Citation : 2022 Latest Caselaw 1965 AP
Judgement Date : 22 April, 2022
1
HON'BLE SRI JUSTICE D.V.S.S.SOMAYAJULU
WRIT PETITION No.16394 of 2014
ORDER:
This Court has heard Sri P. Veera Reddy, learned
senior counsel appearing for the petitioner, learned
Government Pleader for Civil Supplies and Sri P. Hema
Chandra, learned standing counsel representing the
respondents 1 to 3-Civil Supplies Corporation.
The petitioners before this court are the legal heirs of
the deceased contractor for the respondent-civil supplies
corporation.
Sri P. Veera Reddy, learned senior counsel for the
petitioners submits that the petitioner was awarded a work of
transportation of food grains for the years 2008-09 and a
contract dated 29.03.2008 was entered into. The learned
senior counsel submits that the petitioner fulfilled all the
statutory contractual conditions by depositing the security
deposit, EMD, bank guarantee etc., and an agreement dated
08.04.2008 was entered into.
On 17.10.2008, 300 bags of food grains, weighing
approximately 14.805 Metric Tons were given for
transportation to the petitioner, engaged a lorry bearing
No.AP 02 T 0546 to transport the same. According to the
learned senior counsel the driver of the lorry diverted the
stocks. Realizing that the lorry did not reach the destination
the petitioner approached the 3rd respondent and also the
police and lodged a complaint. It transpires that the driver
attempted to divert the said stocks, FIR No.85 of 2008 was
registered. In view of the diversion of stocks, the petitioner's
contract was also suspended. Later, the learned senior
counsel points out that the lorry was traced, the driver was
arrested and the law took it's own course. Further, learned
senior counsel points out that the petitioner was not made an
accused in the case. The charge sheet was also filed before
the Judicial First Class Magistrate Court. The 14.795 MTs of
rice, which was tracked and recovered, were handed over to
the respondents. Learned senior counsel also points out that
basing on the orders of the Hon'ble Sessions Judge,
Ananthapur in Criminal Revision Petition No. 28 of 2009 the
seized stock was directed to be handed over to the District
Manager, Civil Supplies, Anantapur for disposal. Accordingly,
the Joint Collector, who is the 2nd respondent herein
permitted the sale of the seized stocks also. It is submitted
that the seized stocks were also directed to be handed over to
various Fair Price Shops pursuant to the proceedings of the
Tahsildar on 31.01.2010. Learned senior counsel, therefore,
submits that the entire stock of diverted rice was brought
back into the system and distributed through the Fair Price
Shops. He, therefore, submits that the respondents did not
sustain any loss whatsoever. Learned senior counsel also
points out that against the action taken by the respondents
against the Contractor-petitioner W.P.No.3268 of 2009 was
also filed. Learned single Judge after considering the facts
noticed that a penalty of recovery Rs.2,66,499/- towards the
double the economic cost of the goods diverted was levied.
While disposing the W.P.No.3268 of 2009 the Court, however,
held that the amount already recovered was the double the
amount of cost of goods diverted is valid recovery as per the
terms of the contract. The other amounts that were withheld
i.e., bank guarantee, security deposit etc., was held to be
disproportionate. Against the orders of the learned single
Judge a Writ Appeals were also filed by the Contractor and
also by the Civil Supplies Corporation. These were numbered
as W.A.Nos.340 and 638 of 2014. By a common order dated
10.04.2014, these Writ Appeals were disposed of. Learned
senior counsel also points out that the order of the learned
trial Judge setting aside the termination of the contract of the
present petitioner was upheld, but the "double penalty" was
upheld. The Division Bench also held that a fresh show
cause notice should be issued to the petitioner and a de novo
inquiry is to be conducted. Accordingly, a show cause notice
was issued on 28.04.2014 pursuant to the orders of the
Division Bench, wherein the issue of the termination of the
contract, forfeiture of the security deposit, bank guarantee
and pending bills was directed to be reconsidered. To the
show cause notice issued the petitioner gave a detailed reply
raising among other issues the fact that no loss is caused to
the Corporation and that all further actions should be
dropped. The contractor cited certain case law also in the
said reply notice and requested the Corporation to release the
bank guarantee, security deposit and also the pending bills.
Learned senior counsel submits that despite the said detailed
reply, the impugned order dated 07.06.2014 was passed.
Learned senior counsel submits that without considering the
reply or the legal and factual issues raised the impugned
order has been passed. Learned senior counsel submits that
the order is bereft of reasons and does not consider the actual
issues that are raised by the present petitioner. He also
submits that in the absence of any loss being caused,
forfeiture of the security deposit, refusal to return the bank
guarantee and also retaining the pending bills, is not called
for. Therefore, learned senior counsel argues that the
amounts pending should be directed to be returned with
interest along with security deposit, bank guarantee etc.
Learned standing counsel, however, argues that the
forfeiture of these amounts is in accordance with the terms of
the contract and after considering the explanation only. It is
submitted that it is an admitted fact that the stocks were
diverted. The record filed by the petitioner himself clearly
established the same, as per the learned standing counsel.
Relying upon the terms of the work order and Clause 3(iii),
the learned standing counsel argues that the petitioner
contractor is responsible for the transportation of the
material. He argues that as per Clause 8 (iv) and (v) of the
agreement the respondents are absolutely justified in the
action taken. Even if there is a diversion of the truck the
petitioner is responsible and the respondents have the right to
terminate the contract, forfeit the security deposit, bank
guarantee and also the pending bills. Learned standing
counsel submits that as per condition 8(iv) the contract and
his representative is responsible in case of diversion of stocks
under the Essential Commodities Act. Learned standing
counsel points out that the contractor is responsible for the
acts of his agents including the truck owner, driver and
cleaner of the truck, in which the stocks are loaded for the
transportation. Relying upon these clauses of agreement,
learned standing counsel argues that the impugned order is
correct and therefore, there is no cause made out for
interference.
COURT:
After examining the submissions made by the learned
senior counsel and the learned standing counsel for
respondents along with record of this case, this Court is of the
opinion that the essential facts are not really in dispute.
Amongst the documents filed by the petitioners, this
Court notices that the letter issued by the Inspector of Police,
which is at page 58, Ex.P.10 of the material documents. As
per this letter the contractor and the owner of the lorry are
not responsible for the actual commission of the offence and it
is the driver of the lorry, who was held to be responsible for
the actual commission of the offence. The proceedings of the
SDPO, Anantapur, show that a direction was granted to delete
the name of the contractor and the owner of the lorry from the
list of accused. Thereafter the seized stock of 300 rice bags
was directed to be handed over to the Manager of the
respondent-corporation, who received the same. In the
charge sheet it is clear that the contractor is an not accused.
Thereafter, pursuant to the proceedings of the Court,
including the revision petition in Crl.R.P.No.28 of 2009 the
seized stocks were directed to be handed over to the District
Manager, Civil Supplies Corporation. The Joint Collector
passed orders to release the stocks, which was seized.
Accordingly, the seized stocks were handed over to the
District Manager, Anantapur, APSCSCL.
By proceedings dated 31.01.2010 the seized stock of
14.795 MTs was handed over for distribution through the Fair
Price Shops. This is evidenced by an order dated 31.01.2010
and the letter of the respondent corporation dated
15.03.2010. Thus, this Court finds the entire stock of 14.795
MTs was disposed through the six fair price shops and an
amount of Rs.29,590/- was realized. Thus, this Court finds
that there is no pecuniary loss caused to the Corporation.
In W.P.No.3268 of 2009 filed by the petitioner, the
deceased 1st petitioner, this aspect was taken note of by the
learned single Judge. The order of termination of the
contractor, which is challenged in the said writ was set aside
by the learned single Judge. Learned single Judge came to
the conclusion that the impugned order visited severe penal
and civil consequences on the contractor. Ultimately, in
paragraph 28 of the order learned single Judge held that the
amount of penalty which was levied i.e., to double the cost of
the amount diverted can be sustained and the contractor has
no claim over the same. The Writ petition was allowed
directing the respondents to issue a fresh show cause notice
for the other part of the claim. This order was again upheld
in the Writ Appeals filed and a fresh show cause notice is
directed to be issued. Accordingly, the show cause notice
dated 28.04.2014 was issued and a detailed reply was given,
running into a few pages.
The contractor very clearly asserted that the diverted
stocks were re-entrusted for disposal and sales through the
PDS system. It is asserted that the entire stock of 14.295
MTs were again utilized by the respondent-corporation and
therefore, there is no loss to the respondent corporation.
Clause 8 (vi) of agreement was held to be not applicable and
the forfeiture of the deposit, bank guarantee etc., is
questioned. Four judgments were also relied upon by the
petitioner contractor in his reply. These are mentioned in
paragraph 21 of the reply notice.
The order in Writ Appeal directed the respondents to
consider the contentions urged and to pass a speaking order
after receiving the reply.
The next issue for consideration is whether the
impugned order is in line with the law on the subject
including the reply of the respondents.
As stated by the learned senior counsel and in line with
the orders in Writ Appeal, the penalty amount of
Rs.2,66,499/- has been held to be due to the respondent-
corporation by the learned single judge and later by the
Division Bench. Any question about the said amount cannot
be reagitated once again. The larger issue is about the recent
order being passed. Time and again the highest courts of the
land have held when a reasoned order is to be passed along
with reasons the same should be ex facie visible from the
reading of the order itself. If the impugned order is examined
against the background of the settled law on the subject with
regard to reasons it is clear that there is no discussion
whatsoever about the issues raised by the contractor in his
reply to the show cause notice. The reply which is filed, from
paragraph 9 onwards, raises the issue of sale of the diverted
stocks and the utilization of the sale proceeds by the
respondent corporation. The Writ Petition No.3268 of 2009
and the order in the Writ Appeal Nos.340 and 638 of 2014 are
discussed in paragraphs 12 and 13 of the reply. In paragraph
15 it is asserted that the entire diverted stock was brought
back into the system and the sale proceeds were also realized
/ utilized. Therefore, it is asserted that there are no damages
/ loss etc., that are sustained by the Corporation. It is stated
in paragraph 15 that no loss is caused to the corporation and
the petitioner is not liable under Clause 8(vi). In paragraph
19 it is again asserted that an amount of Rs.2,66,499/- was
already taken by the Corporation and again the show cause
notice was issued for forfeiting the bank guarantee, security
deposit and pending bills. The law on the subject and the
need for reasons being furnished after considering the reply
are very clear. Reasons are the hallmark of justice. They
show the application of mind (Victoria Memorial Hall v
Howrah Ganatantrik Nagarik Samity 1). The impugned
order in the opinion of this Court does not discuss the issues
raised by the contractor. For the purpose of forfeiture of the
security deposit and the other claims, Clauses 8(iv) and 8(vi)
are to be seen. Under Clause 8(iv) also the Corporation shall
have a right to suspend the contract at any time without
notice, without assigning reasons if the contractor or his
representative is involved in a case of diversion of stocks or
under the Essential Commodities Act or any other Act. Under
the Clause 8 (v) the Corporation has a right to forfeit the
security deposit, bank guarantee and pending bills in the
event of failure or diversion of trucks. Under the Clause 8 (vi)
the Corporation shall have a right to terminate the contract
and to get the work done for the unexpired period of the
contract at the petitioner's risk and cost and forfeit the
security deposit or any part thereof, in addition to claim the
(2010) 3 SCC 732
bank guarantee amount for any damages, loss charges etc.,
that may be suffered by the Corporation. Therefore, this
Court is of the opinion that while the respondent corporation
has a right to suspend the contract or to terminate the same
but it can only forfeit the security deposit for any "loss",
"damages" sustained by the Corporation. Maula Bux v
Union of India2 is the leading case on this issue. In the case
on hand the Corporation has recovered the cost of the rice
diverted by getting the same back into the PDS system
pursuant to the orders of the Joint Collector. The seized
stock was brought back into the system pursuant to the
orders of the Joint Collector and Courts referred to above and
a sum of Rs.2,66,999/- was also recovered from the petitioner
contract. Apart from this, this Court notices that the
respondents did not sustain any monetary loss. This
forfeiture, retention etc., these are in the nature of the
penalty. As per the settled law on the subject the question of
awarding compensation or recovery of compensation will only
arise if there is a "loss". Compensation as per the term
means making good the loss. If no loss is sustained
respondents cannot automatically forfeit the security deposit
or make other claims.
This Court reiterates that rice has already been
brought into the PDS system, and an amount of Rs.2.66
lakhs has already been recovered. This has been upheld by
(1969) 2 SCC 554)
the learned single judge vide its orders dated 26.11.2013 in
W.P.No.3268 of 2009 and in the Writ Appeal Nos.340 and 638
of 2014, any further recovery in the form of forfeiture of the
security deposit, bank guarantee and pending bills would
amount to unjust enrichment. Therefore, this Court holds
that the impugned order suffers from two fundamental flaws.
(1) It does not consider the detailed reply and the case law
and the implications of the case law submitted by the
respondents. (2) The point raised by the contractor that no
loss is caused to the Corporation has not been considered at
all by the respondents. The case law submitted has also not
been considered by the respondents. Therefore, this Court
has no hesitation to hold that the respondents should be
directed to forthwith release the security deposit of
Rs.10,00,000/-, Bank Guarantee of Rs.15,00,000/- and
pending bills of the petitioner along with interest at the rate of
6% per annum from February, 2009 till the date of actual
payment. The respondent Corporation which is an
instrumentality of the State has a duty to act as a model
employer. It cannot enrich itself at the cost of a contractor.
Retention of all these amounts would be contrary to law and
also amount to unjust enrichment.
The contractor's legal heirs are fighting this battle since
long after the contractor expired. The respondent-corporation
did not sustain any loss as a result of the diversion of the
stock. Double the amount of the value of the stock has
already been realized. Therefore, the retention of the other
monies due to the contractor are held to be bad in law.
With the above observation, the Writ Petition is
allowed. There shall be no order as to costs.
Consequently, the Miscellaneous Applications pending,
if any, shall also stand closed.
__________________________ D.V.S.S.SOMAYAJULU, J Date:22.04.2022 Ssv
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!