Citation : 2022 Latest Caselaw 1837 AP
Judgement Date : 19 April, 2022
*HONOURBLE SRI JUSTICE D.V.S.S. SOMAYAJULU
+ W.P.No. 13597 of 2018
% 19.04.2022
#M/s. Sri Sai Investigation & Security Services
Rep., by its Managing Partner
... Petitioner
Vs.
$ Secretary, Ministry of Railways,
Government of India, New Delhi and 2 others.
... Respondents
! Counsel for the petitioner : Sri C.V.Ram Mohan Reddy
! Counsel for the Respondents : Smt. Sasikala, standing counsel for
Railways.
< Gist:
> Head Note:
? Cases referred:
1 (2018) III LLJ 362 Bom
2 W.P.No.2702 of 2018
3 AIR 2003 SC 1216
4 2020 II LLJ 235 Mad
5 1996 SCR (5) Supp.447
6
1994 (3) SCC 521
7 AIR 1960 SC 588
2
HON'BLE SRI JUSTICE D.V.S.S.SOMAYAJULU
W.P.No.13597 of 2018
ORDER :
This writ petition is filed by the petitioner questioning the
termination of two contracts by the respondent-Railways.
This Court has heard Sri C.V.Ram Mohan Reddy, learned
counsel for the petitioner and Smt. Sasikala, learned standing
counsel for the Railways.
Petitioner: Sri C.V.Ram Mohan Reddy, learned counsel for the
petitioner took great pains to argue the matter at length. The
petitioner is a contractor, who was participated in two tenders for
Kakinada and Narsapur for the mechanised cleaning of coaches,
cleaning of depot premises, garbage etc., which was floated by the
respondent-Railways. The date of the tender is 04.07.2016. Tenders
were finalized and letters of acceptance dated 27.12.2016 were issued
for both the works. Formal contracts for both the works were
executed in March 2017. The value of the Kakinada contract was
Rs.3,65,87,811/- and the value of Narsapur contract was
Rs.2,40,19,790/-. Learned counsel for the petitioner points out that
basing on the minimum wages that were prevalent at the time of the
filing of the tender, the petitioner had quoted the rates. However, on
28.04.2017, the minimum wages were revised by 42% with effect from
19.01.2017. Learned counsel submits that the minimum wages
payable to the workers increased from Rs.250/- to Rs.359/- per day
with retrospective effect from 19.01.2017. Learned counsel submits
that this upset the entire planning and the financial basis of the
contract. Learned counsel submits that despite the phenomenal
increase in the rates due to the increase in the minimum wages, the
petitioner did his level best to absorb the loss and also to carry on the
work. He points out that on 09.10.2017, after executing the work for
sometime, the petitioner requested the respondent-Railways to
foreclose the work and also relies upon a letter addressed by the
Deputy Chief Labour Commissioner, Visakhapatnam, who advised the
Railways to enhance the wages or to foreclose the contract since the
wage hike is very high. Learned counsel points out that in reply to
this, the Railways also addressed a letter stating that the foreclosure
of the contract is under process. Learned counsel submits that
despite this assertion, Railways went ahead and terminated the
contract. Questioning the same, the writ petition is filed.
Among other grounds, learned counsel for the petitioner argues
that the responsibility to pay the minimum wages is with the Railways
as the principal employer and that both on grounds of justice and
equity, the contractor should be indemnified and reimbursed for this
extraordinary raise in the wages. He also raises an issue that the
contract was not terminated in accordance with the terms of the
contract. He relies upon a compilation of judgments in support of his
argument which are as follows:
(1) Division Bench judgment of the Bombay High Court in
WP.No.1996 of 2017 in A2Z Infraservices Limited v. Union
of India, Ministry of Railways1.
(2) Judgment of the High Court of Bombay in M/s.
S.K.Enterprises, Through its Proprietor v. The Union of
India, Ministry of Railways2.
1 (2018) III LLJ 362 Bom
(3) Judgment of Supreme Court of India in Government of
Maharashtra v. M/s. Deokar's Distillery3
(4) M/s. Aarthi Enterprises, Rep., by its Partner G.Mythili v.
Southern Railways, rep., by General manager, Senior
Divisional Manager, Divisional Office, Commercial
Branch, southern Railways, Deputy Chief Labour
Commissioner (Central)4.
And also
(5) The order of the Regional Labour Commissioner (Central()
and Authority under Minimum Wages Act, 1948, Hyderabad
in Application No.46/27/2018-E
Learned counsel submits that most of these cases cited relate to
the Railways only. Relying upon the first judgment of the Division
Bench of the Bombay High Court, learned counsel argues that the
Railways are duty bound to neutralize the cost of labour and that the
principle of business efficacy should be pressed into service to
interpret this contract and to grant relief to the petitioner against the
extraordinary wages in the prices.
For respondents: In reply to this, Smt. Sasikala, learned
standing counsel also argues at length. She points out that under the
terms of the agreements, the primary responsibility rests upon the
petitioner to pay the minimum wages. She relies upon clauses 15, 16
and 17 of the letter of intent in both the contracts and also the
clauses 46 to 53 of Chapter III of the agreement to argue that it is the
primary responsibility of the contractor to comply with the statutory
requirements including the payment of minimum wages. Therefore,
3 AIR 2003 SC 1216 4 2020 II LLJ 235 Mad
the learned standing counsel submits that the petitioner cannot avoid
his responsibility of paying the minimum wages. With regard to pre-
closure, learned counsel submits that even the Railways were
interested in pre-closing the agreement, but the same was not an
unconditional agreement. It is pointed out that the petitioner
company was put on notice that the contract would be closed by
mutual agreement, provided the petitioner pays all the statutory
dues to the labour etc. Wages were also to be paid by the
contractor till the pre-closure. However, learned counsel points
out that the petitioner did not pay the said wages leading to
action according to the contract. She relies upon the letters
dated 20.12.2017 issued to the petitioner by the Railways,
wherein four conditions were stipulated. Learned counsel points
out that even thereafter, the petitioner did not pay the wages
and the Labour Enforcement Officer noticed the shortfall in
payment. Ultimately, the learned counsel points out that on
15.02.2018, the Railways address a combined letter in both the
contracts pointing out that as the petitioner failed to pay the
wages, remit the EPF and ESI, the Railways have no other
choice, but to initiate the procedure for termination. She points
out that in both the agreements, seven day notice was issued on
12.02.2018 followed by a 48 hour notice in terms of clause 62
and ultimately the termination orders dated 10.03.2018 and
28.03.2018 were issued terminating the contracts. Therefore,
learned standing counsel argues that as there is a clear breach
of the terms of the contract and violation of the conditions, the
Railways had no option but to terminate the contracts. She
relies upon a judgment of the Hon'ble Supreme Court of India in
the case of Hindustan Steel Works v. The Commissioner of
Labour5 to argue that the employer is not liable to pay the
additional amount and that ultimately, even if the same is paid,
they will have to recover it from the contractor.
COURT: This Court after hearing both the learned counsel,
who took great pains to argue the matter realizes that there is
no dispute essentially on the facts of the case.
The petitioner is a successful tenderer, who was awarded
two works. Letters of acceptance was issued on 27.12.2016 for
Kakinada and on 29.12.2016 for Narsapur. Formal contracts
were concluded on 07.03.2017. In the interim period, the
Government of India has revised the minimum wages with effect
from 19.01.2017.
The first question that arises for the determination is, who
is responsible for the payment of the minimum wages?. The
letters of acceptance issued in the both the contracts are
identical. They resulted in the formation of the contract.
Clauses 15, 16 and 17 of this letters of acceptance, clearly
states that the petitioner is liable for complying with the labour
laws. Of significance, is clause 16, which clearly states that the
petitioner is responsible for payment of minimum wages to the
staff engaged by him. The proof of payment of minimum wages
as witnessed by the Railway Officials should be submitted with
every bill. It is made clear that bill will not be processed unless
5 1996 SCR (5) Supp.447
the proof is submitted for wage payment. The contract
agreement entered into between both the parties is also similar.
Clause 46 of this agreement deals with the "wages to labour". It
clearly states that the contractor shall be responsible to ensure
compliance with the provisions of Minimum Wages Act, 1948.
Even if the Railways is called upon to make the payment to the
workers by virtue of any claim or application made by them, the
Railways have a right to claim the same from the contractor
within 7 days. Railways are also entitled to recover the sum
from any money due or accruing to the contractor under this or
any other contract with the Railways.
Therefore, from a plain language interpretation of the
contract, it is clear that the primary obligation to pay the wages
as per the Minimum Wages Act always rests with the contractor
only. The Railways, as a principal employer, even if they are
called upon to pay any amount by virtue of a claim made by the
workers, can recover the money within 7 days and from any
money due under this contract or other contracts. This clause
also strengthens this Court's conclusions. Therefore, in the
opinion of this Court, there is no doubt that it is the 'contractor'
alone who is liable to pay the minimum wages.
The view that the Railways can recover the money is also
supported by the High Court of Madras judgment reported in
M/s. Aarthi Enterprises case, wherein it was held that in case
the minimum wages are enhanced, the principal employer is
bound to reimburse the same on the petitioner making such
payment to employees. Therefore, if the petitioner proves that
he had in fact paid the enhanced minimum wages and submits
documents as per the contract, the petitioner would be entitled
for reimbursement. In a judgment reported in Tarapore and
Co. v. State of M.P.6, the Hon'ble Supreme Court of India also
held that as the contractor was bound to pay the minimum
wages and to follow the labour laws, there was an 'implied
contract' to reimburse the increased payment made by the
contractor on account of the raise in wages.
In the case on hand, the stand of the Railways is that the
petitioner has failed to pay the wages and this has lead to the
cancellation of the contract. The letters of contemporaneous
period dealing with the issue are filed by both the parties. The
petitioner addressed a letter dated 09.10.2017, wherein he
assured the Railways that in view of the heavy burden, the
contract should be foreclosed and they would be paying all the
pending statutory dues till the date of pre-closure. On
12.12.2017, the Railways addressed a letter to the Labour
Enforcement Officer stating that in his inspection report he
noticed that the present petitioner failed to comply with the
payment of minimum wages. With the counter affidavit, the
respondents are also filed letter dated 20.10.2017 addressed to
the petitioner in both the works. It was clarified that the
petitioner had failed to pay the wages as per the latest revision,
did not remit the PF and ESI and also pointed out about the
1994 (3) SCC 521
non-issuance of pay slips etc. It is agreed to pre-close the
agreement with four conditions of which, the most important in
this case is that the contractor shall in fact pay arrears of wages.
On 29.12.2017, Railways in fact addressed a letter to the Labour
Enforcement Officer pointing out that they are withholding a
sum of Rs.6.10 lacks on account of the failure of petitioner to
pay wages at Kakinada. This was followed by letter dated
05.02.2018 wherein the Railways clearly informed the petitioner
that pre-closure is only possible on mutually agreed terms and
that the request of increase in wages is not possible as per the
agreement. Thereafter, it was categorically informed that in view
of the failure of the petitioner to pay minimum wages, the
Railways had no option, but to terminate the contracts. Thus, it
is clear that there is no consensus on the aspect of pre-closure.
Any variation in the terms of the contract can only be by mutual
consent. If the Railways imposed certain conditions for the pre-
closure and requested the petitioner to pay minimum wages till
the closure, the petitioner could demand for pre-closure if he
adheres to the conditions. Since he did not do so, in the opinion
of this Court, the petitioner cannot rely on the issue of pre-
closure of agreement.
As decided in the leading judgment of Alopi Parshad and
Sons Ltd. vs. Union of India7, contractors are often faced with
a rise in prices or changed circumstances during the course of
the execution of the work. This by itself will not give them an
7 AIR 1960 SC 588
option to walk out the contract and will not also permit the
Court to ignore the settled terms of contract. This leading
judgment, in the opinion of this Court, is squarely applicable to
the facts and circumstances of this case. Merely because the
performance becomes more onerous the petitioner cannot avoid
the same. The terms of the agreement are crystal clear and the
petitioner is under an obligation to pay the wages. If the
principal employer-Railways is called upon to pay the wages,
they will recover it from the money due to the petitioner. There
is no escalation clause in this contract also for the petitioner to
claim the increase of wages. Therefore, in the opinion of this
Court, the petitioner was duty bound to pay the minimum wages
and thereafter seek reimbursement by submitting clear proper
and adequate proof in terms of the agreement. Without doing
so, he cannot absolve himself of his responsibility.
The next question that survives for consideration is about
termination of the contract. As mentioned earlier, there is no
consensus on the terms for the pre-closure. The letters
addressed by the respondents clearly show that the wages were
not being paid to the labour-workmen. Certain amounts and
details are also highlighted in the counter affidavit filed which
are not controverted. Thereafter, this Court notices that the
respondents have given the seven day notice followed by a 48
hour notice as per clause 55 and then ultimately terminated the
contract. The procedure stipulated under the contract was
followed in the opinion of this Court.
Lastly, the submission of the learned counsel about the
interpretation of the contract to give business efficacy needs to
be answered. The learned counsel relied upon the Division
Bench judgment in A2Z Infraservices Limited (1 supra). This
judgment also clearly states that the terms of contract are
always final. It was held in para 26 that the business efficacy
test can only be applied in cases where the term that is sought
to be read as a term intended by the parties. The Bombay High
Court found that the Railways in that case also followed the
same principle and granted price variation to the contractor till
18.01.2017 and thereafter the Railways refused to give the
benefit to the contractor when the wages were escalated. There
was also a price variation clause. In these circumstances, the
Bombay High Court held that by applying the principle of
business efficacy, the minimum wages are to be increased. It
was held that as long as the contract is subsisting, the Railways
are bound to reimburse the contract.
In the opinion of this Court, the terms of the present
contract are crystal clear. Relevant clauses in the letters of
acceptance and the general conditions are extracted earlier. By
a process of interpretation, this Court cannot make out a new
contract for the parties. Once the terms of the agreed contract
are clear, and the contract does not suffer from any infirmity or
ambiguity, this Court cannot rely on the 'business efficacy' test
to bring in an implied term. This would amount to doing
violence to the clear written terms of the contract. Besides, this
is a matter of clear pleading which is lacking in this case.
Primary responsibility rests with the petitioner. He failed to
discharge his statutory obligation. This led to the termination.
Therefore, in the opinion of this Court, the petitioner is not
entitled to any relief.
The writ petition is therefore dismissed. No order as to
costs. As a sequel, the miscellaneous petitions, pending if any,
shall stand closed.
________________________ D.V.S.S.SOMAYAJULU,J
Date : 19.04.2022 Note: L.R. copy be marked.
KLP
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!