Citation : 2022 Latest Caselaw 303 AP
Judgement Date : 24 January, 2022
HON'BLE SRI JUSTICE NINALA JAYASURYA
WRIT PETITION No.2483 of 2019
ORDER:-
The present Writ Petition is filed seeking to declare the
impugned action of the respondents in rejecting the case of
petitioners for absorption without properly verifying the Service
Certificates vide Lr.No.SE/ O/ E1.R/ DE.T/ ADM/ POSSESSION/
JAO/ F.No.49/ D.No.2870/18, dated 28.09.2018 and passing the
impugned order, as highly illegal, arbitrary and violative of
Articles 14 and 16 of the Constitution of India apart from
contrary to the judgment made in W.P.No.8249 of 2010, dated
20.02.2018 and consequently set aside the same by directing
the respondents to absorb the petitioners with LDC's or any
other equivalent posts with all other benefits.
Heard Smt.Akella Padma, learned counsel for the
petitioners and Sri Metta Chandra Sekhar Rao, learned Standing
Counsel for APSEB appearing for the respondents.
The brief facts of the case as culled out from the affidavit
filed in support of the Writ Petition may briefly be narrated for
better appreciation of the petitioners' case. The 1st petitioner
worked as contract labour from 01.07.1991 to 31.03.1998
through M/s Sailaja Engineering Construction, Narsapur and
further continued upto November, 2000. The 2nd petitioner
worked as contract labour from 01.05.1996 to 10.10.2000
through the same contractor. Several contract works were
entrusted by erstwhile A.P. State Electricity Board (APSEB) which
was bifurcated into A.P. Transco & A.P. Genco and later
NJS, J W.P.No.2483 of 2019
transformed into different companies viz., APEPDCL, APSPDCL
and APNPDCL and Central Power Distribution Company of Andhra
Pradesh Limited. Claiming that they are entitled for absorption as
contract labour under the scheme laid down vide B.P.Ms.No.36,
dated 18.05.1997 of the erstwhile APSEB, the petitioners
approached the erstwhile Common High Court of Andhra Pradesh
at Hyderabad by filing W.P.No.14241 of 2002. The said Writ
Petition was allowed vide order, dated 11.03.2003 and the
respondents therein were directed to consider the petitioners'
case for absorption in terms of the said B.P. However, the case
of petitioners was rejected by orders, dated 12.09.2003 on the
ground that they were not on rolls as on 18.05.1997.
Aggrieved by the same, the petitioners filed W.P.No.20539
of 2003 and W.P.No.20465 of 2003 respectively, which were
allowed by an order dated 29.09.2004. Against the said orders,
the respondents filed W.A.No.1606 and W.A.No.1842 of 2004
and the same were disposed of by orders dated 25.11.2004 inter
alia, observing as follows:-
"Para 7: BP.Ms.No.36 was issued by the Board only to provide employment opportunities to the contract labour in the regular service of the Board provided they fulfilled the requisite condition. Therefore, every effort should be made to ensure that the benefit only goes to the eligible contract labour and not the others who try to enter the protection of BP.Ms.No.36 by resorting to illegal methods. Though the learned Single Judge having no other material to come for a definite conclusion had drawn the inference, but at the same time it does not preclude the authorities from reconsidering the issue as to whether the respondent had in fact worked as contract labour with reference to the documents and further enquiry if any conducted by the authorities in this regard to
NJS, J W.P.No.2483 of 2019
reach the object sought to be achieved by BP.Ms.No.36. Under those circumstances, we do not find any ground to interfere with the order of the learned Single Judge.
Para 8: Accordingly, the Writ Appeals are disposed of subject to the above observations, The appellants are directed to consider the case of the workmen and pass appropriate orders within a period of eight (08) weeks from the date of receipt of a copy of this order. No costs."
Against the said orders, the petitioners carried the matter
by way of appeal to the Hon'ble Supreme Court. The Hon'ble
Supreme Court vide orders, dated 04.03.2005 in Special Leave
to Appeal (Civil) Nos.4142-4146/2005) disposed of the same in
the following terms:-
"Learned counsel for the petitioner submits that he has valid certificate as required under Notification to show that on the relevant date, namely, 18.05.1997 he was working with the contractor in the project concerned and that he is entitled to the benefit of Notification. If that be so as provided in the impugned judgment of the Division Bench itself it is open to him to show the certificate to the authorities concerned and convince them."
Thereafter, the petitioners filed W.P.No.20049 of 2005
challenging the order, dated 18.07.2005 passed by the
respondents rejecting the petitioners' case on the ground that no
fresh material was placed. The said Writ Petition was disposed of
vide orders, dated 26.10.2007, wherein the learned Single Judge
while observing that the respondents cannot be blamed for not
considering the cases of petitioners, however was pleased to
grant one more opportunity to the petitioners to establish their
case that they were on rolls as on 18.05.1997 and directed them
to file a detailed representation along with the documents to
NJS, J W.P.No.2483 of 2019
show that they were on rolls with the contractor as on
18.05.1997 and the respondents therein were directed to
consider the cases of petitioners based on the said documents to
be produced by them and pass appropriate orders thereon,
within a period of four (04) weeks from the date of receipt of a
copy of this order.
Pursuant to the said orders, the 4th respondent passed
orders on 19.03.2009 once again rejecting the case of the
petitioners. Challenging the same, the petitioners filed
W.P.No.8249 of 2010 which came to be disposed of by the
erstwhile Common High Court for the State of Telangana and the
State of Andhra Pradesh at Hyderabad by orders dated
28.02.2018. The learned Single Judge allowed the Writ Petition
and the relevant portion of the order reads as follows:-
"As rightly contended by the learned counsel for petitioners, the order impugned is liable to be set aside on the sole ground non-application of mind to the issue involved more particularly when specific direction was issued in the earlier round of litigation by the learned Single Judge followed by Division Bench. Hence, order impugned is set aside and matter is remitted to 4th respondent to examine whether petitioners were working on 18.05.1997 based on the certificate submitted by them as observed by the Division Bench in W.A.No.1606 of 2004 and batch dated 24.11.2004. A decision shall be taken by duly considering material on record and in terms of the directions issued in the earlier material on record and in terms of the directions issued in the earlier material on record and in terms of the directions issued in the earlier round of limitation. It is also open to the petitioners to place any material in support of their claim. Material, if any, shall be placed before the competent authority within a period of two weeks from the date of receipt of copy of this order and within four weeks thereon 4th respondent shall take appropriate decision in the matter."
NJS, J W.P.No.2483 of 2019
Thereafter, the 4th respondent passed separate orders,
dated 28.09.2018 once again rejecting the cases of petitioners
for absorption for the reasons set out in the said order.
Aggrieved by the same, the petitioners are constrained to
challenge the same, in the present Writ Petition, on various
grounds.
The learned counsel for the petitioners while reiterating the
contentions raised in the Writ Petition, inter alia, submits that
the petitioners were denied absorption of their services without
verification of the documents submitted on their behalf in a
proper perspective. While drawing the attention of this Court to
the Certificate, dated 07.08.1997 of the concerned Assistant
Divisional Engineer, Construction and Operation, APTRANSCO
Limited, Narsapur she submits that Form-XV, dated 10.10.2000
issued by the Contractor M/s Sailaja Engineering Constructions
would also support the case of the petitioners that they were
working as contract labour as on 18.05.1997 and therefore they
are entitled for absorption in terms of B.P.Ms.No.36, dated
18.05.1997. She submits that the material on record would
clearly disclose that the petitioners were working as on
18.05.1997 as contract labour with the above said contractor for
execution of works relating to the respondent Company and
therefore the reasons assigned in the impugned order to the
effect that the contract labour cannot work two different works
at the same point of time is misconceived. She contends that
once the competent authority i.e., Assistant Divisional Engineer
NJS, J W.P.No.2483 of 2019
had certified that the petitioners were engaged as contract
labour for the works relating to the respondent Company as is
evident from the pages 59 and 77 of the material papers, the
stand taken that the Service Certificate of the contractor is not
countersigned by the concerned Assistant Divisional
Engineer/Assistant Engineer is of no consequence. The learned
counsel submits that the authorities instead of examining the
case of petitioners as directed by the Hon'ble High Court on the
earlier occasions, in true letter and spirit, had bent upon to pass
rejection orders only to deprive the petitioners of their valid
claims, on untenable grounds. She submits that the impugned
order is liable to be set aside on the ground of non-application of
mind and the Writ Petition be allowed, directing absorption of the
petitioners, by setting aside the order dated 28.09.2018.
On the other hand, the learned Standing Counsel
strenuously contended that the arguments advanced by the
learned counsel for petitioners are not tenable. He submits that
the authorities concerned have scrupulously considered the
material i.e., Service Certificates, dated 10.10.2000 issued by
the Contractor and as the same were not countersigned by the
concerned Assistant Divisional Engineer/Assistant Engineer, the
same were not taken into consideration. He also submits that the
nature of work mentioned in the said Service Certificate is
different from the work as mentioned in the Certificate dated
07.08.1997 of the Assistant Divisional Engineer and therefore
the 4th respondent had rightly observed that the petitioners
cannot be expected to be present in respect of two different
NJS, J W.P.No.2483 of 2019
works, at the same time. He also submits that B.P.Ms.No.36,
dated 18.05.1997 was withdrawn in the year 2006 and the
petitioners' cases for absorption in terms of the said
B.P, cannot, therefore be considered. He also submits that the
petitioners have not submitted any concrete material to establish
that they were working as contract labour as on 18.05.1997,
though the Hon'ble High Court granted liberty to them in the
orders passed in the earlier round of litigation. He submits that
the respondents have passed orders in strict obedience to the
orders passed by the Hon'ble High Court and therefore the
allegation of non-application of mind is absolutely baseless and
untenable. Making the said submissions, the learned Standing
Counsel submits that the Writ Petition is devoid of merits and
seeks dismissal of the same.
This Court has considered the submissions of the
respective Counsel and perused the material on record.
The orders passed in the Writ Petitions filed by the
petitioners on the earlier rounds are borne out by record and a
reading of the same goes to show that the petitioners were
granted liberty to submit the documents in support of their case
that they were working as contract labour as on 18.05.1997 and
the respondent authorities were directed to examine the same.
Though in the impugned order one of the reasons stated for
rejection of petitioners' cases is that Service Certificate is not
countersigned by the concerned Assistant Divisional
Engineer/Assistant Engineer, the Certificate dated 07.08.1997
which was countersigned by the concerned Assistant Divisional
NJS, J W.P.No.2483 of 2019
Engineer would clearly establish that the petitioners were
engaged as contractor labour in respect of the works entrusted
to M/s Sailaja Engineering Constructions and pages 48 to 72 of
the material papers discloses the details of the respective
petitioners and in the relevant column No.5 extracted for ready
reference, it is stated as follows:
"Whether the works executed relates to the then
A.P.S.E. Board as on 18.05.1997 - Yes"
It may also be appropriate to extract the
Certification/Endorsement of the Assistant Divisional Engineer,
Construction and Operation, AP TRANSCO Limited, Narsapur
which reads thus:-
"It is certified that the particulars furnished by the contractor at columns 6 to 12 of the format have been duly verified with reference to the agreements. The contract labour as stated to have been engaged by the contractor furnished by the contractor at columns 2 to 5 of the same format. It is to confirm that the check measurements is in respect of L.S. Agt. No.4/1997-98 covered in the statement has been done on 07.08.1997."
In the light of the above certification/endorsement, the
order of rejection on the premise that the Service Certificate,
dated 10.10.2000 of the concerned Contractor is not
countersigned by the concerned Assistant Divisional Engineer,
holds no water.
Further, the nature and location of or work described at
Sl.No.3 in the Service Certificate of the Contractor contains
broad description, which relates to construction, operation and
maintenance works connected to APSEB. The nature of work
NJS, J W.P.No.2483 of 2019
done at Sl.No.4 of the Tabular Form in the said Certificate refers
to erection of poles, stringing, paying out of conductor, erection
of Transformers and other works connected to H.T and L.T Lines
and sub-stations etc., and construction of inner fencing wall for
structural yard at sub-station, Mogaltur (33/11 KV SS) vide L.S.
Agreement No.4/97-98 would definitely fall within the ambit of
works entrusted to the contractor. Therefore, the view taken in
the impugned order with reference to nature of works and that
"a contract labour cannot work two different works at the same
point of time" cannot be countenanced. The other submission of
learned Standing Counsel that the petitioners' cases cannot be
considered as B.P.Ms.No.36 has been withdrawn, cannot be
appreciated. As seen from the impugned order, the said B.P was
withdrawn vide E.O.No.276 dated 04.10.2006 on the premise
that there are no eligible candidates. The case of petitioners
stands on a different footing and the earlier orders passed in
their favour would clearly go to show that, in the event, they
succeed in establishing that they were working as contract labour
as on 18.05.1997, their cases shall be considered for absorption.
In the present case, the material on record, as observed
earlier, would establish that the petitioners were working as
contract labour as on 18.05.1997 and rejection of their cases
without appreciation of material in a proper perspective amounts
to non-application of mind.
NJS, J W.P.No.2483 of 2019
For the afore going reasons, the rejection proceedings
dated 28.09.2018 are set aside. The respondents are directed to
absorb the petitioners in any suitable post, within a period of
eight (08) weeks from the date of receipt of a copy of this order.
In the result, the Writ Petition is allowed, in part, to the
extent indicated above. There shall be no order as to costs.
As a sequel, miscellaneous applications, if any, pending
shall stand closed.
__________________ NINALA JAYASURYA, J Date: 24.01.2022
IS
NJS, J W.P.No.2483 of 2019
HON'BLE SRI JUSTICE NINALA JAYASURYA
Writ Petition No.2483 of 2019 Date: 24.01.2022
IS
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!