Citation : 2022 Latest Caselaw 1117 AP
Judgement Date : 3 March, 2022
1
HON'BLE SRI JUSTICE D.V.S.S.SOMAYAJULU
WRIT PETITION No.242 of 2022
ORDER :
This Writ Petition is filed by the petitioner questioning
their disqualification as a bidder for the work of Mechanization
of WQ 7 & 8 berths in the respondent Port Trust and to issue
a consequential relief.
This Court has heard Sri P. Veera Reddy, learned senior
counsel for the petitioner and Sri Raviteja Padiri, learned
standing counsel for Visakhapatnam Port Trust
PETITIONER'S SUBMISSIONS:
Learned counsel for the petitioner submits that the
petitioner is aggrieved by the action of the respondent dated
17.12.2021 and the disqualification of the petitioners bid on
the sole ground that the bid was not filed "online" and was filed
physically only.
Learned senior counsel submits that the petitioner
participated in a bid for mechanization of WQ 7 and 8 berths.
They had purchased the documents (RFQ) on 11.11.2021.
They submitted their bid on 30.11.2021. According to the
petitioner they were required to submit the bid in the physical
form along with a soft copy of all the documents. The case of
the petitioner is that they had physically submitted their bid
complete in all respects on 30.11.2021. During the course of
meeting for opening of bids, they were informed that they were
disqualified on the ground that they had not uploaded their bid
in the online method in a particular portal
https://etenders.gov.in. Learned senior counsel for the
petitioner took this Court to various clauses available in the
bid documents, which according to him provided for filing of
the bid manually and in the physical form only. Learned senior
counsel argues that at no point of time that the petitioners were
informed that they had to file a bid in the online form. Learned
senior counsel drew the attention of this Court to the very
notice of the invitation which stated that the documents should
be submitted by hand delivery or sent by registered post etc.
He also drew the attention of this Court to Clause 2.1.0 of RFQ
which states that the respondent has the right to modify the
RFQ terms by issuing an addendum. But as per 2.10.2 the
addendum this has to be sent in writing to all the applicants.
Learned counsel drew the attention of this court to Clause
2.1.3 which mandated that the application should be filed in
an envelope which needed to have certain markings, sealing,
seals etc. He also drew the attention of this court to Clause
2.1.3 stating that the application submitted by fax, telex or
email shall be rejected. Learned senior counsel, therefore,
argues that the respondent did not act bona fide or in a manner
required as per law. According to him the action of the
respondent is per se arbitrary and are therefore this Court
must interfere at this stage only. Learned senior counsel relies
upon the judgment of the Hon'ble Supreme Court of India in
B.S.N.Joshi & Sons Ltd., v Nair Coal Services Ltd., 1to argue
that the respondent did not act as required under law and that
their action is not fair and that consequently the Writ Petition
is to be allowed.
In reply to the stand taken by the respondent that a
corrigendum was issued he submits that the same was never
communicated to the petitioner. It is also submitted by the
learned senior counsel that at no point of time the respondent
clarified that the electronic filing is mandatory. Learned senior
counsel submitted that they had purchased their bids on
11.11.2021 and the alleged clarification was issued in a
meeting purportedly held on 05.11.2021. Learned senior
counsel submits that the petitioner did not even purchase the
bid papers at that point of time and they were not informed of
this so-called mandatory clause.
RESPONDENT SUBMISSIONS:
In reply to this, Sri Raviteja Padiri, learned standing
counsel argues in line with what is stated in his counter
affidavit. According to him on 05.11.2021 in the pre-
application meeting held some of the bidders raised some
queries, as a result of which a corrigendum was issued making
online submission of the RFQ mandatory. Learned counsel
argues that in this case petitioner merely filed their bid in the
manual method but did not file in online method which
according to the learned standing counsel is mandatory. He
(2006) 11 SCC 548
also argues that the bidder should take care to download all
the clarifications etc., and to download all the required data.
He relies upon a note which is annexed to the bid which states
as follows:
"Note: In case RFQ document is downloaded from VPT's website, the applicant is responsible to download Addendums / Amendments / replies to queries etc., if any issued by the Port"
Learned counsel argues that it is not correct to state that
the corrigendum was not noticed by the petitioner as he has a
duty to download all the addendums, amendments and reply
to queries. In the brief submitted by the learned standing
counsel to the Court in a single page he points out that there
are 13 corrigendum issued and he highlights the present
corrigendum. Therefore, for this reason learned counsel argues
that as the petitioner failed to meet the essential condition the
rejection of this bid is correct. He relies upon a compendium
of case law to argue that the Court should lightly interfere in
tender matters etc., that the mandatory condition is not
fulfilled and that the decision is rightly taken.
COURT:
In the opinion of this Court there is no dispute on facts
in this case. It is clear that the petitioner purchased the bid
documents and submitted their bid in the manual
mode/physically only The petitioner was disqualified as they
have not submitted their bid in the online mode also. The
disqualification is based on a corrigendum to the tender
document which mandated the filing of the bid in the online or
electronic form also.
After hearing the learned counsels the questions that
arise are about the corrigendum said to have been issued on
12.11.2021:- Whether the same is mandatory and whether it
was communicated to the petitioner.
This Court notices that the entire stand of VPT-
respondents is based upon the alleged corrigendum which was
issued in a meeting dated 12.11.2021. As can be seen from the
pleadings, documents etc., the pre-bid meeting that was held
on 12.11.2021 was for "EQ7" project (the present case and the
present tender relates to WQ7/WQ8). In this pre-bid
conference, a corrigendum is said to have been issued, wherein
it is stated that the completed application is to be submitted
through online CPC portal and also to submit the hard copies.
Hence, the decision making process based on this
"corrigendum clause" is being examined by this Court and the
conditions in the bid document/tender document that are
essential are discussed below.
The first clause that falls for consideration about the
manner of filing, is in Ex.P.1. This is the opening page of the
document which describes the RFQ etc.
"....The completed Application in the required format containing all information requested in RFQ document should be submitted either by hand delivery or sent by Registered Post / Speed Post / Courier to reach the office of the Chief Mechanical Engineer, Administrative Office, Building, 2nd floor, Visakhapatnam Port Trust,
Visakhapatnam - 530035 before 14:00 hrs., on 20.11.2021 and will be opened at 15:00 hrs on the same day." (Emphasis supplied)
The next clause in the immediate next page is as follows:
"Note: in case an RFQ document is downloaded from VPT's website, the Applicant is responsible to download Addendums / Amendments / Reply to Queries etc., if any issued by the Port (CHIEF MECHANICAL ENGINEER)."
The next important clause is 2.10 -
"2.10 Amendment of RFQ 2.10.1 At any time prior to the deadline for submission of application, the Authority may, for any reason, whether at its own initiative or in response to clarifications requested by an Applicant, modify the RFQ by the issuance of Addenda.
2.10.2 Any Addendum thus issued will be sent in writing to all those who have purchased the RFQ.
2.10.3 In order to afford the Applicants a reasonable time for taking an Addendum into account, or for any other reason, the Authority may, in its sole discretion, extend the Application due date." (Emphasis supplied)
Clauses 2.13.1 and 2.13.2 (vii) are also important:
"2.13 Sealing and Marking of Applications 2.13.1 the Applicant shall submit the Application in the format specified at Appendix-I, together with the documents specified in Clause 2.13.2, and seal it in an envelope and mark the envelope as "APPLICATION". The applicant shall seal the original and the copy of the Application, together with their respective enclosures, in separate envelopes duly marking the envelopes as "ORIGINAL" and "COPY". The envelopes shall then be sealed in an outer envelope which shall also be marked in accordance with Clauses 2.13.2 and 2.13.3. .....
.....
(vii) 2 (two soft copies of the Application on a Compact disc (CD): and ....
....
2.13.5 Applications submitted by fax, telex, telegram or e- mail shall not be entertained and shall be rejected."
A conjoint reading of these clauses makes it very clear
that (a) RFQ document shall be downloaded from the CPP
portal and submitted in the physical form by hand delivery or
sent by Registered Post / Speed Post / Courier to reach the
office of the Chief Mechanical Engineer-Respondent No.3.
b) these clauses can be amended but Clause 2.10.2 very
clearly states that any addendum issued will be sent "in
writing" to all those who have purchased the RFQ. It is clear
that there is a duty cast upon the respondent Port to send every
addendum in writing to all those who have purchased the RFQ.
Considering the importance of addendum, Clause 2.10.3 states
that the authority can also extend the date of application.
c) Clause 2.13 also assumes importance. It describes in
great detail the manner in which the application is to be
physically filed. The sealing of the cover, the enclosures to be
included, the manner in which the cover is to be marked etc.,
are spelt out with great clarity in 2.13. Separate envelopes are
to be given marking them as Original and Copy. These two
envelopes should be kept in an outer envelope which should
also be marked in accordance with clause 2.13.2 and 2.13.3.
The envelope should also contain two soft copies of the
application on a Compact disc.
c) Clause 2.31.5 assumes even greater significance. It
clearly states that an application submitted by fax, telex,
telegraph or e-mail shall not be entertained and shall be
rejected.
A conjoint reading of all these clauses makes it very clear
that as per the original terms of the bid which were purchased
by the petitioner the application / bid should be submitted in
the physical form only. It is also specified the bid was
submitted in online form it will not be entertained and shall be
rejected.
This Court also notices that the so called addendum
issued on 05.11.2021 is not filed as a document. It is
mentioned in a typed note submitted during the hearing and it
is as follows:
"There are about 13 Corrigendums issued to the RFQ in the present project. Out of the 13, Corrigendum No.8 relates to Page No.5 Para No.5 of the RFQ Document, by which there is a modification in respect of submitting the RFQ document. As per the modified condition, The completed Application in the required format containing all information requested in RFQ document should be submitted through online in CPP Portal, https://etenders.gov.in and also submit the hard copies by hand delivery or sent by Registered Post / Speed Post / Courier to reach the ......... before 15.00 hrs on 20.11.2021."
It is relied upon in the counter affidavit also.
Even if what is stated in the counter affidavit is treated
at face value as correct, this Court is of the opinion that the
Claus does not indicate that the bid filed in the manual mode
/ physical mode will be rejected, if the same is not filed in the
electronic form also. In the opinion of this court if filing in the
electronic mode was mandatory it should have been very
specifically clarified in the corrigendum and also
informed/communicated in writing in terms of Clause 2.10.2
to every purchaser of the bid documents. The mere fact that
such a corrigendum was issued and it was purportedly
uploaded on the website does not make it "mandatory". It
should have been expressly communicated to all the potential
bidders since it is contrary to many of the other clauses. The
language used should be clear and categorical, if it leads to
such drastic consequences. For example, in Clause 2.13.5 it
is very clearly stated that if the application is submitted by
e-mail it shall not be entertained and shall be rejected. Such
clear and categorical language spelling out the consequences
is not visible from the corrigendum. Clauses with potentially
serious consequences should be clearly and categorically spelt
out in the bid documents more so when they are the result of
an amendment or an addendum.
There is also an issue raised by the petitioner about the
portal from which they had downloaded the document. The
petitioner before this Court is clearly stating that they have
downloaded the RFQ document from the CPP portal but not
from the VPT portal. The clause relied upon by the respondent-
VPT casting a duty on a bidder to download the addendum is
referring only to VTPs website and it is not referred to CPP
Portal.
Apart from what is stated above there is no material
available before this Court to show that the corrigendum as
stated has actually been posted on the website.
Therefore, while being conscious of this Courts
limitations while exercising power in tender matters under
Article 226 of the Constitution this Court has to hold that the
corrigendum relied upon by the respondent does not support
their case and the decision taken by the respondent is arbitrary
and runs contrary to the law which mandates that every bidder
is entitled to fair and equal treatment. In the opinion of this
Court, the number of clauses which are reproduced earlier
which mandated the filing of the tender document in a
particular format (physically) cannot be brushed aside totally.
The weight that is to be given to these clauses is very significant
in the opinion of this Court. The respondent VPT definitely has
a right to modify the clause but they should communicate the
same "in writing". Even if the corrigendum as mentioned in the
note is taken at its face value and can be said to have been
communicated, this Court is of the opinion that it was never
specified anywhere that if the bid is also not filed in the
electronic mode / offline also it will be rejected. Only if the
corrigendum is as per the tender conditions and it specifies
that the bids will be rejected if they are not filed both in the
physical and electronic mode, can it be said that the mandatory
condition was not followed by the petitioner. Needless to say
this corrigendum must be communicated clearly to all bidders.
In the absence of any such proof and in the light of these clear
and categorical directions given to the petitioner how to file a
tender this court is of the opinion that the respondent's
decision is arbitrary and contrary to their own instructions
given at various other places in the tender document.
In addition to all of the above, as mentioned earlier, the
tender is still at the stage of evaluation of the pre-bid
qualifications. The bidders are being pre -qualified and then
invited to file their financial bids etc. Therefore, public interest
is also not being hurt in any way nor is any delay likely to be
caused to the project itself. The writ petition is itself being
decided with the consent of all the learned counsels.
The very purpose of inviting tenders is to ensure that the
respondent-VPT gets the service it wishes at the best prices.
By widening the scope or by getting more bids the requirements
of the respondent would in fact be satisfied. More competitive
bidding would result in better services for the respondent-VPT
since the project is a long term project.
In conclusion this Court holds that the respondent VPT
which is a state instrumentality should be a model employer.
It should not take hyper technical pleas. Transparency, clarity
and procedural fairness in action are essential but unwritten
conditions in all such tender documents which are
incorporated by law. The said procedural fairness aspect is not
visible in this case. The corrigendum is not clear enough to
eliminate the petitioner. The case law filed by the petitioner is
not being adverted to in full. They are the settled law on the
subject. The locus classicus is Tata Cellular v Union of
India2. In line with para 77 of this famous judgment if the
decision making in the present case is examined this Court
finds that: the decision making authority exceeded its powers;
committed an error of law; reached a conclusion that no
reasonable tribunal would reach. The facts taken as a whole
cannot logically warrant the conclusion of the respondent VPT.
The procedural impropriety is striking and clear. The petitioner
was denied the right to equality and fair treatment (Meerut
Development Authority v Association of Management
Studies3).
For all the above reasons, the Writ Petition is allowed.
The action of the respondent No.1 in disqualifying the
petitioner at this stage is held to be illegal. The respondents
are therefore directed to consider the bid submitted physically
(1994) 6 SCC 651
(2009) 6 SCC 171 (para 27)
by the petitioner and evaluate it strictly on its own merits.
There shall be no order as to costs.
Consequently, the Miscellaneous Applications
pending, if any, shall stand closed.
__________________________ D.V.S.S.SOMAYAJULU,J Date:03.03.2022 Ssv
HON'BLE SRI JUSTICE D.V.S.S.SOMAYAJULU
WRIT PETITION No.242 of 2022 Date:03.03.2022 ssv
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!