
claimed by the respondent authorities, which if he has not already deposited
and (2) 10% of the electricity consumption charges due from M/s. Om Sri
Sai Ferroy Alloys Private Limited to the respondents within a specified time
to show its bonafides.
15. Accordingly, this application is allowed and the respondents are
directed to release power supply to the petitioner as per the sanction order
issued in Lr.No.SE/0/NLR/EE-T/DEE-C/F/D No.C1828/21 dated
16.08.2021 on the conditions of the petitioner depositing:
(1) the charges as mentioned in the aforesaid sanction order dated 16.08.2021 and other incidental charges (which, if he already paid can be ignored)
(2) 1/10th of the electricity consumption charges due from M/s. Om Sri Sai Ferroy Alloys Private Limited to the respondents as on the date of auction sale.
The above amounts shall be deposited by the petitioner within eight (8)
weeks from the date of this order, in which case, the respondent authorities
shall release power supply to the petitioner unit. Needless to emphasize that
in case the petitioner succeeds in the writ petition, the electricity
consumption charges of M/s. Om Sri Sai Ferroy Alloys Private Limited paid
by him, can be requested to be adjusted towards petitioner‟s own
consumption charges.
As a sequel, interlocutory applications pending, if any, shall stand
closed.
_________________________ U.DURGA PRASAD RAO, J 21.03.2022 mva
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!